Professional Documents
Culture Documents
drivers were saving rig time, product reliability, flexibility, The removable packer was designed to be compatible with
and removability. existing alternative setting modules — hydrostatic setting
module or various disappearing plug modules. These
Save Rig Time: (Figure 3) alternative setting modules would allow the packer to be set
1) One-trip, flanged up, no tubing manipulation, no- without wireline intervention (Figure 4).
movement required during hydraulic setting. Removal. Equalize pressure above and below the packer
2) Multiple interventionless setting options to further by opening sliding sleeves or perforating the tubing. To
reduce installation costs and risk. retrieve the packer and tailpipe, the packer mandrel must be
3) Removal of packer on the production string in event cut. Two methods of removal are available, depending on
of pre-set while running in the well. the geometry of the completion: 1) removal on the completion
4) Optional contingency removal methods using thru- string using a thru-tubing chemical or mechanical cutter,
tubing and workstring methods. and/or 2) removal on the workstring using a removing or
milling tool. In either case, once the mandrel is cut, upward
Reliability: (Figure 3) movement of the tubing will release and stretch out the slips
1) Simple robust design similar to permanent packer and element of the packer (Figure 5).
with no integral retrieving mechanism to complicate
the design. 1) Removal on Completion String.
2) Use of proven non-deforming slips and element
system with retrievable extrusion barriers to ensure Using Thru-Tubing Chemical Cutter.
removability. In non-restrictive ID completions, chemical cutting is the
3) Design verification illustrated using permanent primary method of removing the packer. This cutting method
packer performance envelope, according to highest is applicable only when the OD of the pre-determined cutting
ISO 14310, Level V0 specifications for production assembly can pass through all the restrictions above
packer testing. the packer.
4) System verification by means of a stack-up test from Care should be given when running the completion
a drilling rig. bottomhole assembly to take accurate length, ID and OD
measurements of the packer, pipe and crossover connections.
Flexibility: (Figure 4) One should allow enough space below the desired cutting area
1) Modular design based on three components: “head”, for the collar locator or correlation device to pass below the
packer, “tail”. packer to ensure accurate depth correlation. The use of a
2) Head configurable for tubing connection — floating radioactive tag run on the original completion is recommended
seals, anchored seals, or no seals. as a means of locating the cutting zone of the packer.
3) Head configurable for removal: thru-tubing or A Chemical Cutter should be run on an appropriately
workstring cut-to-removal options. designed wireline tool string consisting of weight bars, collar
4) Tail configurable for setting — hydraulic, hydrostatic locator and/or gamma ray correlation device, firing sub, upper
or via remote actuated plugging device. propellant sub, slip sub, lower propellant sub, chemical
cylinder, cutting head and bull plug. The chemical cutter is
Removability: (Figure 5) anchored by a button type slip sub, which anchors the tool
1) On production string during the cutting operation. Once the cutting operation is
a) Thru-tubing chemical cut completed, the slips retract and the tool is free to be pulled
b) Thru-tubing mechanical cut from the well.
c) Straight-pull shear release (low service only). Once activated, the chemical cutter will cut cleanly
2) On workstring through the packer mandrel, allowing the packer and tailpipe
a) Removing tool to be retrieved. In stacked packer applications, all the packers
b) Milling tool. can be retrieved on the production tubing simultaneously,
simply by cutting all the packer mandrels.
Operations
Running. The removable packer was designed to be run Using Thru-Tubing Mechanical Cutter.
and set as with traditional hydraulic set packers. Once at In restricted ID type completions, coiled tubing conveyed
setting depth, land the tubing into the wellhead hanger and mechanical cutting allows retrieval of the removable packer
install the plugging device below the packer. Slowly apply on the completion string. This cutting method must be pre-
internal pressure to the tubing string to the calculated setting designed into the original completion as it requires the use of a
pressure. Hold the pressure for 15 minutes to ensure all Thru-Tubing Cutting Extension (TCE). The TCE, placed
components of the packer are fully deployed. Bleed off tubing above the removable packer, allows the cutting BHA to locate
and test the packer. Remove plugging device from tubing by and position itself across the cutting zone of the packer.
appropriate means. Care should be given when running the completion
bottomhole assembly to take accurate length, ID and OD
SPE 76711 RESOLVING THE COMPLETION ENGINEER'S DILEMMA: PERMANENT OR RETRIEVABLE PACKER? 3
This is a test inclusive of all intersection points of the rated installations put the removable packer’s design concepts to the
performance envelope, with temperature cycles, and with no test immediately: 1) removability: ability to remove the
leaks- holding gas pressure bubble tight. 4 packer by multiple methods, and 2) performance: operate in
Additional testing was performed to verify the no body a drilling/workover environment and in a stacked
movement was required during setting specification so the packer application.
packer would qualify for straddle packer and liner top
isolation completions. Case History #1 (Figure 8)
Removability. To speed up development, the two aspects
of the cut-to-remove technique were tested separately in the Design concept tested & proven: Multiple removable
laboratory: 1) cut and 2) remove. methods
Cutting ability was tested, both on the mechanical cutter Application: Single packer, frac,
and chemical cutter. Sample targets, cylinders of same cross- produce & remove
section and metallurgy of the body of the packer, were Well Reference: BP MPF-86
furnished to the cutting service providers. The mechanical Date of Packer Setting: August 8, 2001
cutter was qualified using a mud motor in a flow loop, while Casing Size: 7 in. 26 ppf
the chemical cutter was qualified in an environmental test cell Tubing Size: 4½ in. 12.6 ppf
that could simulate temperature and hydrostatic pressure. Number of Packers: 1
Special non-destructive, laboratory-based removal Packer Setting Depth (MD): 10,806 ft (3294 m)
procedures were developed to test the ability of the packer to Max. Deviation: 64º
be removed after full ISO 14310 V0 verification testing. Well Type: Oil Producer
2) Operations Validation: Stack-up Tests The Milne Point F-86 well was drilled and completed
There were two main objectives in the stack-up system initially with a removable packer, sliding sleeve and jet pump
tests performed from a drilling rig based in Bossier City, installation to allow formation fracturing of Kuparuk A2
Louisiana. The first objective was to determine the ability of sands. The jet pump was placed after the frac treatment was
the packers to perform in a drilling environment and in a completed and the well was preproduced and tested. At a later
stacked packer application. The tools were set and then date, the frac tubing and packer installation were removed and
pressure tested to ascertain the seal integrity. The second the A1 and A3 sands perforated. An electrical submersible
objective was to remove the packers using four different pump was installed after the A2/A3 sands were perforated.
removal methods: thru-tubing chemical cut, workstring The well was then brought on production.
conveyed retrieving tool, milling, and thru-tubing mechanical Performance. Removable packer was set by dropping a
cut with mud motor. ball onto the seat in a plug below the packer. Packer set with
Performance. Two removable packers were run in applied pressure and the tubing was tested. Bled pressure on
stacked, about 90 ft (27 m) apart. The tools were set at the tubing, and applied pressure to annulus for backside test of the
same time. After they were set, pressure was applied between packer. The well was fraced using 205,200 lb (76,588 kg) of
them, below the bottom packer, and then above the top packer. carbolite treatment over a 3½ hour time period. Maximum
Removability. Once the pressure test was completed, the surface treating pressure was 5260 psi (387 bar) with an
bottom packer was chemically cut on wireline. Then the top average flow rate of 25 barrels per minute during the job.
packer was cut on workstring using the retrieving tool. Both Calculated combined loads at the packer were 6789 psi (468
packers were retrieved together (Photos 1 & 2). bar) and 64,000 lb tension (29,205 kg).
A third packer was run in and set by itself. After a push- Removability. After well testing using a jet pump, rigged
pull test, the tool was milled over and retrieved using standard up the chemical cutter with collar locator and attempted to cut
procedures. The packer and sealbore head were milled over in and remove the packer on the production tubing. Pulled up
3½ hours, which is similar to the time required to mill over a 40,000 lb (18,144 kg) over string weight to free the packer.,
permanent packer (Photo 3). but the packer was still set and would not release. Released
A fourth packer was set and tested in the same manner as anchor type seal assembly from the packer and came out of
the third. It was cut through tubing on small OD pipe well with the production tubing. Went back in with
(simulating coiled tubing) using a mechanical cutter powered workstring conveyed removing tool (WCRT) and tagged
by a mud motor (Photo 4). packer at 10,794 ft. (3290 m). Cut the packer mandrel in five
All well tests validated our original design concepts. The minutes and pulled 25,000 lb. (11,340 kg) over string weight
testing also led to design enhancements to the mechanical and the packer came free. Pulled two stands and saw only
cutter and workstring retrieving tools that led to more minimal drag at the first two casing collars. Continued out of
efficient operations. the well bore with no signs of drag or sticking for the
remainder of the trip.
3) Application Validation: Case Histories Subsequent examination of the packer revealed that the
The first two installations with removable packers were in chemical cut was 2.5 in. too low and was placed across the
the remote areas of northern Alaska (Figure 7). These two bottom guide. The workstring removal tool cut the mandrel in
SPE 76711 RESOLVING THE COMPLETION ENGINEER'S DILEMMA: PERMANENT OR RETRIEVABLE PACKER? 5
the exact location as planned (Photo 5). This case history Additional Case Histories
validated the benefit of having multiple methods of removing The field experience validated our original design
the packer. concepts. The removable packer has proven to save rig time
by being stackable, reliable in drilling/workover
Case History #2 (Figure 9) environments, flexible and removable. Additional runs have
been recorded in Alaska, the Middle East and Caspian
Design concept tested & proven: drilling/workover Sea areas.
environment & stacked
packer application Benefits/Limitations/Enhancement Opportunities
Application: Triple-straddle isolation
completion Benefits. The current removable packer and cutting
Well Reference: BP Prudhoe Bay, S-107 technology provides the following significant benefits for
Date of Packer Setting: August 8, 2001 high-profile monobore wells, which are found in remote or
Casing Size: 7 in. 26 ppf offshore environments, many in deepwater or subsea wells or
Tubing Size: 4½ in. 12.6 ppf involving horizontal or extended reach wells:
Number of Packers: 3 1) Saves rig time - using one-trip, flanged-up hydraulic,
Top Packer, MD: 11,718 ft (3572 m) with no-mandrel movement during setting procedures, greatly
Measured Depth (MD), simplifying space-out procedures.
6635 ft +(2022 m)- True 2) Reliability - simple robust design similar to the
Vertical Depth (TVD) permanent packer’s slip-element-slip configuration.
Middle Packer, MD: 11,823 ft (3604 m) MD, 3) Flexibility - modular design using head, packer, and
6680 ft +(2036 m)- TVD tail adds flexibility to cover a wide range of applications,
Bottom Packer, MD: 12,223 ft (3726 m) MD, allowing multiple removal and setting methods.
6850 ft + (2088 m)- TVD 4) Removability - non-deforming slips and attached
Max. Deviation: 97.6º extrusion barrier proven to be retrievable.
Well Type: Horizontal H2O Injection
Limitations. Current removable packer and cutting
The dual purpose of this triple-packer completion was to technology limitations are as follows:
selectively capture two seawater injection targets in the 1) Metallurgy - limited experience in cutting high-nickel
Kuparuk C-sands ~3700 ft. (1128 m) apart and isolate an old alloy CRA tubulars.
set of perforations above the injection target zones. The old 2) Restricted ID completions - limited to workstring
perforations were isolated between the top packer at 11,720 ft retrieving tool and thru-tubing mechanical cutting
(3572 m) MD and the middle packer at 11,825 ft (3604 m) removal options.
MD. Current desirable injection zones were perforated for 3) Thru-tubing cutters - only as good as the means to
placement between the middle packer and the bottom packer locate the cutting zone of the packer mandrel. Use of
at 12,226 ft (3226 m) MD. A sliding sleeve was installed no-go or selective locating profiles above the packer
between the middle packer and bottom packer at 11,967 ft are recommended, and where applicable, a
(3648 m) MD to provide injection selectivity between radioactive tag for locating the chemical cutter.
subzones of the Kuparuk C sands. The main area of
injectivity below the lower packer was cased behind solid pipe Enhancements. Enhancements of removable packer and
from a liner top packer at 12,259 feet to an external casing cutting technology under development, or that are being
packer at 15,127 ft (4611 m) MD with slotted uncemented sought, include:
liner from the external casing packer to 15,938 ft MD (4858 1) Cutting technology for high-grade corrosion resistant
m) plug back total depth of the well. alloys - development of industry accepted and
Performance. Three removable packers were run everyday usage of cutters for high- nickel
immediately following clean-out trip where a cast iron bridge alloy tubulars.
plug was drilled up. During the run-in with the packers, the 2) Through tubing release methods - development of
string stopped multiple times as the packers encountered cast industry accepted and everyday usage of lower cost
iron plug debris. At one point, circulation was stopped due to thru-tubing releasing methods.
the debris in the wellbore. At setting depth, all three packers 3) Commercialization/standardization - opportunity to
were hydraulically set using standard procedures. The tubing develop universal and standard thru-tubing locating
and backside were pressure tested successfully to 3,500 psi methods for use in restricted and non-restricted
(241.3 bar). This case history validated the removable completions. Efficient solutions exist, though they
packer’s application in drilling/workover environments and in tend to be operator and well specific.
stacked packer applications.
6 M. T. TRIOLO, L. F. ANDERSON, M. V. SMITH SPE 76711
Conclusion
1) Removable packers resolve the completion
engineer’s dilemma when deciding between
retrievable and permanent large-bore packers.
2) Removable packers offer value in high-profile
monobore wells, which are found in remote or
offshore environments, deepwater or subsea wells, or
involve horizontal or extended reach completions.
3) The removable packer design concept was validated
by performance testing in the laboratory, system
testing at a rig, and application testing in the field.
4) Enhancements in cutting technologies will continue
to offer additional value in using removable packers.
5) Wider usage and experience with removable packers
will lead to improved and standardized thru-tubing
locating and cutting techniques.
Acknowledgments
The authors wish to thank the management of BP and Baker
Oil Tools for the permission to publish this paper, and thank
the various other operators for their investment in removable
packer technology. This development would not have been
successful without the many synergistic efforts of Baker Oil
Tools’ Packer group and Fishing Group with their
Metal Muncher technology, and Baker Atlas’ chemical
cutting technology.
References
1. Bradley, W.B. (ed): Petroleum Engineering Handbook, Third
Printing, Richardson, TX (1992), Chapter 4, pgs. 1-11.
2. Economides, M. J., Watters, L.T., Dunn, S. (ed): Petroleum
Well Construction, John Wiley & Sons, West Sussex, England,
1998, pg. 381-387.
3. Hopmann, M., and Walker, T.: “Predict Permanent Packer
Performance,” Petroleum Engineering International (1995)
35-39.
4. ISO/DIS 14310, “Petroleum and Natural Gas Industries -
Downhole Equipment - Packers and Bridge Plugs,” 18
January 2001.
5. Jones, R. D.: SPE 68349, “Developing Coiled-Tubing
Techniques on the Karachaganak Field, Kazakhstan”, presented
at SPE/ICoTA Coiled Tubing Roundtable, Houston, TX, 7-8
March 2001.
SPE 76711 RESOLVING THE COMPLETION ENGINEER'S DILEMMA: PERMANENT OR RETRIEVABLE PACKER? 7
Removable
ent Re
n Simple slip-element- tri
a slip design ev
m Destructive removal
Non-drillable
Uses proven
r
Non-integral equalizing
ab
retrievable components
Pe
le
Can be milled over & removal
recovered
High performance
w/large IDs
Actuate
Set
Grip & Seal
Big bore
monobore
Positive, element-type
debris barrier
Field proven,
non-deforming
retrievable slip
system
Slip-element- Retrievable
slip: gripping sealing system
slips isolated
from high
pressure
No mandrel
movement during
setting
Configurable for
traditional or
interventionless setting
10 M. T. TRIOLO, L. F. ANDERSON, M. V. SMITH SPE 76711
HEAD
PACKER
Removable
Packer
TAIL
Above 0 Below
Tension
Applied Axial Load
Set-Down
Differential Pressure
Arctic Ocean
ALASKA
CANADA
Beaufor t Sea
Barrow
Umiat
k
rk o
Colville River
v ani
ag a
S
NORTH SLOPE
YUKON-KOYUKUK
KOBUK
SPE 76711 RESOLVING THE COMPLETION ENGINEER'S DILEMMA: PERMANENT OR RETRIEVABLE PACKER? 13
Figure 8. Milne Point F-86 Well with Frac, Test and Remove Completion
MPF-86
4-1/2 Tbg.12.6#,
L-80, ID=3.958
10827 WLEG
7 Csg. 26#,
L-80, ID = 6.276 11206
14 M. T. TRIOLO, L. F. ANDERSON, M. V. SMITH SPE 76711
S-107
2277 4-1/2 SSSVN, ID = 3.813
15938 PBTD
Photo 3. Recovered packer using milling tool Photo 4. Disassembled recovered packer showing mandrel
severed by mechanical cutter and mud motor
16 M. T. TRIOLO, L. F. ANDERSON, M. V. SMITH SPE 76711