Professional Documents
Culture Documents
Ammonia Team
Page 1
Fertial Arzew Plant1, Arzew, Algeria
Catalyst Performance Evaluation
Ammonia Team
INTRODUCTION
The starting point for analysis of a plant data-set is a calculation of a theoretical heat and
mass balance from the plant data provided. Using the calculated theoretical heat and mass
balance, the difference between measured and theoretical process parameters is
determined. These differences are used to calculate standard errors based on the expected
error in any particular measurement. The plant data, if necessary, are then varied to
minimise the root mean square (RMS) error to obtain an overall best fit to the theoretical
heat and mass balance. It is the calculated ‘best fit’ data which are used to comment upon
the actual plant data (flows and analysis) and the calculated approach to equilibrium (ATE)
for each catalyst.
The CATPER catalyst evaluation program, which is Johnson Matthey proprietary simulates
the main process units of ammonia plants and has been developed over the years to meet
the needs of plant operators to assess plant operation and characterise catalyst
performance.
During the fitting calculation, CATPER sums the adjustments to each measurement into a
root mean square (RMS) value. The RMS value is a measure of the total amount of
adjustment necessary to give consistency with the model, and is a measure of the quality of
the plant data. In general, the lower the RMS value, the better the fit between the measured
and calculated values. An RMS value of less than 0.5 is regarded as a good fit, i.e. most
measurements lie within their 95% confidence limits. An RMS less than 1.0 is regarded as a
reasonable fit and an RMS of greater than 1.0 indicates a poor fit.
The calculated Root Mean Square Error (RMS Error) for 10th Feb 2010 dataset is 0.881
indicating a reasonable fit to the measured data.
We have used Johnson Matthey proprietary programs ‘SHIFT’ and ‘AMMCON’ to evaluate
the performance of HT and LT shift converters and also ammonia converter based on the
calculated results of ‘CATPER’.
Plant rate is reported to be 730 TPD against design 1000 TPD. Reason of such low
throughput is not known to us.
PRIMARY REFORMER 13m3 S-C G90-LDP and 13m3 S-C G91, Installed May 2009
Date Time on line S/C* Exit Temp* Exit CH4* ATE Delta P
Years (Ratio) (°C) (%) (°C) (bar)
10 Feb. 10 0.75 4.02/4.28 760/765 8.35 / 9.19 0 2.7
* Measured/Calculated
In general good agreement between measured and calculated parameter have been
achieved however and as can be seen from above table calculated inlet steam carbon ratio
is marginally higher than measured value while exit CH4 slip is higher than reported one.
Catalyst tubes pressure difference is 2.7 bar however normalized pressure drop should be
considered as an indication of catalyst performance in conjunction with CH4 slip.
Page 2
Fertial Arzew Plant1, Arzew, Algeria
Catalyst Performance Evaluation
Ammonia Team
As can be seen Pressure drop is proportional to second power of flow, in other words if 730
TPD can be considered as if reformer exit flow is 73% of design reformer exit flow then
reported pressure drop is equivalent to 5.07 bar. Fertial is asked to investigate this matter.
Having high inlet S/C ratio, high CH4 slip and pressure drop can potentially be an indication
of catalyst poor performance and insufficient activity which is likely to cause carbon
formation in the hottest parts of tubes.
It is recommended to keep a close eye on the performance of the primary reforming catalyst
and in particular reformer tubes wall temperature and appearances.
Hot banding, giraffe necking, tiger tailing and hot tubes are totally unwanted phenomenon
and will cause tubes short service life and failure. It should be noted that visible hot bands
tubes are typically operating at least 20 to 40ºC above design temperature.
To prevent hot bands and hot spotting in the tubes, methods of preventing carbon formation
are:
• Use more active catalyst
• Use better heat transfer catalyst
• Reduce levels of higher hydrocarbons
• Increase the steam ratio
• Use promoted catalyst (e.g. KATALCOJM 25-4Q) that reduces probability of carbon
formation
• Use UNIDENSE loading technique for an even distribution of catalysts across the
tubes.
Page 3
Fertial Arzew Plant1, Arzew, Algeria
Catalyst Performance Evaluation
Ammonia Team
With good catalyst activity and high degree of carbon resistance the catalyst life can be
around 6-8 years while with poor catalyst activity and high degree of carbon resistance the
catalyst life can be around 3-4 years, making the catalyst cost double per year.
However a more significant cost is from unplanned tube failures plant downtime, most plants
such as Fertial Arzew have no means of isolating a leak e.g. by pigtail nipping so furnace
cool down, repair and restart for a single tube failure may typically take 3-5 days so lost
product sales may be €2 to 3 M, also a unplanned tube failure normally causes damage to
adjacent tubes
Page 4
Fertial Arzew Plant1, Arzew, Algeria
Catalyst Performance Evaluation
Ammonia Team
Performance of any water gas shift catalyst can be assessed by CO slip and pressure drop
out of the bed in conjunction with inlet condition and in particular steam/dry gas ratio. As per
CATPER results exit CO is very good however pressure drop has not been reported.
To have a more sensible understanding for the performance of this HTS catalyst we have
used Johnson Matthey proprietary software ‘SHIFT’ result of which for temperature rise and
CO gradient are plotted in following figures.
420
400
Temperature
380
360
340
0 20 40 60 80 100
%of bed depth
Page 5
Fertial Arzew Plant1, Arzew, Algeria
Catalyst Performance Evaluation
Ammonia Team
12.00
10.00
CO dry mol%
8.00
6.00
4.00
2.00
0.00
0 20 40 60 80 100
%of bed depth
Following table shows exit condition of HTS based on ‘SHIFT’ output and ‘CATPER’ output.
As can be seen from CO and CO2 compositions this catalyst charge is not performing as
expected. Reason of having such a low CO is having a very high steam/carbon ratio at
primary reformer inlet.
There’s a good agreement between measured and calculated results however catalyst
performance should be evaluated by kinetic basis software such as ‘SHIFT’ therefore same
HTS we have used Johnson Matthey proprietary software ‘SHIFT’ for this purpose.
Page 6
Fertial Arzew Plant1, Arzew, Algeria
Catalyst Performance Evaluation
Ammonia Team
210.0
208.0
206.0
Temperature
204.0
202.0
200.0
198.0
196.0
194.0
0 20 40 60 80 100
%of bed depth
2.50
2.00
CO dry mol%
1.50
1.00
0.50
0.00
0 20 40 60 80 100 120
%of bed depth
Expected exit conditions at the exit of LTS catalyst bed and also fitted plant data are shown
below:
Page 7
Fertial Arzew Plant1, Arzew, Algeria
Catalyst Performance Evaluation
Ammonia Team
Good agreement between measured gas analyses inlet and exit the methanator and
calculated data is observed. Observed temperature rise is also in good agreement with the
calculated value.
This catalyst is performing well and reaction completes in one third of the bed however
pressure drop not been mentioned
16.00
14.00
12.00
NH3 Concentration
10.00
8.00
6.00
4.00
2.00
0.00
320.0 370.0 420.0 470.0 520.0 570.0 620.0 670.0
Temperature (C)
Page 8
Fertial Arzew Plant1, Arzew, Algeria
Catalyst Performance Evaluation
Ammonia Team
As can be seen from above figure ammonia synthesis converter is not performing well.
Operating line is expected to be around max rate curve and close to equilibrium curve at the
exit of each bed.
Approach to equilibrium at the exit of each bed is shown in the following table:
Bed 1 2 3
ATE (oC) 109 47.2 59
Bed 1 2 3
Contribution% 29.88 37.36 32.76
To show the performance of KATALCOJM 35-8 and KATALCOJM 35-4 in a modern ammonia
converter with double age of Fertial (7.6 vs 3.5 year) following operating line and contribution
which were achieved.
18.00
16.00
14.00
12.00
NH3 mole%
10.00
8.00
6.00
4.00
2.00
0.00
350.0 400.0 450.0 500.0 550.0 600.0 650.0 700.0 750.0
Temperature (C)
Page 9
Fertial Arzew Plant1, Arzew, Algeria
Catalyst Performance Evaluation
Ammonia Team
I hope you find this report useful but should you have any comments it would be very
welcome.
Please do not hesitate to contact us in case you have any technical query.
Best Regards
Reza Ebadi
Page 10
Fertial Arzew Plant1, Arzew, Algeria
Catalyst Performance Evaluation
Ammonia Team
DATAFIT RESULTS
NG Recycle
H2 % 0.00 74.34
N2 % 5.44 24.60
CH4 % 83.48 0.76
Ar % 0.00 0.30
CO % 0.00 0.00
CO2 % 0.21 0.00
C2H6 % 7.85 0.00
C3H8 % 2.10 0.00
C4H10 % 0.92 0.00
C5H12 % 0.00 0.00
Measured Calculated
value value
PRIMARY REFORMER
Present YES
Catalyst #1 type G90 EW
Catalyst #1 volume m3 13.0
Catalyst #2 type G90 LDP
Catalyst #2 volume m3 13.0
Installation date 01-May-2009
Time online days 285.
Measured Calculated
value value
Page 11
Fertial Arzew Plant1, Arzew, Algeria
Catalyst Performance Evaluation
Ammonia Team
SECONDARY REFORMER
Present YES
Catalyst #1 type C 14-2
Catalyst #1 volume m3 26.4
Catalyst #2 type
Catalyst #2 volume m3 0.0
Catalyst #3 type
Catalyst #3 volume m3 0.0
Installation date 01-Feb-2008
Time online days 740.
Reference exit wet gas flow Nm3/hr 181503.3
Measured Calculated
value value
Page 12
Fertial Arzew Plant1, Arzew, Algeria
Catalyst Performance Evaluation
Ammonia Team
HTSHIFT
Present YES
Catalyst #1 type G 3C
Catalyst #1 volume m3 78.0
Installation date 01-Aug-2006
Time online days 1289.
Reference exit wet gas flow Nm3/hr 181503.3
Measured Calculated
value value
Page 13
Fertial Arzew Plant1, Arzew, Algeria
Catalyst Performance Evaluation
Ammonia Team
LTSHIFT
Present YES
Catalyst #1 type C 18 AMT
Catalyst #1 volume m3 71.4
Installation date 01-Aug-2006
Time online days 1289.
Reference exit wet gas flow Nm3/hr 181503.3
Measured Calculated
value value
Page 14
Fertial Arzew Plant1, Arzew, Algeria
Catalyst Performance Evaluation
Ammonia Team
CO2 REMOVAL
Present YES
Measured Calculated
value value
METHANATOR
Present YES
Catalyst #1 type C14-4-04
Catalyst #1 volume m3 19.0
Installation date 01-Aug-2008
Time online days 558.
Reference exit wet gas flow Nm3/hr 91566.8
Measured Calculated
value value
Page 15
Fertial Arzew Plant1, Arzew, Algeria
Catalyst Performance Evaluation
Ammonia Team
Measured Calculated
value value
Page 16
Fertial Arzew Plant1, Arzew, Algeria