MISURATA FREE ZONE PROJECT

SEWERAGE NETWORK
BILL OF QUANTITIES

SNo. Description of Item Unit Quantity Rate Amount


(LD) (LD)
1 Earthwork for excavation of pipe trenches
including dressing and soil support for
trench sides as required, dewatering,
preparation of trench bottom as per
specifications, lift up to 4m and disposal of
surplus excavated material up to 10km
from the site as directed by the Engineer
a. Excavation in ordinary soil m3 45,000 9.474
b. Excavation in rocky soil m3 15000 24.0917
2 Providing, placing and compacting granular m3 1,200 32.125
pipe bedding material in the pipe trenches
as per drawings and specification and as
directed by the Engineer
3 Providing, placing and compacting in layer m3 8,300 25.710
not exceeding 20cm imported fill material
for pipe zone as per drawings and
specification and as directed by the
Engineer
4 Backfilling the trenches with available m3 30,000 12.127
excavated material (excluding rocks) and
compacting in layer not exceeding 20cm as
per specifications and as directed by the
Engineer
5 Providing and laying uPVC sewer grade
pipes to line and levels as per drawings,
including pipe fittings such as Wyes, bends,
tees, sockets, plugs etc. complete. Cost
includes stringing, laying, joining and
testing of pipeline as per specifications and
as directed by the Engineer
a DN 200mm pipes m 8700 26.512
b DN 250mm pipes m 60 44.984
c DN 300mm pipes 1300 57.836
6 Providing and laying GRP sewer grade
pipes SN10000 to line and levels as per
drawings, including pipe fittings such as
Wyes, bends, tees, sockets, plugs etc.
complete. Cost includes stringing, laying,
joining and testing of pipeline as per
specifications and as directed by the
Engineer
a DN 600mm pipes m 670 174.893
b DN 700mm pipes m 860 231.482
Carried over to Summary

1
MISURATA FREE ZONE PROJECT
SEWERAGE NETWORK
BILL OF QUANTITIES

SNo. Description of Item Unit Quantity Rate Amount


(LD) (LD)
7 Providing and construction of R C C
manholes as per drawings and
specifications. The cost includes earthwork
in excavation and backfilling, insitu
foundation, shuttering, reinforcement,
building-in of pipes in manhole, benching,
finishing and testing etc, complete as per
specifications.
a. Manhole up to depth 2.0m No. 95 915.77
b. Manhole depth 2.0m to 3.0m No. 78 1204.9
69
c. Manhole depth 3.0m to 4.0m No. 46 1542.3
61
d. Manhole depth 4.0m to 5.0m No. 13 2008.2
84

8. Providing and fixing hot dipped galvanized No. 950 12.850


step irons in the manholes according to
drawings and specifications.

9. Providing and fixing heavy duty ductile No. 232 231.01


iron manhole covers including frames on 6
the manholes according to drawings and
specifications, and as directed by the
Engineer.

10. Road cutting for pipe trenches as directed m 100 1020.2


by the Engineer 05

11. Reinstatement of road as per specifications m 100 104.44


and as directed by the Engineer 5

12. Design, provide and construction of DI or m 2000 381.54


GRP rising mains dia. 450mm from sewage 4
pumping station to the inlet works of the
existing sewage treatment plant in the
Misurata Steel Complex. The cost includes
survey of pipe route, design, approval of
design, permissions from authorities,
excavation and backfilling of pipe trenches,
road cuttings and reinstatement; providing,
laying, joining and testing of pipes and
fittings; and connection into existing inlet
works, complete.
Carried over to Summary

2
MISURATA FREE ZONE PROJECT
SEWERAGE NETWORK
BILL OF QUANTITIES

3
MISURATA FREE ZONE PROJECT
SEWERAGE NETWORK
BILL OF QUANTITIES

SUMMARY

S.No. Description Amount (LD)


1 Carried over from page 1
2 Carried over from page 2
Grand Total