Greenlife Hydropower Limited

Khanikhola-1 Hydropower Project


Road Mainttenance Estimate

Name of Employer: Greenlife Hydropower Limited


Name of Contractor: Eco Infra Builder Pvt.Ltd.

SN Description unit Rate Nos Length Breadth Height Quantity Amount Remarks

1.00 Site Clearance m2 50.00 1.00 886.54 4.50 3989.43 199,471.50


2.00 Backfilling
2.10 Ropeway to Microhydro ph m3 300.00 3.00 285.60 4.00 1.50 5140.80 1,542,240.00
2.20 Microhydro ph to S-bend m3 300.00 2.00 600.93 4.00 1.00 4807.44 1,442,232.00

Total amount 3,183,943.50


In words: Rupees ThirtyOne Lakh EightyThree Thousand Nine Hundred FourtyThree Paise Fifty
Only