You are on page 1of 16

SPE 76711

Resolving the Completion Engineer's Dilemma: Permanent or Retrievable Packer?


M.T. Triolo, BP; L.F. Anderson, SPE, M.V. Smith, SPE, Baker Oil Tools

Copyright 2002, Society of Petroleum Engineers Inc.


any retrieval mechanism, or internal pressure equalizing
This paper was prepared for presentation at the SPE Western Regional/AAPG Pacific Section system, permits a larger internal diameter, while maintaining
Joint Meeting held in Anchorage, Alaska, U.S.A., 20–22 May 2002.
high differential pressure ratings. Hostile environments are
This paper was selected for presentation by an SPE Program Committee following review of
information contained in an abstract submitted by the author(s). Contents of the paper, as
typically addressed with permanent packers, both for
presented, have not been reviewed by the Society of Petroleum Engineers and are subject to management of cost and concerns for the long-term integrity
correction by the author(s). The material, as presented, does not necessarily reflect any
position of the Society of Petroleum Engineers, its officers, or members. Papers presented at of the retrieval mechanism.
SPE meetings are subject to publication review by Editorial Committees of the Society of
Petroleum Engineers. Electronic reproduction, distribution, or storage of any part of this paper
The retrievable option offers the most flexibility and
for commercial purposes without the written consent of the Society of Petroleum Engineers is potential economy in cases where the removal is anticipated in
prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300
words; illustrations may not be copied. The abstract must contain conspicuous the short term, or repeatedly in the life of the well.
acknowledgment of where and by whom the paper was presented. Write Librarian, SPE, P.O.
Box 833836, Richardson, TX 75083-3836, U.S.A., fax 01-972-952-9435.
Performance characteristics in terms of differential pressure
ratings, as well as the reliability of retrieval, have improved
dramatically in recent years. Some of the current retrievable
Abstract designs actually rival permanent packer performance in some
Traditionally, completion engineers have faced a dilemma size ranges. Despite performance enhancements, retrievable
when deciding whether to run a large bore, hydraulic set, packer models still dictate limitations in their internal diameter
permanent, or retrievable packer. Thanks to advances in specifications, associated with the internal bypass and
cutting technology, this decision is no longer an retrieval mechanisms.
either/or proposition. The innovative alternative is the In recent years, a niche has evolved for a third option,
removable packer. driven by the use of larger diameter production tubulars. The
This paper will address the development of a removable required packer bore diameters, relative to the available cross-
packer that combines the best features of both permanent and section, exceed the possibility of conventional retrievable
retrievable packers: large bore, high performance, simple technology. At the same time, all of the flexibility of a true
design, and flexible retrieving options. The paper will trace the retrievable packer is not required. The combination of
development of the technique from stack-up testing to the permanent packer performance, with a means to facilitate
maiden run and retrieval of the first removable packer in the removal without a costly milling operation, has led to a new
Milne Point field, Alaska. Through analysis of this case platform of “removable” packer design. This option provides
history, the paper will address challenges faced, problems for the removal of the packer through advanced chemical or
solved and lessons learned that are now being applied to future mechanical cutting technologies (Figure 1).
enhancements of the removable packer technique.
Removable Packer
Introduction
Historically, the selection of a completion’s production packer Application
has been an either or proposition — either a permanent or The removable packer was designed for prolific reservoirs
retrievable packer. In practical applications, there is that employ large-diameter tubulars for high-volume
considerable overlap in which either option is acceptable, but production. Often these developments are high-profile
determination of the boundaries of that overlap continues to be monobore wells, which are found in remote or offshore
debated. There are, however, application considerations environments, many in deepwater or subsea wells or involving
that should provide the engineer with a general guideline horizontal or extended reach wells. The packer will function
for selection. as either a production packer or an isolation packer, above a
The permanent packer has long been thought of as the liner top or run in tandem as a straddle (Figure 2).
most reliable option for extreme conditions. As milling is its
only means of removal, consideration of reservoir life Benefits
expectancy versus the costs of removal will usually weigh Given the high profile and varied applications for a large-
heavily in the choice of options. By definition, the permanent bore packer, the four main removable packer design
set offers simplicity, requiring few moving parts. The lack of
2 M. T. TRIOLO, L. F. ANDERSON, M. V. SMITH SPE 76711

drivers were saving rig time, product reliability, flexibility, The removable packer was designed to be compatible with
and removability. existing alternative setting modules — hydrostatic setting
module or various disappearing plug modules. These
Save Rig Time: (Figure 3) alternative setting modules would allow the packer to be set
1) One-trip, flanged up, no tubing manipulation, no- without wireline intervention (Figure 4).
movement required during hydraulic setting. Removal. Equalize pressure above and below the packer
2) Multiple interventionless setting options to further by opening sliding sleeves or perforating the tubing. To
reduce installation costs and risk. retrieve the packer and tailpipe, the packer mandrel must be
3) Removal of packer on the production string in event cut. Two methods of removal are available, depending on
of pre-set while running in the well. the geometry of the completion: 1) removal on the completion
4) Optional contingency removal methods using thru- string using a thru-tubing chemical or mechanical cutter,
tubing and workstring methods. and/or 2) removal on the workstring using a removing or
milling tool. In either case, once the mandrel is cut, upward
Reliability: (Figure 3) movement of the tubing will release and stretch out the slips
1) Simple robust design similar to permanent packer and element of the packer (Figure 5).
with no integral retrieving mechanism to complicate
the design. 1) Removal on Completion String.
2) Use of proven non-deforming slips and element
system with retrievable extrusion barriers to ensure Using Thru-Tubing Chemical Cutter.
removability. In non-restrictive ID completions, chemical cutting is the
3) Design verification illustrated using permanent primary method of removing the packer. This cutting method
packer performance envelope, according to highest is applicable only when the OD of the pre-determined cutting
ISO 14310, Level V0 specifications for production assembly can pass through all the restrictions above
packer testing. the packer.
4) System verification by means of a stack-up test from Care should be given when running the completion
a drilling rig. bottomhole assembly to take accurate length, ID and OD
measurements of the packer, pipe and crossover connections.
Flexibility: (Figure 4) One should allow enough space below the desired cutting area
1) Modular design based on three components: “head”, for the collar locator or correlation device to pass below the
packer, “tail”. packer to ensure accurate depth correlation. The use of a
2) Head configurable for tubing connection — floating radioactive tag run on the original completion is recommended
seals, anchored seals, or no seals. as a means of locating the cutting zone of the packer.
3) Head configurable for removal: thru-tubing or A Chemical Cutter should be run on an appropriately
workstring cut-to-removal options. designed wireline tool string consisting of weight bars, collar
4) Tail configurable for setting — hydraulic, hydrostatic locator and/or gamma ray correlation device, firing sub, upper
or via remote actuated plugging device. propellant sub, slip sub, lower propellant sub, chemical
cylinder, cutting head and bull plug. The chemical cutter is
Removability: (Figure 5) anchored by a button type slip sub, which anchors the tool
1) On production string during the cutting operation. Once the cutting operation is
a) Thru-tubing chemical cut completed, the slips retract and the tool is free to be pulled
b) Thru-tubing mechanical cut from the well.
c) Straight-pull shear release (low service only). Once activated, the chemical cutter will cut cleanly
2) On workstring through the packer mandrel, allowing the packer and tailpipe
a) Removing tool to be retrieved. In stacked packer applications, all the packers
b) Milling tool. can be retrieved on the production tubing simultaneously,
simply by cutting all the packer mandrels.
Operations
Running. The removable packer was designed to be run Using Thru-Tubing Mechanical Cutter.
and set as with traditional hydraulic set packers. Once at In restricted ID type completions, coiled tubing conveyed
setting depth, land the tubing into the wellhead hanger and mechanical cutting allows retrieval of the removable packer
install the plugging device below the packer. Slowly apply on the completion string. This cutting method must be pre-
internal pressure to the tubing string to the calculated setting designed into the original completion as it requires the use of a
pressure. Hold the pressure for 15 minutes to ensure all Thru-Tubing Cutting Extension (TCE). The TCE, placed
components of the packer are fully deployed. Bleed off tubing above the removable packer, allows the cutting BHA to locate
and test the packer. Remove plugging device from tubing by and position itself across the cutting zone of the packer.
appropriate means. Care should be given when running the completion
bottomhole assembly to take accurate length, ID and OD
SPE 76711 RESOLVING THE COMPLETION ENGINEER'S DILEMMA: PERMANENT OR RETRIEVABLE PACKER? 3

measurements of the packer, pipe and crossover connections. Design Concept


One should allow enough space above the desired cutting area Performance. The removable packer concept utilized
for the adjustable no-go locating sub to locate and still provide proven retrievable components taken from both mechanical
sufficient distance for the motor and the underreamer. and hydraulic set packers. A slip-element-slip with positive
An underreaming tool should be run on an appropriately debris barrier design was chosen over conventional element-
designed coiled tubing tool string, consisting of a connector, slip or the unconventional slip-element design for its ability to
dual-flapper back pressure valve, hydraulic disconnect, dual- emulate the permanent packer in performance and simplicity.
actuated circulation sub, adjustable no-go locating sub, and Having a slip on either side of the element reduces tri-axial
mud motor. stresses, both in the casing and the body of the packer; the
Upon reaching the TCE, the adjustable no-go sub will casing, as the load (holding slip) is separated (by the packing
position the underreamer across the cutting zone of the packer. element) from the pressure; the body, as the load path doesn’t
Gradually bring the pump rate up to the flow rate determined extend past the slips on the body, thus permitting use of
by the service company representative on site. Continue the standard yield strength materials and reduced cross section to
cutting process until a positive pressure drop has been enable more reliable cutting and removal of the packer.
observed. This will indicate that the cut has been made. Removability. The cut-to-remove concept is based on the
Once the cutting operation is completed, the cutting knives premise that the cross-section of the packer’s cut zone is
retract into the underreamer and the entire cutting bottomhole similar to that of the production tubing. Thus, as long as the
assembly is removed from the well. Upward movement of the operator can chemically cut his tubing and no major
production tubing will release and stretch out the slips and restrictions exist above the packer, then the packer body
packing element system. The packer and tailpipe can be should be able to be cut. Mechanical cutting would be much
pulled out of the well with upstrain. the same, requiring no new tool developments, though the
travel of the knives would need to be controlled so the cut did
2) Removal on Workstring not extend past the body. The workstring retrieving tool
would combine a proven retrieving tool with a mechanical
Using Workstring Conveyed Removing Tool (WCRT). cutter. In summary, no new technology development or
This method of removal can only be used when the characterization of cutters was planned using this cut-to-
removable packer is run with an alternative upper sealbore. remove design concept.
To use the WCRT, the anchor type seal assembly must be
removed from the upper sealbore of the packer. Design Validation
The WCRT is run in on an appropriately designed The design concepts covering the packer performance and
workover string consisting of jars, drill collars, or if rotation of its removability would be validated analytically by component
the pipe is not possible, a downhole motor. in the laboratory, systemically on a test rig, and operationally
Upon reaching the upper sealbore receptacle, the tool in the field.
enters the packer bore and is automatically positioned for
mechanical cutting. Applying set-down weight at this point 1) Equipment Validation: Lab Tests
will ensure that the anchor latch positively engages the left- Performance. Extensive component testing was
hand thread in the sealbore receptacle. Gradually, bring the performed on both the slip mechanism and packing element
pump rate up to the flow rate and RPMs, which was system to ensure removability.
determined by the service company representative on site. Packer performance was verified using a ratings
Continue the cutting process until a positive pressure drop has performance envelope (Figure 6). The rating envelope was
been observed. This will indicate that the cut has been made. originally developed to describe the performance of permanent
Once the packer mandrel is cut, upward movement of the packers and their failure modes.3 The rating envelope has
workstring will release and stretch out the slips and packing evolved through the International Standards Organization, ISO
element system. The packer and tailpipe can be pulled out of 14310, as a standard means to illustrate the combined loading,
the well with upstrain. i.e., applied pressure and axial load, which a packer sees
during design validation testing. ISO 14310 sets six standard
Using Milling Tool. design validation grades (V6 to V1) and one special grade
In the event the packer can not be removed using standard (V0). These standardized grades allow the user/purchaser to
removal procedures, the packer can be milled over match the appropriate level of validation testing to the actual
and retrieved. well application requirements. Design validation grade V6 is
A milling tool can be used in conjunction with a washover the minimum grade where the validation method has been
assembly to burn over and retrieve the removable packer in defined by the supplier/manufacturer. The complexity and
one trip. Run in the hole with washover assembly with severity of the validation testing increases as the grade number
appropriately sized milling shoe. Mill down to the slips or decreases. (Table 1). Full-scale testing of the removable
until the packer moves downhole. Pull out of the hole with packer was performed according to the most stringent ISO
washover assembly and recovered packer. 14310, level V0 validation testing criteria. V0 validation
testing requires testing in gas, in maximum rated casing ID.
4 M. T. TRIOLO, L. F. ANDERSON, M. V. SMITH SPE 76711

This is a test inclusive of all intersection points of the rated installations put the removable packer’s design concepts to the
performance envelope, with temperature cycles, and with no test immediately: 1) removability: ability to remove the
leaks- holding gas pressure bubble tight. 4 packer by multiple methods, and 2) performance: operate in
Additional testing was performed to verify the no body a drilling/workover environment and in a stacked
movement was required during setting specification so the packer application.
packer would qualify for straddle packer and liner top
isolation completions. Case History #1 (Figure 8)
Removability. To speed up development, the two aspects
of the cut-to-remove technique were tested separately in the Design concept tested & proven: Multiple removable
laboratory: 1) cut and 2) remove. methods
Cutting ability was tested, both on the mechanical cutter Application: Single packer, frac,
and chemical cutter. Sample targets, cylinders of same cross- produce & remove
section and metallurgy of the body of the packer, were Well Reference: BP MPF-86
furnished to the cutting service providers. The mechanical Date of Packer Setting: August 8, 2001
cutter was qualified using a mud motor in a flow loop, while Casing Size: 7 in. 26 ppf
the chemical cutter was qualified in an environmental test cell Tubing Size: 4½ in. 12.6 ppf
that could simulate temperature and hydrostatic pressure. Number of Packers: 1
Special non-destructive, laboratory-based removal Packer Setting Depth (MD): 10,806 ft (3294 m)
procedures were developed to test the ability of the packer to Max. Deviation: 64º
be removed after full ISO 14310 V0 verification testing. Well Type: Oil Producer

2) Operations Validation: Stack-up Tests The Milne Point F-86 well was drilled and completed
There were two main objectives in the stack-up system initially with a removable packer, sliding sleeve and jet pump
tests performed from a drilling rig based in Bossier City, installation to allow formation fracturing of Kuparuk A2
Louisiana. The first objective was to determine the ability of sands. The jet pump was placed after the frac treatment was
the packers to perform in a drilling environment and in a completed and the well was preproduced and tested. At a later
stacked packer application. The tools were set and then date, the frac tubing and packer installation were removed and
pressure tested to ascertain the seal integrity. The second the A1 and A3 sands perforated. An electrical submersible
objective was to remove the packers using four different pump was installed after the A2/A3 sands were perforated.
removal methods: thru-tubing chemical cut, workstring The well was then brought on production.
conveyed retrieving tool, milling, and thru-tubing mechanical Performance. Removable packer was set by dropping a
cut with mud motor. ball onto the seat in a plug below the packer. Packer set with
Performance. Two removable packers were run in applied pressure and the tubing was tested. Bled pressure on
stacked, about 90 ft (27 m) apart. The tools were set at the tubing, and applied pressure to annulus for backside test of the
same time. After they were set, pressure was applied between packer. The well was fraced using 205,200 lb (76,588 kg) of
them, below the bottom packer, and then above the top packer. carbolite treatment over a 3½ hour time period. Maximum
Removability. Once the pressure test was completed, the surface treating pressure was 5260 psi (387 bar) with an
bottom packer was chemically cut on wireline. Then the top average flow rate of 25 barrels per minute during the job.
packer was cut on workstring using the retrieving tool. Both Calculated combined loads at the packer were 6789 psi (468
packers were retrieved together (Photos 1 & 2). bar) and 64,000 lb tension (29,205 kg).
A third packer was run in and set by itself. After a push- Removability. After well testing using a jet pump, rigged
pull test, the tool was milled over and retrieved using standard up the chemical cutter with collar locator and attempted to cut
procedures. The packer and sealbore head were milled over in and remove the packer on the production tubing. Pulled up
3½ hours, which is similar to the time required to mill over a 40,000 lb (18,144 kg) over string weight to free the packer.,
permanent packer (Photo 3). but the packer was still set and would not release. Released
A fourth packer was set and tested in the same manner as anchor type seal assembly from the packer and came out of
the third. It was cut through tubing on small OD pipe well with the production tubing. Went back in with
(simulating coiled tubing) using a mechanical cutter powered workstring conveyed removing tool (WCRT) and tagged
by a mud motor (Photo 4). packer at 10,794 ft. (3290 m). Cut the packer mandrel in five
All well tests validated our original design concepts. The minutes and pulled 25,000 lb. (11,340 kg) over string weight
testing also led to design enhancements to the mechanical and the packer came free. Pulled two stands and saw only
cutter and workstring retrieving tools that led to more minimal drag at the first two casing collars. Continued out of
efficient operations. the well bore with no signs of drag or sticking for the
remainder of the trip.
3) Application Validation: Case Histories Subsequent examination of the packer revealed that the
The first two installations with removable packers were in chemical cut was 2.5 in. too low and was placed across the
the remote areas of northern Alaska (Figure 7). These two bottom guide. The workstring removal tool cut the mandrel in
SPE 76711 RESOLVING THE COMPLETION ENGINEER'S DILEMMA: PERMANENT OR RETRIEVABLE PACKER? 5

the exact location as planned (Photo 5). This case history Additional Case Histories
validated the benefit of having multiple methods of removing The field experience validated our original design
the packer. concepts. The removable packer has proven to save rig time
by being stackable, reliable in drilling/workover
Case History #2 (Figure 9) environments, flexible and removable. Additional runs have
been recorded in Alaska, the Middle East and Caspian
Design concept tested & proven: drilling/workover Sea areas.
environment & stacked
packer application Benefits/Limitations/Enhancement Opportunities
Application: Triple-straddle isolation
completion Benefits. The current removable packer and cutting
Well Reference: BP Prudhoe Bay, S-107 technology provides the following significant benefits for
Date of Packer Setting: August 8, 2001 high-profile monobore wells, which are found in remote or
Casing Size: 7 in. 26 ppf offshore environments, many in deepwater or subsea wells or
Tubing Size: 4½ in. 12.6 ppf involving horizontal or extended reach wells:
Number of Packers: 3 1) Saves rig time - using one-trip, flanged-up hydraulic,
Top Packer, MD: 11,718 ft (3572 m) with no-mandrel movement during setting procedures, greatly
Measured Depth (MD), simplifying space-out procedures.
6635 ft +(2022 m)- True 2) Reliability - simple robust design similar to the
Vertical Depth (TVD) permanent packer’s slip-element-slip configuration.
Middle Packer, MD: 11,823 ft (3604 m) MD, 3) Flexibility - modular design using head, packer, and
6680 ft +(2036 m)- TVD tail adds flexibility to cover a wide range of applications,
Bottom Packer, MD: 12,223 ft (3726 m) MD, allowing multiple removal and setting methods.
6850 ft + (2088 m)- TVD 4) Removability - non-deforming slips and attached
Max. Deviation: 97.6º extrusion barrier proven to be retrievable.
Well Type: Horizontal H2O Injection
Limitations. Current removable packer and cutting
The dual purpose of this triple-packer completion was to technology limitations are as follows:
selectively capture two seawater injection targets in the 1) Metallurgy - limited experience in cutting high-nickel
Kuparuk C-sands ~3700 ft. (1128 m) apart and isolate an old alloy CRA tubulars.
set of perforations above the injection target zones. The old 2) Restricted ID completions - limited to workstring
perforations were isolated between the top packer at 11,720 ft retrieving tool and thru-tubing mechanical cutting
(3572 m) MD and the middle packer at 11,825 ft (3604 m) removal options.
MD. Current desirable injection zones were perforated for 3) Thru-tubing cutters - only as good as the means to
placement between the middle packer and the bottom packer locate the cutting zone of the packer mandrel. Use of
at 12,226 ft (3226 m) MD. A sliding sleeve was installed no-go or selective locating profiles above the packer
between the middle packer and bottom packer at 11,967 ft are recommended, and where applicable, a
(3648 m) MD to provide injection selectivity between radioactive tag for locating the chemical cutter.
subzones of the Kuparuk C sands. The main area of
injectivity below the lower packer was cased behind solid pipe Enhancements. Enhancements of removable packer and
from a liner top packer at 12,259 feet to an external casing cutting technology under development, or that are being
packer at 15,127 ft (4611 m) MD with slotted uncemented sought, include:
liner from the external casing packer to 15,938 ft MD (4858 1) Cutting technology for high-grade corrosion resistant
m) plug back total depth of the well. alloys - development of industry accepted and
Performance. Three removable packers were run everyday usage of cutters for high- nickel
immediately following clean-out trip where a cast iron bridge alloy tubulars.
plug was drilled up. During the run-in with the packers, the 2) Through tubing release methods - development of
string stopped multiple times as the packers encountered cast industry accepted and everyday usage of lower cost
iron plug debris. At one point, circulation was stopped due to thru-tubing releasing methods.
the debris in the wellbore. At setting depth, all three packers 3) Commercialization/standardization - opportunity to
were hydraulically set using standard procedures. The tubing develop universal and standard thru-tubing locating
and backside were pressure tested successfully to 3,500 psi methods for use in restricted and non-restricted
(241.3 bar). This case history validated the removable completions. Efficient solutions exist, though they
packer’s application in drilling/workover environments and in tend to be operator and well specific.
stacked packer applications.
6 M. T. TRIOLO, L. F. ANDERSON, M. V. SMITH SPE 76711

Conclusion
1) Removable packers resolve the completion
engineer’s dilemma when deciding between
retrievable and permanent large-bore packers.
2) Removable packers offer value in high-profile
monobore wells, which are found in remote or
offshore environments, deepwater or subsea wells, or
involve horizontal or extended reach completions.
3) The removable packer design concept was validated
by performance testing in the laboratory, system
testing at a rig, and application testing in the field.
4) Enhancements in cutting technologies will continue
to offer additional value in using removable packers.
5) Wider usage and experience with removable packers
will lead to improved and standardized thru-tubing
locating and cutting techniques.

Acknowledgments
The authors wish to thank the management of BP and Baker
Oil Tools for the permission to publish this paper, and thank
the various other operators for their investment in removable
packer technology. This development would not have been
successful without the many synergistic efforts of Baker Oil
Tools’ Packer group and Fishing Group with their
Metal Muncher technology, and Baker Atlas’ chemical
cutting technology.

References
1. Bradley, W.B. (ed): Petroleum Engineering Handbook, Third
Printing, Richardson, TX (1992), Chapter 4, pgs. 1-11.
2. Economides, M. J., Watters, L.T., Dunn, S. (ed): Petroleum
Well Construction, John Wiley & Sons, West Sussex, England,
1998, pg. 381-387.
3. Hopmann, M., and Walker, T.: “Predict Permanent Packer
Performance,” Petroleum Engineering International (1995)
35-39.
4. ISO/DIS 14310, “Petroleum and Natural Gas Industries -
Downhole Equipment - Packers and Bridge Plugs,” 18
January 2001.
5. Jones, R. D.: SPE 68349, “Developing Coiled-Tubing
Techniques on the Karachaganak Field, Kazakhstan”, presented
at SPE/ICoTA Coiled Tubing Roundtable, Houston, TX, 7-8
March 2001.
SPE 76711 RESOLVING THE COMPLETION ENGINEER'S DILEMMA: PERMANENT OR RETRIEVABLE PACKER? 7

Figure 1. Packer Options

Removable

• Thru-tubing and workstring removal options


• Can be redressed when practical

ent Re
n • Simple slip-element- tri
a slip design ev
m • Destructive removal
•
•
Non-drillable
Uses proven
r

• Non-integral equalizing

ab
retrievable components
Pe

or retrieving mechanism • No milling required for

le
• Can be milled over & removal
recovered
• High performance
w/large ID’s
• Actuate
• Set
• Grip & Seal

• Drillable • Non-destructive removal


• Can not be redressed • Can be redressed easily
• Integral retrieving mechanism
• Integral equalizing mechanism
• Generally not mill friendly
• Moderate performance with
large ID’s
8 M. T. TRIOLO, L. F. ANDERSON, M. V. SMITH SPE 76711

Figure 2. Removable Packer Applications

Big bore
monobore

Liner Top Isolation

Extended reach deepwater


SPE 76711 RESOLVING THE COMPLETION ENGINEER'S DILEMMA: PERMANENT OR RETRIEVABLE PACKER? 9

Figure 3. Removable Packer Features

Configurable for floating seals, Configurable for thru-


anchored seals, or no seals tubing and/or workstring
cut-to-removal

Positive, element-type
debris barrier

Field proven,
non-deforming
retrievable slip
system

Slip-element- Retrievable
slip: gripping sealing system
slips isolated
from high
pressure

No mandrel
movement during
setting

Configurable for
traditional or
interventionless setting
10 M. T. TRIOLO, L. F. ANDERSON, M. V. SMITH SPE 76711

Figure 4. Removable Packer Components

HEAD

Seals Seals No Seals Disconnect Thru-Tubing


Anchored Floating Premium Premium Cut Extension

PACKER

Removable
Packer

TAIL

Intervention-to-Set Interventionless Interventionless Interventionless


Disappearing Plug Module Hydrostatic Setting Moddule Tubing Tester/
Packer Setting
Module
SPE 76711 RESOLVING THE COMPLETION ENGINEER'S DILEMMA: PERMANENT OR RETRIEVABLE PACKER? 11

Figure 5. Removable Packer Removal Techniques

ON PRODUCTION TUBING ON WORKSTRING

Thru-tubing Thru-tubing Removing Tool Milling Tool


Chemical Cut Mechanical Cut
12 M. T. TRIOLO, L. F. ANDERSON, M. V. SMITH SPE 76711

Figure 6. Performance Envelope

Above 0 Below

Tension
Applied Axial Load

Set-Down
Differential Pressure

Figure 7. Geographic Location of Milne Point and Prudhoe Bay, Alaska

Arctic Ocean
ALASKA
CANADA

Beaufor t Sea
Barrow

Teshekpuk Harrison Bay Milne Point Field


Lake Prudhoe Bay-Field
Camden Bay Kaktovik
River

Umiat
k
rk o

Colville River
v ani

ag a
S

NORTH SLOPE

YUKON-KOYUKUK
KOBUK
SPE 76711 RESOLVING THE COMPLETION ENGINEER'S DILEMMA: PERMANENT OR RETRIEVABLE PACKER? 13

Figure 8. Milne Point F-86 Well with Frac, Test and Remove Completion

MPF-86

9-5/8” Csg. 40# - 5517’


L-80, ID=8.835”

10578’ 4-1/2” Gas Lift Mandrel

4-1/2” Tbg.12.6#,
L-80, ID=3.958”

10772’ 4-1/2” Sliding Sleeve

10784’ 7”x4-1/2” Anchor Type Seal


Assembly

10786’ 7”x4-1/2” Removable Packer


w/alternative upper seal bore

10816’ 4-1/2” Nipple

10827’ WLEG

7” Csg. 26#,
L-80, ID = 6.276” 11206’
14 M. T. TRIOLO, L. F. ANDERSON, M. V. SMITH SPE 76711

Figure 9. Prudhoe Bay S-107 Well with Triple-Packer Completion

S-107
2277’ 4-1/2” SSSVN, ID = 3.813”

10-3/4” Csg, 45.5#, 4265’


L-80, ID = 9.980”

11654’ 4-1/2” Nipple, ID = 3.813”


RA Tags in Joint # 10 11665’
11718’ 7”x 4-1/2” Removable Pkr, ID= 3.875”

11823’ 7”x 4-1/2” Removable Pkr, ID= 3.875”

11967’ 4-1/2” Sliding Sleeve, ID = 3.812”

12202’ 4-1/2” Nipple, ID =3.813”


12223’ 7”x 4-1/2” Removable Pkr, ID = 3.875”
12250’ 4-1/2” Nipple, ID =3.725”

4-1/2” Tbg, 12.6#, 12262’ 12259’ 7”x 5” Liner Pkr, ID = 5.250”


L-80, ID = 3.958”
12263’ 4-1/2” WLEG, ID =3.958”

7” Csg, 26#, 12274’ 7”x 5” Liner Hanger, ID = 4.430”


12421’
L-80, ID = 6.276”

15019’ 4-1/2” Ext. Csg. Pkr, ID = 3.937”

15274’ Top of 4-1/2” Slotted Liner

15938’ PBTD

4-1/2” Slotted Liner 12.6#, L-80, ID = 3.958” 12274’


4-1/2” Liner, 12.6#, L-80, ID = 3.958” 15980’
SPE 76711 RESOLVING THE COMPLETION ENGINEER'S DILEMMA: PERMANENT OR RETRIEVABLE PACKER? 15

Photo 1. Disassembled recovered packer Photo 2. Disassembled recovered packer showing


showing mandrel severed by chemical cutter mandrel severed by workstring-conveyed removing tool

Photo 3. Recovered packer using milling tool Photo 4. Disassembled recovered packer showing mandrel
severed by mechanical cutter and mud motor
16 M. T. TRIOLO, L. F. ANDERSON, M. V. SMITH SPE 76711

Photo 5. Disassembled recovered packer showing both


workstring-conveyed retrieving tool cut on mandrel and
chemical cut in bottom guide

Table 1. ISO 14310 Production Packer Design Validation Grades

Grade V6 Supplier/manufacturer defined test


Grade V5 Liquid pressure test
Grade V4 Liquid performance envelope
Grade V3 Liquid performance envelope with temperature cycling
Grade V2 Gas performance envelope
Grade V1 Gas performance envelope with temperature cycling
Grade V0 Gas performance envelope plus temperature cycling with zero bubble leakage

You might also like