PROJECT
Crash Cost
Two main important things in doing crash cost (rule
of thumb!)
○ Normal Costs
○ Crash Costs
a - 6 5 60 90 30/d
b - 7 4 50 150 33/d
d a 7 7 30 30 N.A.
e b 5 4 70 85 15/d
f c 9 7 40 120 40/d
g d, e 7 4 50 230 60/d
6 12
c 6
0 6 12 21
6 12
a 6 f 9
6 13
12 21
Finish
0 6 d 7
Start
13 20
0 7 7 14 g 7
b 7 7 12
e 5 14 21
2 9
9 14
6 12
c 6
0 6 12 21
6 12
a 6 f 9
6 13
12 21
Finish
0 6 d 7
Start
13 20
0 7 7 14 g 7
b 7 7 12
e 5 14 21
2 9
9 14
a - 6 5 60 90 30/d
b - 7 4 50 150 33/d
d a 7 7 30 30 N.A.
e b 5 4 70 85 15/d
f c 9 7 40 120 40/d
g d, e 7 4 50 230 60/d
Finish
0 5 d 7
Start
12 19
0 7 6 13 g 7
b 7 7 12
e 5 13 20
1 8
8 13
a - 6 5 60 90 30/d
b - 7 4 50 150 33/d
d a 7 7 30 30 N.A.
e b 5 4 70 85 15/d
f c 9 7 40 120 40/d
g d, e 7 4 50 230 60/d
Finish
0 6 d 7
Start
13 20
0 7 7 14 g 7
b 7 7 12
e 5 14 21
2 9
9 14 Original AON
Modified AON
❑Let say, crash ‘c’ by two days that will cost $60
❑ But by crashing ‘c’, ‘a’ will remain 6 days, ‘d’ – 7 days
and ‘g’ – 7 days that total 20 days (new critical path)
Finish
0 5 d 7
Start
12 19
0 7 5 12 g 7
b 7 7 12
e 5 12 19
0 7
7 12
○ Crash 1 day at task a, as before.
○ Another 1 day:
• May choose a or f, but ‘a’ was crash to maximum 1 day.
• This lead to the only choice by crash the ‘f’
• Then, the extra cost will be $30 + $40 = $70
a - 6 5 (1) 60 90 30/d
d a 7 7 (0) 30 30 N.A.
e b 5 4 (1) 70 85 15/d
6 12
c 6
0 6 12 21
6 12
a 6 f 9
6 13
12 21
Finish
0 6 d 7
Start
13 20
0 7 7 14 g 7
b 7 7 12
e 5 14 21
2 9
9 14
Original AON
Finish
0 5 d 7
Start
12 18
0 7 5 12 g 6
b 7 7 12
e 5 12 18
0 7
7 12
Finish
0 5 d 7
Start
12 17
0 7 5 12 g 5
b 7 7 12
e 5 12 17
0 7
7 12
• This could be done by crashing activity ‘f’ and ‘g’ for another day (from
crashed to 18 days)
• New project cost = $400 + $30 (a) + $60 (2c) + $40 (f) + $120 (2g) =
$650
Management for Engineers
Crash for 16 days
5 9
c 4
0 5 9 16
5 9
a 5 f 7
5 12
9 16
Finish
0 5 d 7
Start
12 16
0 7 5 12 g 4
b 7 7 12
e 5 12 16
0 7
7 12
• The only choise is to crash activity ‘f’ and ‘g’ for another day
• New project cost = $400 + $30 (a) + $60 (2c)+ $80 (2f) + $180 (3g)=
$750
Management for Engineers
Project Cost Versus Project Duration for Sample Crash
Problem
Table 3.1
○ Develop an AON network and find the critical path, critical time and cost for an all-normal
level of project activity.
○ Suggest the optimal way of getting a 40-day delivery time. What is the project cost?
○ Deduce the shortest path delivery time for the project. What is the cost and duration of the
project?
Table 3.1
Table 3.1
Activity Predecessor Normal Normal Crash Crash Cost Total crash Cost per day
Time Cost (RM) Time (RM) days
a - 15 20,000 12 26,000 3 2,000
b - 10 35,000 8 45,000 2 5,000
c b 12 17,000 8 21,000 4 1,000
d a,c 5 5,500 - -
e a,c 18 26,200 14 31,000 4 1,200
f b 24 105,000 20 117,000 4 3,000
g d 15 15,000 12 17,100 3 700
h e,f 6 12,000 - -
○ Develop an AON network and find the critical path, critical time and cost for an all-normal level of
project activity.
• Answer , Critical path = b-c-eh, duration = 46 days, cost = RM 235, 700
○ Suggest the optimal way of getting a 40-day delivery time. What is the project cost?
• Crash c to 4 days, crash e to 2 days,
• cost = 235, 700 + 4,000 + 2, 400 = RM 242,100
○ Deduce the shortest path delivery time for the project. What is the cost and duration of the
project?
• 36 days
• Crash b= 2 days, c = 4 days, e = 4 days , f = 2 days
• 235700 + 10000+ 4000 + 4800 + 6000 = RM 260,500