Professional Documents
Culture Documents
Voyage planning
The voyage must be planned to ensure that the piece of cargo can be safely
transported from origin to destination. The points to be borne in mind are as
follows.
Some heavy-lift items are not fitted with any form of bedding arrangements
apart from foundations or legs upon which they would ordinarily stand. Others
will be completely cased in timberwork and will be provided with a timber floor
that is capable of taking and spreading the weight of the item, while others will
be fitted with cradles of limited strength. Information about the construction of
base-units is required so that appropriate arrangements can be made on board to
bed and support the item adequately and appropriately.
Stowage planning
When details of the base-structure or cradles are known, a suitable stowage
location can be chosen and suitable bedding material can be ordered. With
regard to the stowage location, the following points should be borne in mind.
• The accelerations generated by the ship are less low down at the mid-part of
the ship than they are further from that centre of motion. Heavy items of cargo
should, when possible, be stowed close to the ship’s centre of motion.
• Distribution of the weight of the item should be considered together with the
maximum permissible loading of the deck or tank-top on to which the piece is
to be stowed. The extent to which the weight of the item must be spread must
then be calculated and, from that, the bedding requirements can be assessed.
• The purpose of bedding is to provide a solid base onto which the item can be
placed and secured down onto and to distribute the weight of the unit evenly
over the stowage area so as to keep loading below the maximum permissible
loading rate. Also, bedding provides a high friction coefficient between the
cargo unit and the deck or tank-top.
• Of sufficient size such that its base has sufficient area to spread and load over
the deck to less than the maximum permissible loading.
• Of sufficient size such that its top has sufficient area to spread the weight of
the unit so that damage is not sustained by the unit when it is placed on the
support.
• Of sufficient rigidity such that it will not buckle or move after it has taken the
load.
• All of the above bearing in mind that the ship will roll and pitch in the seaway.
The rolling and pitching to be considered should be the most extensive motion
in the worst weather conditions likely to be encountered, bearing in mind the
ship’s GM for the voyage.
Securing planning
When the detail of a piece of heavy-lift or project cargo is known, calculations
can be carried out to determine how many lashings are required to secure the
cargo adequately against movement. Also, the required distribution of those
lashings can be assessed. Points to be borne in mind during such an assessment
are as follows.
• Calculations should be carried out to determine how many lashings of the type
decided upon are needed by use of the advanced calculation method or, if
insufficient information is available, by use of the rule-of-thumb method.
• The optimum lashing angle to act against sliding is about 25º to the horizontal,
whereas the optimum lashing angle to act against tipping is in the range 45–60º
to the horizontal.
On board a ship that often carries heavy-lift items or project cargoes, either as
part of the ISM procedures or within the Cargo Securing Manual, there might be
a checklist to be completed when a heavy or awkward piece of cargo is to be
loaded. The ship’s checklist should be used to ensure the completion of a safe
loading operation and a safe discharge operation. The following list covers all
the main points to be borne in mind by the master of a ship during an operation
where ship’s crane(s) will be used.
• Cranes and their wires to be checked to ensure they are in good operational
condition and any limits to be appropriately set.
• Briefing meeting to be held to ensure that all crew members are aware of their
duties and the procedures, and of the system of signals and orders. A dedicated
signalman to be appointed.
• Master to supervise the deck operation. If masters are not available, they
should delegate the duties to another deck officer.
• Chief engineer to supervise the ballasting operation. If chief engineers are not
available, they should delegate the duties to another engineer officer, but only
with the agreement of the master.
• Double-bottom tanks and other tanks with a large surface area to be full or
empty to avoid free surface. • Moorings to be checked and adequate, and to be
tended throughout the operation.
When all of the preparatory work has been completed the operation can be
started, but if any one of the items of the checklist has not been verified, the
operation should not begin. The master or master’s deputy must be and remain
in overall charge of the operation with the signalman in an appropriate position.
The lifting of the cargo unit should be steady and controlled and the hoist
wire(s) of the crane(s) must be vertical throughout the operation. When two
ship’s cranes are used in tandem, the operation should be carried out only in
daylight. Tag lines should be fitted to the cargo unit to allow control of any
rotational movement, if appropriate. The ballasting operation should be carried
out in conjunction with the cargo transfer operation to maintain the ship as near
to upright as possible, and any list should not exceed 3º.
If, when the cargo unit is first lifted from the quay, it is found that either the
weight is in excess of that declared or the centre of gravity is not where it is
shown to be such that the lifting points are incorrectly positioned, the operation
should be abandoned and the cargo unit should be carefully placed back on the
quay. The situation should then be carefully considered; expert advice should be
sought and further information should be obtained to devise a system for the
safe loading of the cargo unit. If a programme for the safe load of the unit
cannot be devised the cargo unit should not be loaded at all.
Sea fastenings, sometimes referred to as dogs, are lengths of steel section, for
example I-beam, which are welded to the deck plating or tank-top hard against
the base-structure of the item of cargo or with a small clearance to allow the
fitting of timber wedges or blocks. Timber shores, buttresses or chocking are
carefully constructed from good-quality timber of adequate cross-section and
are set up against the sides and ends of the item of cargo and against adjacent
items of cargo or against the ship’s structural members. Sea fastenings and
timber shores correctly set up at appropriate places around the base of the unit
will assist in the prevention of sliding of the unit in both the athwartships and
the fore-and-aft line. Timber shores and buttresses can also be fitted at high
level against the sides and ends of the unit to prevent it from tipping over.
The strength of sea fastenings and timber shores can be calculated and therefore
the load capacity of the fittings can be allowed for in any lashing calculation.
Sea fastenings are welded to the deck plating or tank-top and their strength is
determined from the area of welded connection. The welded connection should
be of good quality, with good penetration. Such a weld, of possibly three runs of
welding along each leg, should have a thickness of about 1 cm.
Assuming that all checks are in order, the chief officer would not normally
intervene with the lifting operation being controlled by the hatch foreman,
unless something untoward happened which would warrant intervention by
the ship’s officer. This is strictly a case of too many cooks could spoil a safe
loading operation.
NB: The main duties of the chief officer are to ensure that the vessel has
adequate positive stability and this can be improved by filling DB water
ballast tanks. Additionally, he should ensure that the derrick is rigged
correctly and that all moving parts are operating in a smooth manner.
The outcome of the load and causing an upward movement of ‘G’ is to cause G
to move towards M (the Metacentre. This action would be to effect a reduction
in the ship’s GM Value.
Once the weight of the load is taken by the ship’s derrick, chief officer should
appreciate that the ship’s “G” will rise towards ‘M’, probably even rising above
‘M’ causing an unstable condition. It would, therefore, make sense to lower the
position of ‘G’, in anticipation of the rising ‘G’ prior to a heavy lift being made.
If the GM can be increased before the lift takes place, i.e. by filling DB tanks,
the angle of the heel can be seen to be less.