Professional Documents
Culture Documents
The following
information was recorded by the company for October:
Additional information:
• stocks of raw materials and finished goods are valued at standard cost;
• during the month the actual number of units produced was 1550;
• the actual sales revenue was £12 000;
• the direct materials purchased were 1000 kg.
Required:
(a) Calculate
(i) the actual sales volume;
(ii) the actual quantity of materials used;
(iii) the actual direct material cost;
(iv) the actual direct labour hours;
(v) the actual direct labour cost;
(vi) the actual variable overhead cost;
(vii) the actual fixed overhead cost. (19 marks)
(b) Explain the possible causes of the direct materials usage variance, direct
labour rate variance and sales volume variance. (6 marks)
CIMA Operational Cost Accounting Stage 2
Answer:
17.16
(a) Sales price variance = (actual margin – budgeted margin) x actual sales volume
(£17 – £12) x 8 200 = £41 000 Favourable
(Answer = (ii))
Note that fixed overhead rate per unit is £4 (£34 800/8 700)
(b) Sales volume = (actual sales volume – budgeted sales volume) x Standard
margin
(8 200 – 8 700) x £12 = 6 000 Adverse
(Answer = (i))
17.18
(a) (i) A fixed overhead volume variance only occurs with an absorption costing system.
The question indicates that a volume variance has been reported. Therefore the
company must operate an absorption costing system and report the sales volume
variance in terms of profit margins, rather than contribution margins.
Budgeted profit margin = budgeted profit (£4 250)/budgeted volume (1 500 units) = £2.83
(ii) Standard quantity of material used per units of output: budgeted usage (750 kg)/
budgeted production (1 500 units) = 0.5 kg
Standard price = budgeted material cost (£4 500)/budgeted usage (750 kg) = £6
Material usage variance = (standard quantity – actual quantity) standard price
£150A = (1550 x 0.5 kg = 775 kg - AQ)
£6 - £150 = 4 650 - 6AQ
6AQ = 4 800
Actual quantity used = 800 kg
(iii) Material price variance = (standard price – actual price) x actual purchases
£1 000F = (£6 - actual price) x 1 000 kg
£1 000F = £6 000 - 1 000AP
1 000AP = £5 000
AP = £5 per kg
Actual material cost = 1 000 kg x £5 = £5 000
(iv) Standard wage rate = budgeted labour cost (£4 500)/budgeted hours (1 125) = £4
Labour efficiency variance = (standard hours – actual hours) x standard rate
£150A =(1 550 x 0.75 = 1 162.5 – actual hours) x £4 – £150 = £4 650 – 4AH
4AH = £4 800
Actual hours = 1 200
Answer:
17.18
(v) Total labour variance = standard cost – actual cost
(£200A + £150A) = (1 550 x 0.75 hrs x £4) – Actual cost
£350A = £4 650 - actual cost
Actual cost = £5 000