UEI/OMMSI/GE/100123 v 2 Page 2 of 18
Test Specification
1. INTRODUCTION
1.1 OVERVIEW
This Test Specification is to verify and validate the functional configuration of the 2
x 265 Kw Generators located on the Zahara Desert Camp, Bidiya site and their
combined functionality in respect of the Synchronisation panel.
The aim of the tests is to show:
(a) That the synchronisation panel and generators is operating as expected
under normal working conditions.
(b) That the Synchronisation and generators will operate correctly in an
emergency/redundancy scenario
(c) That the Synchronisation and generators will operate in a load sharing
capacity.
See Figure 2 -1
The synchronisation tests will include
(a) The 265 KW Generator – D.G.1
(b) The 265 KW Generator – D.G.2
(c) Synchronisation Panel
(d) Electrical Load Simulator
UEI/OMMSI/GE/100123 v 2 Page 3 of 18
Test Specification
2. TEST CASES
UEI/OMMSI/GE/100123 v 2 Page 4 of 18
Test Specification
Test Data
Provide details of the test data to be used. This may take the form of a
description or a link.
UEI/OMMSI/GE/100123 v 2 Page 5 of 18
Test Specification
UEI/OMMSI/GE/100123 v 2 Page 6 of 18
Test Specification
3 Gensets G1 and G2 are connected to the Both generators are operating Connected as stated and no load PASS
Synchronisation panel. On no load. Load Bank is in sync
connected to the outgoing breaker of the Sync
Panel
4 Apply load on both synchronisation panel via load Both generators to run in sync
bank to the value of 66 KW in total (25%) and load share (half load on
______ KW load on simulator
each Genset)
Load & voltages are:
Note: load on each Genset
UEI/OMMSI/GE/100123 v 2 Page 7 of 18
Test Specification
UEI/OMMSI/GE/100123 v 2 Page 8 of 18
Test Specification
7 Genset G1 is powered down and Genset G2 is Genset G2 is running on load Load & voltages are:
operating to a load of 198 KW. (75%) 198 KW without power
G1= _____ KW
interruption
G2= ____ KW
Note : Load on Genset G2
Voltage on 3 phase to be 415
V 3-phase volts = ____ V ___Hz
Voltage on single phase to be Single phase volts = ______V
240 V
8 With G2 still set to 198 KW, Genset G1 has power Genset G1 should Simulated load was 198 KW
restored synchronise and load share
with Genset G2. Half load so Load & voltages are:
that: G1= 99 KW
G1= 99 KW G2= 99 KW
G2= 99 KW 3-phase volts = ____ v ___Hz
Voltage on 3 phase to be 415 Single phase volts =239-240 v
V
Voltage on single phase to be
240 V
Note load on each Genset
and voltages
9 Genset G2 is powered down and Genset G1 is Genset G1 is running on load Load & voltages are:
operating to a load of 198 KW. (75%) 198 KW without power
G1= _____ KW
interruption
Note load on Genset G1 and
Voltages 3-phase volts =____ v ___ Hz
UEI/OMMSI/GE/100123 v 2 Page 9 of 18
Test Specification
Set sync panel so that it is on AUTO Sync Parameter is set to 185 3-phase volts = ____V,___Hz
KW
Power down Genset G1 Single phase volts =______V
UEI/OMMSI/GE/100123 v 2 Page 10 of 18
Test Specification
14 Genset G2 is powered down. The load is increase The synchronisation panel Load & voltages are:
on Genset G1 to 185 KW (70%) automatically starts Genset 2 G1=_________ KW
and distributes the load over
the two generators. The load G2= __________ KW
across the two generators is 3-phase volts =___ V, ___ Hz
evenly distributed.
Single phase volts = _____V
G1= 92 KW
G2= 92 KW
Voltage on 3 phase to be 415
V
Voltage on single phase to be
240 V
Note load on each Genset
and voltages
UEI/OMMSI/GE/100123 v 2 Page 11 of 18
Test Specification
16 Reduce KW load on synchronisation panel to Genset G1 has the total load Load & voltages are: PASS
below 132 KW (50%) of 132 KW
G1= ____ KW
Genset G2 is automatically
G2= _____ KW
shut down after a time of 5
minutes to dormant state and 3-phase volts =____V,___ Hz
has no load
Single phase volts =____V
UEI/OMMSI/GE/100123 v 2 Page 12 of 18
Test Specification
21 Extra Test using Load Simulator At 24:01 G2 should start and G2 started and had ___ KW load,
G1 should shut down G1 shut down
G2 is set to be Master on a Saturday.
The time should be set to 23:55 on Friday with G1
having a load of 132KW
UEI/OMMSI/GE/100123 v 2 Page 13 of 18
Test Specification
23 Extra Test using Load Simulator G2 shuts down and G1 is the G2 shut down
running as Master with a load
G1 set to Master, Load on Sync Panel is 183 KW, G1 = _____KW
of 132 KW
both Gensets are running. Load is then reduced to
132 KW
24 Power down both generators & disconnect Load No load on the As stated PASS
Bank. synchronisation panel
Power cables from Sync Panel to be connected to
the Two DB (TTTF & PMO)
26 Gensets are powered up and are operating as per Both buildings are being Both buildings were being PASS
their correct specifications. powered from the powered and in sync
synchronisation panel.
Loads on generators,
synchronisation panel are
within normal specifications
and each share half the total
load
UEI/OMMSI/GE/100123 v 2 Page 14 of 18
Test Specification
UEI/OMMSI/GE/100123 v 2 Page 15 of 18
Test Specification
UEI/OMMSI/GE/100123 v 2 Page 16 of 18
Test Specification
UEI/OMMSI/GE/100123 v 2 Page 17 of 18
Test Specification
UEI/OMMSI/GE/100123 v 2 Page 18 of 18