SCHEDULE YOUR PROJECT USING

Md. Aliullah Sujan


PMP, B.Sc. In EEE

Executive, Project Coordination & Procurement


Rahimafrooz Renewable Energy Limited

www.linkedin.com/in/aliullahsujan

www.facebook.com/aliullahsujan
• Download & Install ORACLE Primavera P6 • Sequence Activities
• Setting up User Preference & Admin Preference • Assign Resources
• Create OBS & EPS • Assign Expenses
Topics • Create Project Calendar • Lock project baseline
• Create your own project • Activity Network Diagram
• Create WBS • Report Gantt Chart View
• Add Activities to WBS
Download & Install ORACLE Primavera P6

✓ Web search: https://edelivery.oracle.com/ ✓ Unzip and run setup file


✓ Sign Up – Create your own ORACLE account ✓ Select Typical and install
✓ Verify Email ✓ Run database configuration
✓ Sign in ✓ Driver type – P6 Pro standalone SQLite
✓ Search for Primavera P6 Professional Project Management ✓ Set Password
✓ Select latest version and add to cart ✓ Load sample data – checked
✓ Download latest version
Setting up User Preference & Admin Preference

Edit > User Preference Admin > Admin Preference


Create OBS & EPS

Enterprise > OBS Enterprise > Enterprise Project Structure


Create Your Own Project

✓ Select EPS
✓ Enter Project ID and Project Name
✓ Planned start date
✓ Identify responsible manager
✓ Finish and create project
Create Project Calendar

✓ Add project calendar


✓ Modify calendar
✓ Work week, work hour, time period

Enterprise > Calendar


Create WBS

Add WBS
Add Activities and Sequence Activities

Add Activities
Assign predecessor / successor
Original duration
Schedule
Add Resources & Expenses

Add resources > ID & Name > Type > Unit/time > set calendar
Gantt Chart view
That’s all !
Happy Learning !