LPG/OPS/002

INDIAN OIL CORPORATION LIMITED Test Report 2525


INDANE BOTTLING PLANT, SITAPURA JAIPUR Page No. 01
TEST REPORT FOR THERMAL OVERLOAD RELAY
Frequency - Yearly Test Date :19/09/2021 TO 25/09/2022
S. NO. ERTK100/2K20/08/0011 Next Due Date : 18/09/2022
Make - ENERZIO
CALIBRATION CERT NO & VALIDITY: ERTK100/2K20/08/0011[ 29.08.2022]
S/No. Feeder Name KW Relay Relay Range Relay Current Response Remar
Rating make Setting Applied time ks
(A)

1 DU-1 2.2 kw L&T 4.5 to 7.5 4.5 14 35 ok


2 DU-2 2.2 kw L&T 4.5 to 7.5 4.5 10 45 ok
3 DU-3 3.7 kw L&T 6 to 10 7.5 9 41 ok
4 DU-4 3.7 kw L&T 6 to 10 7.5 14 18 ok
5 DU-5 5.5 kw L&T 9 to 15 11 16 39 ok
6 DU-6 5.5 kw L&T 9 to 15 11 14 29 ok
7 DU-7 5.5 kw L&T 9 to 15 11 18 28 ok
8 DU-8 5.5 kw L&T 9 to 15 11 14 25 ok
9 DU-9 2.2 kw L&T 4.5 to 7.5 4.5 11 24 ok
10 DU-10 5.5 kw L&T 9 to 15 11 16 21 ok
11 DU-12 2.2 kw L&T 4.5 to 7.5 4.5 11 20 ok
12 DU-13 5.5 KW L&T 9 to 15 11 14 29 ok
13 DU-14 5.5 kw L&T 9 to 15 11 18 21 ok
14 DU-15 3.7 kw L&T 6 to 10 7.5 9 41 ok
15 DU-16 2.2 kw L&T 4.5 to 7.5 4.5 11 28 ok
16 DU-11 3.7 kw L&T 9 to 15 7.5 14 28 ok
17 DU-19 2.2 kw L&T 4.5 to 7.5 4.5 13 24 ok
18 DU-20 3.7 kw L&T 6 to 10 7.5 17 40 ok
19 DU-21 2.2 kw L&T 4.5 to 7.5 4.5 12 34 ok
20 DU-22 5.5 kw L&T 9 to 15 11 12 40 ok
21 DU-23 5.5 kw L&T 9 to 15 11 12 34 ok
22 DU-24 5.5 kw L&T 9 to 15 11 13 39 ok
23 DU-25 5.5 kw L&T 9 to 15 11 12 38 ok
24 DU-26 2.2 kw L&T 4.5 to 7.5 4.5 11 41 ok

Note : Permit system as per OISD-105 revised to be followed.


* If external Agency/ Contractor is carrying out the testing.

Testing Agency: TEJA POWER TECH


License No: 9672A
Lic. Validity: 17/06/2029

IOCL Representative
Seal & Signature Name & Designation
LPG/OPS/002
INDIAN OIL CORPORATION LIMITED Test Report 2525
INDANE BOTTLING PLANT SITAPURA JAIPUR Page No. 02
TEST REPORT FOR THERMAL OVERLOAD RELAY
Frequency - Yearly Test Date :19/09/2021 TO 25/09/2021
S. NO. ERTK100/2K20/08/0011 Next Due Date : 18/09/2022
Make - ENERZIO
CALIBRATION CERT NO & VALIDITY: ERTK100/2K20/08/0011[ 29.08.2022]
S/No. Feeder Name KW Rating Relay Relay Relay Current Response Remarks
make Range Setting Applied time (sec)
(A)

25 DU-27 3.7 kw L&T 6 to 10 7.5 14 40 ok


26 DU-28 3.7 kw L&T 6 to 10 7.5 14 41 ok
27 DU-29 5.5 kw L&T 9 to 15 11 15 39 ok
28 DU-30 3.7 kw L&T 6 to 10 7.5 11 40 ok
29 DU-31 3.7 kw L&T 4.5 to 7.5 7.5 11 50 ok
30 DU-32 3.7 kw L&T 4.5 to 7.5 7.5 14 45 ok
31 DU-33 2.2 kw L&T 4.5 to 7.5 4.5 8 36 ok
32 DU-35 2.2 kw L&T 4.5 to 7.5 4.5 8 40 ok
33 DU-36 3.7 kw L&T 4.5 to 7.5 7.5 14 38 ok
34 DU-37 2.2 kw L&T 4.5 to 7.5 4.5 9 35 ok
35 DU-38 2.2 kw L&T 4.5 to 7.5 4.5 8 38 ok
36 DU-39 2.2 kw L&T 4.5 to 7.5 4.5 14 38 ok
37 DU-40 5.5 kw L&T 9 to 15 11 14 39 ok
38 DU-41 2.2 kw L&T 4.5 to 7.5 4.5 9 39 ok
39 Unloading boom 1 2.2 kw L&T 4.5 to 7.5 4.5 9 36 ok
40 Unloading boom 2 2.2 kw L&T 4.5 to 7.5 4.5 10 33 ok
41 Unloading boom 3 2.2 kw L&T 4.5 to 7.5 4.5 9 35 ok
42 Unloading boom 4 2.2 kw L&T 4.5 to 7.5 4.5 9 35 ok
43 Unloading boom 5 2.2 kw L&T 4.5 to 7.5 4.5 14 31 ok
44 Unloading conveyor 1 2.2 kw L&T 4.5 to 7.5 4.5 8 35 ok
45 Unloading conveyor 2 2.2 kw L&T 4.5 to 7.5 4.5 7 36 ok
46 Unloading conveyor 3 2.2 kw L&T 4.5 to 7.5 4.5 8 35 ok
47 Unloading conveyor 4 2.2 kw L&T 4.5 to 7.5 4.5 18 39 ok
48 Unloading conveyor 5 2.2 kw L&T 4.5 to 7.5 4.5 10 39 ok

Note : Permit system as per OISD-105 revised to be followed.


* If external Agency/ Contractor is carrying out the testing.

Testing Agency: TEJA POWER TECH


License No: 9672A
Lic. Validity: 17/06/2029

IOCL Representative
Seal & Signature Name & Designation
LPG/OPS/002
INDIAN OIL CORPORATION LIMITED Test Report 2525
INDANE BOTTLING PLANT SITAPURA JAIPUR Page No. 03
TEST REPORT FOR THERMAL OVERLOAD RELAY
Frequency - Yearly Test Date :19/09/2021 TO 25/09/2021
S. NO. ERTK100/2K20/08/0011 Next Due Date : 18/09/2022
Make - ENERZIO
CALIBRATION CERT NO & VALIDITY: ERTK100/2K20/08/0011[ 29.08.2022]
S/No. Feeder Name KW Rating Relay Relay Relay Current Response Remarks
make Range Setting Applied time (sec)
(A)

49 Loading Boom 1 2.2 kw L&T 4.5 to 7.5 4.5 12 24 ok


50 Loading Boom 2 2.2 kw L&T 4.5 to 7.5 4.5 12 25 ok
51 Loading Boom 3 2.2 kw L&T 4.5 to 7.5 4.5 9 23 ok
52 Loading Boom 4 2.2 kw L&T 4.5 to 7.5 4.5 14 21 ok
53 Loading conveyor 1 2.2 kw L&T 4.5 to 7.5 4.5 11 29 ok
54 Loading conveyor 2 2.2 kw L&T 4.5 to 7.5 4.5 11 28 ok
55 Loading conveyor 3 2.2 kw L&T 4.5 to 7.5 4.5 9 30 ok
56 Loading conveyor 4 2.2 kw L&T 4.5 to 7.5 4.5 14 35 ok
57 Nano cut 2.2 kw L&T 4.5 to 7.5 4.5 8 51 ok
58 Valve change M/c Stp 2.2 kw L&T 4.5 to 7.5 4.5 9 29 ok
59 Vapour Blower 1 15 kw L&T 20 to 33 30 40 44 ok
60 Vapour Blower 2 15 kw L&T 20 to 33 30 41 39 ok
61 Purging Unit 1.5 kw L&T 3 to 5 3 11 35 ok
62 STP comp Old 11 kw L&T 20 to 33 21 25 34 ok
63 Drying Unit 2 2.2 kw L&T 4.5 to 7.5 4.5 9 28 ok
64 Drying Unit 1 2.2 kw L&T 4.5 to 7.5 4.5 14 29 ok
65 STP Blower Old 3.7 kw L&T 4.5 to 7.5 4.5 8 32 ok
66 EVAC Comp 5.5 kw L&T 4.5 to 7.5 4.5 8 31 ok
67 STP Water Old p/m 3.7 kw L&T 9 to 15 11 16 31 ok
68 Valve change M/c 1 3.0 kw L&T 9 to 15 11 18 59 ok
69 Cap Unit 2.2 kw L&T 4.5 to 7.5 7.5 10 51 ok
70 Footrim repair m/c 3.7 kw L&T 4.5 to 7.5 6 10 29 ok
71 Test Bath 1 2.2 kw L&T 4.5 to 7.5 4.5 11 28 ok
72 Test Bath 2 2.2 kw L&T 4.5 to 7.5 7.5 14 25 ok

Note : Permit system as per OISD-105 revised to be followed.


* If external Agency/ Contractor is carrying out the testing.

Testing Agency: TEJA POWER TECH


License No: 9672A
Lic. Validity: 17/06/2029

IOCL Representative
Seal & Signature Name & Designation
LPG/OPS/002
INDIAN OIL CORPORATION LIMITED Test Report 2525
INDANE BOTTLING PLANT SITAPURA JAIPUR Page No. 04
TEST REPORT FOR THERMAL OVERLOAD RELAY
Frequency - Yearly Test Date :19/09/2021 TO 25/09/2021
S. NO. ERTK100/2K20/08/0011 Next Due Date : 18/09/2022
Make - ENERZIO
CALIBRATION CERT NO & VALIDITY: ERTK100/2K20/08/0011[ 29.08.2022]
S/No. Feeder Name KW Rating Relay Relay Relay Current Response Remarks
make Range Setting Applied time (sec)
(A)

73 Valve Change M/c 3.0 kw L&T 4.5 to 7.5 6 14 40 ok


74 Washing Unit 3 3.7 kw L&T 4.5 to 7.5 7.5 13 31 ok
75 Washing Unit 4 3.7 kw L&T 4.5 to 7.5 7.5 13 34 ok
76 Carousal 1 2.2 kw L&T 4.5 to 7.5 4.5 10 65 ok
77 Carousal 2 2.2 kw L&T 4.5 to 7.5 6 12 62 ok
78 STP SWP Old 0.75 Kw L&T 4.5 to 7.5 11 10 39 ok
79 DU 17 3.7 kw L&T 4.5 to 7.5 7.5 11 48 ok
80 Air Comp House s. w 1 5.5 kw L&T 9 to 15 11 11 48 ok
81 Air Comp SW 2 5.5 kw L&T 9 to 15 11 12 49 ok
82 Air Comp 1 45 KW L&T 30 to 50 47 60 79 ok
83 Air Comp 2 45 KW L&T 30 to 50 47 78 85 ok
84 VFD 1 55 Kw L&T 66 to 110 94 98 75 ok
85 VFD 2 45 Kw L&T 66 to 110 94 96 69 ok
86 VFD 3 45 KW L&T 66 to 110 94 95 71 ok
87 Jockey pump 1 18.5 kw L&T 20 to 33 21 40 65 ok
88 Jockey pump 2 18.5 kw L&T 20 to 33 21 45 71 ok
89 Security Air Comp 1 5.5 kw L&T 9 to 15 11 18 40 ok
90 Security Air Comp 2 5.5 kw L&T 9 to 15 11 15 39 ok
91 HSD Pump 1 0.75 Kw L&T 1.4 TO 2.3 1.5 6 35 ok
92 HSD Pump 2 0.75 Kw L&T 1.4 TO 2.3 1.5 6 29 ok
93 Bottling Pump 1 75 kw L&T 66 to 110 94 96 74 ok
94 Bottling Pump 2 45 Kw L&T 30 to 50 47 59 79 ok

Note : Permit system as per OISD-105 revised to be followed.


* If external Agency/ Contractor is carrying out the testing.

Testing Agency: TEJA POWER TECH


License No: 9672A
Lic. Validity: 17/06/2029

IOCL Representative
Seal & Signature Name & Designation
LPG/OPS/002
INDIAN OIL CORPORATION LIMITED Test Report 2525
INDANE BOTTLING PLANT SITAPURA JAIPUR Page No. 05
TEST REPORT FOR THERMAL OVERLOAD RELAY
Frequency - Yearly Test Date :19/09/2021 TO 25/09/2021
S. NO. ERTK100/2K20/08/0011 Next Due Date : 18/09/2022
Make - ENERZIO
CALIBRATION CERT NO & VALIDITY: ERTK100/2K20/08/0011[ 29.08.2022]
S/No. Feeder Name KW Relay Relay Relay Current Response Remarks
Rating make Range Setting Applied time (sec)
(A)

95 Loading Pump 1 75 kw L&T 66 to 110 87 90 59 ok


96 Loading Pump 2 37 kw L&T 30 to 50 40 56 64 ok
97 LPG Comp 1 30 kw L&T 20 to 33 22 35 56 ok
98 LPG Comp 2 30 kw L&T 20 to 33 22 36 41 ok
99 LPG Comp 3 18.5 kw L&T 20 to 33 36 49 65 ok
100 LPG P/H sw (1) 3.7 kw L&T 4.5 to 7.5 7.5 11 39 ok
101 LPG P/H sw (2) 3.7 kw L&T 4.5 to 7.5 7.5 15 49 ok
102 DU -101 2.2 kw L&T 4.5 to 7.5 4.5 15 39 ok
103 DU -102 2.2 kw L&T 4.5 to 7.5 4.5 14 54 ok
104 DU-103 3.7 kw L&T 4.5 to 7.5 7.5 13 54 ok
105 DU-104 3.7 kw L&T 4.5 to 7.5 7.5 12 58 ok
106 DU-105 2.2 kw L&T 4.5 to 7.5 4.5 13 51 ok
107 DU-106 2.2 kw L&T 4.5 to 7.5 4.5 14 49 ok
108 DU-107 3.7 kw L&T 4.5 to 7.5 7.5 16 41 ok
109 DU-108 3.7 kw L&T 4.5 to 7.5 7.5 14 35 ok
110 DU-109 1.5 kw L&T 1.4 to 3 3 6 24 ok
111 DU-110 3.7 kw L&T 4.5 to 7.5 7.5 19 31 ok
112 DU-111 3.7 kw L&T 4.5 to 7.5 7.5 14 56 ok
113 DU-112 2.2 kw L&T 4.5 to 7.5 4.5 9 41 ok
114 DU-113 3.7 kw L&T 4.5 to 7.5 7.5 14 47 ok
115 DU-114 2.2 kw L&T 4.5 to 7.5 4.5 9 29 ok
116 DU-115 3.7 kw L&T 4.5 to 7.5 7.5 14 51 ok

Note : Permit system as per OISD-105 revised to be followed.


* If external Agency/ Contractor is carrying out the testing.

Testing Agency: TEJA POWER TECH


License No: 9672A
Lic. Validity: 17/06/2029

IOCL Representative
Seal & Signature Name & Designation
LPG/OPS/002
INDIAN OIL CORPORATION LIMITED Test Report 2525
INDANE BOTTLING PLANT SITAPURA JAIPUR Page No. 06
TEST REPORT FOR THERMAL OVERLOAD RELAY
Frequency - Yearly Test Date :19/09/2021 TO 25/09/2021
S. NO. ERTK100/2K20/08/0011 Next Due Date : 18/09/2022
Make - ENERZIO
CALIBRATION CERT NO & VALIDITY: ERTK100/2K20/08/0011[ 29.08.2022]
S/No. Feeder Name KW Rating Relay Relay Relay Current Response Remarks
make Range Setting Applied time (sec)
(A)

117 DU-116 2.2 kw L&T 4.5 to 7.5 4.5 11 34 ok


118 DU-117 5.5 kw L&T 9 to 15 11 16 46 ok
119 DU-118 2.2 kw L&T 4.5 to 7.5 4.5 8 35 ok
120 DU-119 3.7 kw L&T 4.5 to 7.5 7.5 12 25 ok
121 DU-120 5.5 kw L&T 9 to 15 11 16 29 ok
122 DU-121 5.5 kw L&T 9 to 15 11 18 41 ok
123 DU-122 2.2 kw L&T 4.5 to 7.5 4.5 9 29 ok
124 DU-123 3.7 kw L&T 4.5 to 7.5 7.5 14 35 ok
125 DU-124 2.2 kw L&T 4.5 to 7.5 4.5 16 41 ok
126 DU-125 2.2 kw L&T 4.5 to 7.5 4.5 15 45 ok
127 DU-126 3.7 kw L&T 4.5 to 7.5 7.5 15 47 ok
128 DU-127 2.2 kw L&T 4.5 to 7.5 4.5 14 25 ok
129 Loading shed boom 5 2.2 kw L&T 4.5 to 7.5 4.5 16 64 ok
130 Loading shed convyer 5 3.7KW L&T 4.5 to 7.5 7.5 14 61 ok
131 STP Water Motor 1 0.75 kw L&T 1.4 to 3 1.5 6 39 ok
132 STP Degassing 3.7 kw L&T 4.5 to 7.5 7.5 9 37 ok
133 Vapour Blower 3 7.5 kw L&T 9 to 15 15 26 41 ok
134 Vapour Blower 4 7.5 kw L&T 9 to 15 15 25 51 ok
135 Air comp STP 15 KW L&T 20 to 33 30 38 35 ok
136 HYP Pump 1.5 kw L&T 1.4 to 3 1.5 10 25 ok
137 Hydraulic Pump 1.5 kw L&T 1.4 to 3 1.5 11 24 ok
138 Low Pressure Pump 1.5 kw L&T 1.4 to 3 1.5 10 26 ok

Note : Permit system as per OISD-105 revised to be followed.


* If external Agency/ Contractor is carrying out the testing.

Testing Agency: TEJA POWER TECH


License No: 9672A
Lic. Validity: 17/06/2029

IOCL Representative
Seal & Signature Name & Designation
LPG/OPS/002
INDIAN OIL CORPORATION LIMITED Test Report 2025
INDANE BOTTLING PLANT SITAPURA JAIPUR Page No. 07
TEST REPORT FOR THERMAL OVERLOAD RELAY
Frequency - Yearly Test Date :19/09/2021 TO 25/09/2021
S. NO. ERTK100/2K20/08/0011 Next Due Date : 18/09/2022
Make - ENERZIO
CALIBRATION CERT NO & VALIDITY: ERTK100/2K20/08/0011[ 29.08.2022]
S/No. Feeder Name KW Rating Relay Relay Relay Current Response Remarks
make Range Setting Applied time (sec)
(A)

139 STP Blower 3 3.7 kw L&T 4.5 to 7.5 4.5 11 35 ok


140 STP Water Pump 3 0.75 Kw L&T 1.4 to 3 11 16 39 ok
141 Value Change M/c 2 2.2 kw L&T 4.5 to 7.5 4.5 9 28 ok
142 STP Blower 2 3.7 kw L&T 4.5 to 7.5 7.5 14 37 ok
143 STP Water Motor 2 0.75 Kw L&T 1.4 to 3 11 16 35 ok
144 New STP Blower 1 3.7 kw L&T 4.5 to 7.5 11 14 34 ok
145 Vision Conveyor 2 2.2 kw L&T 4.5 to 7.5 4.5 9 28 ok
146 Valve Change M/c 3.7 kw L&T 4.5 to 7.5 7.5 14 39 ok
147 ETP Plant 5.5 kw L&T 9 to 15 11 16 42 ok
148 LPG PUMP 3 55KW L&T 45 TO 75 63 80 37 ok

Note : Permit system as per OISD-105 revised to be followed.


* If external Agency/ Contractor is carrying out the testing.

Testing Agency: TEJA POWER TECH


License No: 9672A
Lic. Validity: 17/06/2029

IOCL Representative
Seal & Signature Name & Designation