Professional Documents
Culture Documents
Project Management: Exercise 1
Project Management: Exercise 1
Exercise 1:
A project consists of a series of tasks labeled A, B, ...................., H, I with the following
relationships (W< X means X can't start until W is completed)
(A < D, E), (B, D < F), (C < G), (B < H), (F, G < I)
a) Draw the network diagram (AOA) of the project.
b) Develop the Gantt chart for project scheduling.
c) Determine the critical path of the project if the time in days of completion of each task is
as follows:
Task A B C D E F G H I
Time 23 8 29 16 24 18 19 4 10
Exercise 2:
A company is in the process of preparing a budget for launching a new product. The following
table provides the associated activities and their durations.
Page | 2
Exercise 7:
The precedence relationships for five tasks are shown in the following table:
Times(days)
Activity Predecessor Duration
Optimistic Most likely pessimistic
A None 3 1 3 5
B None 4 3 4 5
C A, B 3 1 3 11
D B 3 3 3 9
E A 2 1 2 3
F C 5 2 5 14
G E, F 3 2 3 4
H D, F 2 2 2 2
I G, H 10 10 10 10
Page | 3
Exercise 9:
Hamilton Country Parks is planning to develop a new park and recreational area on a recently
purchased 100-acre tract of land. Project development activities include cleaning playground and
picnic areas, constructing road, constructing a shelter house, purchasing picnic equipment, and so
on. The PERT/CPM network shown below is being used in the planning, scheduling, and
controlling of this project.
Page | 4