Mean Strength of 04
Individual Test Average of (Average - Non overlapping
Date of Date of 28 Standard
Sl. No. Pile No. Results Test Results Individual)= X2 Consecutive Test
Casting days deviation
(N/mm2) (N/mm2) X Result (N/mm2)
43.64 37.74 -5.90 34.86 1.6
103 40CR 18.08.17 15.09.17 38.36 37.74 -0.62 0.38 1.6 38.13
107 240CR 19.08.17 16.09.17 37.51 37.74 0.23 0.05 1.6 38.11
111 234CR 19.08.17 16.09.17 35.87 37.74 1.87 3.51 1.6 36.01
115 237CR 20.08.17 17.09.17 36.71 37.74 1.03 1.06 1.6 36.59
119 231CR 21.08.17 18.09.17 37.16 37.74 0.58 0.34 1.6 36.53
123 222CR 22.08.17 19.09.17 35.33 37.74 2.41 5.79 1.6 35.59
127 39CR 23.08.17 20.09.17 36.13 37.74 1.61 2.58 1.6 36.18
135 P178MT 25.08.17 22.09.17 36.40 37.74 1.34 1.80 1.6 36.17
139 P179MT 26.08.17 23.09.17 37.16 37.74 0.58 0.34 1.6 36.68
143 249CR 26.08.17 23.09.17 37.47 37.74 0.27 0.07 1.6 37.00
147 P182MT 28.08.17 25.09.17 37.38 37.74 0.36 0.13 1.6 36.80
151 01CR 28.08.17 25.09.17 35.96 37.74 1.78 3.18 1.6 36.17
155 18CR 29.08.17 26.09.17 35.02 37.74 2.72 7.39 1.6 35.77
159 P181MT 30.08.17 27.09.17 37.91 37.74 -0.17 0.03 1.6 36.62
163 319CR 30.08.17 27.09.17 36.76 37.74 0.98 0.97 1.6 36.21
167 322CR 31.08.17 28.09.17 37.02 37.74 0.72 0.52 1.6 36.98
171 P229MT 01.09.17 29.09.17 35.87 37.74 1.87 3.51 1.6 36.48
The concrete is deemed to comply with compressive strength requirements when both the conditions as per table of 11 of IS:456 are met.
a) The mean strength determine from any group of four consecutive test result ≥fck +0.825 X establised standard deviation or fck + 4N/mm² whichever is greater. Eg. Concrete cubes
results from Sl no. 1 to 4 average is 42.06 N/mm² ≥ (30 + 4 ) = 34 N/mm² Therefore first criteria is met.
b) Any individual test result ≥fck - 4N/mm². Individual concrete cubes test results from Sl.No. 1 to 174 are >(30-4)=26 N/mm².
Hence the concrete test result mentioned from SL Nos. 1 to 174 are accepted.