A. CONSULTANT’S ORGANIZATION
A.1 Introduction
Kunhwa Engineering & Consulting Co., Ltd. (KUNHWA) in joint venture with PT. Indra
Karya (Persero), PT. Aditya Engineering Consultant. formed an excellent project team of
experts for Engineering Services for Bangka Island Flood Management in Bangka Belitung
Province. Also the local associated consulting firms, [PT.Indra Karya (Persero)]., will support
to the project team for optimum project execution condition. The Kunhwa’s JV experts with
local partner are selected among a pool of Professional Engineers, and the best suited and
experienced professional staff will be assigned to the consulting services to promote the
economic development of Indonesia and its surrounding region and the improvement of the
quality of life of the local residents.
A.2.1 Leading Firm: Kunhwa Engineering & Consulting Co., Ltd. (KUNHWA)
KUNHWA in the spirit of progress has been a dynamic and innovative firm since its foundation
in 1990. We are now internationally recognized as a top engineering and consulting company
based on outstanding project track record, our advanced engineering system, and our
expertise.
For three (3) decades of providing engineering and consulting services, KUNHWA has
successfully carried out more than 6,000 projects involving F/S, Engineering Design and
Construction Supervision.
Especially, in the field of Road and Highway, KUNHWA is a leading engineering company in
Korea.
KUNHWA has been consistently ranked in the annual survey listings of Engineering News
Record (ENR Record). In 2020, KUNHWA is listed at position 144 in the just released ranking
of ‘The Top 225 International Design Firms’.
Moreover, KUNHWA has well-organized project management and project support system
defined within the framework of KUNHWA’s quality management system certified with
international standard: ISO 9001 (Quality systems Model for Quality Assurance), ISO 14001
(Environmental Management Systems) and VE (Value Engineering for Road). Also KUNHWA
is registered in EDCF (Korea Exim Bank) and KOICA, ADB (Asian Development Bank),
IBRD/IDA (World Bank), AfDB (African Development Bank), EBRD (European Bank for
Reconstruction and Development) as Consultant.
TECH 2-1
Bangka Island Flood Management in
Bangka Belitung Province
TECH-2 Loan Agreement Number: Loan EDCF INA-22
Organizational Chart
TECH 2-2
Bangka Island Flood Management in
Bangka Belitung Province
TECH-2 Loan Agreement Number: Loan EDCF INA-22
As an important preliminary step, PT. Indra Karya (Persero) focuses its business in electric
power and water resources development. The success in achieving the initial goals, has
encouraged PT. Indra Karya (Persero) to expand the fields, such as : Buildings and Factories,
Transportation (Toll Roads, Bridges, Ports, Airports, Train Facilities/Infrastructure/LRT,
Community Empowerment, Public Housing, Sanitation, Water Waste and Drainage, Regional
Development, Industrial Development/Specific Areas in line with current development market
segment in Indonesia.
PT.Indra Karya (Persero) has been succeeded in completing all the contract assignments
handled professionally both as Independent Company or as Joint Venture Lead Firms. This
achievement can not be separated from the support of human resources of the company PT.
Indra Karya Persero also has its own land laboratory, integrated planning studio, integrated
online project implementation monitoring system (EKPP), ISO 9001:20 15, OHSAS 18001 :
2007 as welI as backup support for professionals in their fields to foster a second opinion
cultureon products produced by PT. Indra Karya (Persero).
In the next five years, PT. Indra Karya (Persero) has a plan to strengthen and diversify the
business into an EXPANDED CONSULTANTS, specifically the expansion of the water and
energy resources business(upstream-mid-downstream), thus PT. Indra Karya (Persero) will
become Engineering, Developer and Industry at the same time. Engineering activities as an
upstream part, will continue to handle the consulting work that has been energy, carried out
so far. Developer activities as part of the center will act as a developer of reservoirs / ponds /
situ for the management of clean water, wastewater, energy and tourism. Industrial activities
as a downstream part run an industrialization business, namely bottled drinking water (AMDK)
that already has a trademark called INFRESH, this industry provides clean water from river
water sources, reservoirs, ground water, sea water to supply the needs of the Special Area.
PT. Indra Karya has been entrusted to carry out A Large Scale Engineering Projects with high
technology as Lead Firm Consultants Association for IBRD finances projects (Central Java
Transmission & Substantion also Musi HE PP Project) and ADB (HEPP Tanggari II and
Sengguruh HPP).
TECH 2-3
Bangka Island Flood Management in
Bangka Belitung Province
TECH-2 Loan Agreement Number: Loan EDCF INA-22
Organizational Chart
The activities of the Company deal with a lot of water resources project in almost all provinces in
Indonesia with the Company's Branches currently in several provincial capitals, namely:
A. Sumatera Region
Aceh Province
Riau Islands Province
TECH 2-4
Bangka Island Flood Management in
Bangka Belitung Province
TECH-2 Loan Agreement Number: Loan EDCF INA-22
TECH 2-5
Bangka Island Flood Management in
Bangka Belitung Province
TECH-2 Loan Agreement Number: Loan EDCF INA-22
Commissioner
President Director
Information:
1. Commissioner : Dewi Evianne
2. President Director : Herryan Kendra Kaharudin
3. Engineering Director : Budi Anton
: Taufiq
: Andica Brawijaya
: Ima Mirayani
: Eri Yanwari Hikmawan
: Muchlis Anshary
4. Head of Division : Each Field
5. Head of Branches : Each Province
TECH 2-6
Bangka Island Flood Management in
Bangka Belitung Province
TECH-2 Loan Agreement Number: Loan EDCF INA-22
B. CONSULTANT’S EXPERIENCE
B.1 Consultant’s Experience
B.1.1 Leading Firm: Kunhwa Engineering & Consulting Co., Ltd. (KUNHWA)
Name of consulting services: Approximate value of the contract
(in current US$):
Country: Duration of the consulting services
Location within country: (months):
Name of the Employer: Approximate value of the services provided by
your firm under the contract (in current US$):
Start date (month/year): Completion Name of senior professional staff of your firm
date (month/year): involved and functions performed (indicate most
Duration of the consulting services significant profiles such as Project Manager,
(months): Project Coordinate, Team Leader):
TECH 2-7
Bangka Island Flood Management in
Bangka Belitung Province
TECH-2 Loan Agreement Number: Loan EDCF INA-22
TECH 2-8
Bangka Island Flood Management in
Bangka Belitung Province
TECH-2 Loan Agreement Number: Loan EDCF INA-22
Werken as Flood Control and utilization in Ngawi Regency, Bojonegoro, Lamongan, Gresik
Description of actual services provided by your staff within the consulting services:
Secondary data collection
Preparation and Measurement Results of the Situation in the Field
Geological Investigations and Soil Mechanics
Calculation of Hydrological and Hydraulic Analysis
River Management Planning
Making Basic Design Planning
Cost forecast analysis and economic analysis
Start date (month/year): 23/6/2014 Name of senior professional staff of your firm
Completion date (month/year): involved and functions performed (indicate most
19/12/2014 significant profiles such as Project Manager,
Duration of the consulting services Project Coordinate, Team Leader):
(months): 6 months Project Manager: Ferdinandus Baskoro H. S. W,
Certificate of Minutes of Work Handover: ST
01/BASTP/RMPPB/XII/2014
Name of associated Consultants, if any: Role of
the contract (leading or just partner)
Leading – PT. Ika Adya Perkasa (70%)
Partner – PT. Indra Karya (30%)
Narrative description of Project: The Purpose of the Review of the Master Plan for Flood Control
and Management in Samarinda City area is the production of a document that can provide a
reference comprehensively on the condition of the problem
Description of actual services provided by your staff within the consulting services:
Secondary data collection
Ground Control Point Job
Performing Hydrological Analysis
Unmanned Aerial/Drone Shooting
Aerial Photo/Photogrammetry Data Processing
Photo Map Making
Creation of DSM, DEM and Contours
Image interpretation and digitization
Field Identification and Completeness Survey
Making Spatial Thematic Maps
Database Compilation
Technical Base Map Cartography and Photo Map
Map Album printing
TECH 2-9
Bangka Island Flood Management in
Bangka Belitung Province
TECH-2 Loan Agreement Number: Loan EDCF INA-22
TECH 2-10
Bangka Island Flood Management in
Bangka Belitung Province
TECH-2 Loan Agreement Number: Loan EDCF INA-22
Start date (month/year): 1/4/2014 Name of senior professional staff of your firm
Completion date (month/year): involved and functions performed (indicate most
26/11/2014 significant profiles such as Project Manager,
Duration of the consulting services Project Coordinate, Team Leader):
(months): 8 months Project Manager: Gagah Guntur Ariwibowo, ST
Certificate of Minutes of Work Handover:
IK.02.04-AS/BAST/SAT.BWS-NT.I/SPK-
PP/2254/2014
Name of associated Consultants, if any: Role of
the contract (leading or just partner)
PT. Indra Karya
Narrative description of Project: The Purpose of Detail Design West Divertion Canal at West
Lombok Regency is to get a detailed design so that the canal can function properly and can
control the flood
Description of actual services provided by your staff within the consulting services:
Making detail design of canal
Performing Hydrological Analysis
Secondary data collection
Ground Control Point Job
Unmanned Aerial/Drone Shooting
Aerial Photo/Photogrammetry Data Processing
Photo Map Making
Creation of DSM, DEM and Contours
Image interpretation and digitization
Field Identification and Completeness Survey
Making Spatial Thematic Maps
Database Compilation
Technical Base Map Cartography and Photo Map
TECH 2-11
Bangka Island Flood Management in
Bangka Belitung Province
TECH-2 Loan Agreement Number: Loan EDCF INA-22
TECH 2-12
Bangka Island Flood Management in
Bangka Belitung Province
TECH-2 Loan Agreement Number: Loan EDCF INA-22
DED, Model Test and Design Certification of Kusan Dam is located in Tanah Bumbu Regency,
South Kalimantan. The main objective of this project is to control floods, generate power and
source bulk water. The project will be implemented on 2017, 2018, 2019
Description of actual services provided by your staff within the consulting services:
Making detailed engineering design for Kusan Dam
Assess existing information/data and determine information gaps that need to be collected;
Carry out necessary topographic and other surveys as may be required;
Undertake hydrometric and hydrological surveys;
Update/confirm water balance/allocation model as needed to assess sustainable yield in the
sub basin
Carry out geological and geotechnical investigations;
Carry out simulations of dam operations;
Update/prepare the detailed engineering designs (DED) (complete in all respect including,
but not limited to, all drawings, technical specifications, bills of quantities (BOQs) and
method of measurement, and other documents, etc.);
Assess land requirements and prepare the land acquisition and resettlement (LARAP)
documents;
Carry out environment impact assessment and prepare AMDAL documents and facilitate
the approval process;
Testing the model and certificating the design of Kusan Dam.
TECH 2-13
Bangka Island Flood Management in
Bangka Belitung Province
TECH-2 Loan Agreement Number: Loan EDCF INA-22
The objective of the Urgent Disaster Reduction Project for Mount Merapi and Lower Progo
River Area (II), IP-566 is to urgently protect Mt. Merapi and the lower Progo River areas against
volcanic sediment flows which occurred much massively and frequently after the 2010 eruption
by providing both hard and soft urgent countermeasures including construction of diversion
channel and sand pocket.
Description of actual services provided by your staff within the consulting services:
Preparation
Preliminary Planning Inventory
Topographic Situation Measurement
Conducting Geological Engineering Investigations and Soil Mechanics
Performing Hydrological Analysis
Preparation of System Planning
Conducting Social, Economic and Environmental Conservation Studies
Calculation of Bill of Quantity (BOQ) and Engineer Estimate (EE)
Preparation of Technical Specifications and Implementation Method
TECH 2-14
Bangka Island Flood Management in
Bangka Belitung Province
TECH-2 Loan Agreement Number: Loan EDCF INA-22
TECH 2-15
Bangka Island Flood Management in
Bangka Belitung Province
TECH-2 Loan Agreement Number: Loan EDCF INA-22
TECH 2-16
Bangka Island Flood Management in
Bangka Belitung Province
TECH-2 Loan Agreement Number: Loan EDCF INA-22
TECH 2-17
Bangka Island Flood Management in
Bangka Belitung Province
TECH-2 Loan Agreement Number: Loan EDCF INA-22
TECH 2-18
Bangka Island Flood Management in
Bangka Belitung Province
TECH-2 Loan Agreement Number: Loan EDCF INA-22
TECH 2-19
Bangka Island Flood Management in
Bangka Belitung Province
TECH-2 Loan Agreement Number: Loan EDCF INA-22
TECH 2-20
Bangka Island Flood Management in
Bangka Belitung Province
TECH-2 Loan Agreement Number: Loan EDCF INA-22
TECH 2-21
Bangka Island Flood Management in
Bangka Belitung Province
TECH-2 Loan Agreement Number: Loan EDCF INA-22
TECH 2-22
Bangka Island Flood Management in
Bangka Belitung Province
TECH-2 Loan Agreement Number: Loan EDCF INA-22
TECH 2-23