Professional Documents
Culture Documents
On each period (e.g. month), The following values are either computed or assessed by
the Project Manager:
Total Baseline Cost: Computed by summing up all the values of scope items in
scope. Generally stable until budget Change Requests are added.
Typically only costs for services are included, unless other costs are relevant.
By default set as equal to last period in future periods.
Total Earned Cost: Computed by summing up the values of scope items weighted
by corresponding percentage of completion in the period.
By default set as equal to last period in future periods.
Percentage of Completion: Computed as a ratio between Total Earned Cost and
Total Baseline Cost, in the period.
Total Contract Value: Manual input; usually stable until budget CR occurs.
Total Earned Revenue: Computed by applying the percentage of completion to the
Total Contract Value.
By default set as equal to last period in future periods.
Actual Costs: Manual input; typically only costs for services are included, unless
other costs are relevant.
These costs should be of the same type of costs used to define the baseline costs
above.
Computed EAC: Estimate at Completion computed by assuming the same efficiency
applies in future periods, therefore it is computed by means of Actual Costs and
Percentage of Completion.
By default set as equal to last period in future periods.
70,000
60,000
50,000
Total Baseline Co
Computed EAC
Total Earned Rev
40,000 Total Earned Co
Actual Cost
30,000
20,000
10,000
0
M 10
M1
M2
M4
M8
M 11
M 12
M3
M5
M6
M7
M9
s Progress based on Costs
80,000
70,000
60,000
50,000
Total Baseline Cost
Computed EAC
Total Earned Revenue
40,000
Total Earned Cost
Actual Cost
30,000
20,000
10,000
M 11
M 12
M1
M3
M4
M5
M6
M7
M8
M9
M 10
M2
d on Costs
M 12
M9
M 10