Professional Documents
Culture Documents
Name of the Project : Composite works at PTA Unit for Capacity Meeting No. :- 02
Expansion of PX & PTA Project Date of Meeting : 23.12.2021
IOCL Panipat Time : 10:30 AM to 12:00 PM
Location of Meeting : L&T Porta Cabin – IOCL
/Worley Site Panipat
MEMBERS PRESENT
6 Waste material and scrap area not identified L&T RCM 17-12-2021 Completed
Electrical cable route not in properly and its laid Site Engg. /
7 Supervisor 10-12-2021 Completed
on ground in haphazard manner
Site walkway areas not clear due to spread of Site Engg. /
8 Supervisor 10-12-2021 Completed
material
Inspection of tools and tackles needs to be done
9 HSE Team In Progress Completed
as per the monthly activity Plan schedule
Earthing not provide in Db and site porta cabin / Site Engg. /
10 09-12-2021 Completed
Office Supervisor
Access and egress route to be define and no Site Engg. /
11 Immediate Completed
unwanted material staking should be permitted Supervisor
12 Fire point not found near of main panel HSE Team 10-12-2021 Completed
Site Engg. /
13 Drip tray not available in the bottom of DG. 10-12-2021 Completed
Supervisor
Site Engg. /
14 Welding machine body earthing was missing 09-12-2021 Completed
Supervisor
Welding short cable was found in damaged Site Engg. /
15 Immediate Completed
condition Supervisor
Load chart was not displayed in P&C operator Site Engg. /
16 10-12-2021 Completed
cabin Supervisor
Blasting Shed upper support tied by nylon rope
Site Engg. /
17 and also J-hook missing from shed sheet and 15-12-2021 Completed
Supervisor
store area.
Site Engg. /
18 PTW Box Not available at site 10-12-2021 Completed
Supervisor
Site Engg. /
19 Whip check was missing in air hosepipe joint. 10-12-2021 Completed
Supervisor
Electrician not present at site cooling tower Site Engg. /
20 Immediate Completed
waterline work area. Supervisor