Answer these question first and the formulas will be calculated for you.

What is the project budget? 250,000


How complete is the project? 60%
How complete should the project be? 75%
How much has the project spent? $165,000

Budget at completion 250,000


Actual costs 165,000
Earned value 150,000
Planned value 187,500
Cost variance -15,000
Schedule variance -37500
Cost performance index 0.91
Schedule performance index 0.80
Estimate at completion 275,000
Estimate to complete 110,000
To-complete performance index (BAC) 1.18
To-complete performance index (EAC) 0.91
Variance at completion -25,000
Indexes

1.00
0.90
0.80
0.70
Cost performance
0.60 index
0.50 Schedule performance
index
0.40
0.30
0.20
0.10
0.00

Variances

-5000

-10000

-15000
Cost variance
-20000 Schedule variance

-25000

-30000

-35000

-40000