BANAS BRIDGE AT

(564+764)KM

Abstract
Technical & Construction Advancement of PSC Girder on Box Girder (Banas Bridge)

ECO SPACE INFRASTRUCTURE PRIVATE LIMITED


Technical & Construction Advancement of PSC Girder on Box
Girder (Banas Bridge)
Due to site constants and enhance constructions quality and time line it is
recommended to go with PSC I Girder rather than box girder. Following comparison
may be noted for the satisfy our assumption.

BOX GIRDER PSC I GIRDER


If we go with the box girder it will be cast Precast PSC I girder can be erected by
in situ and hence, we have to provide crane. No staging requirement on river bed.
staging supporting form the river bed This lead to faster construction and better
which is very difficult and time consuming control over the time line. The in-situ Deck
with the project time line. slab casting can also be done without
staging with the help of precast plank.
The flow of water in river is non Pre -cast PSC I girder can be erected in very
predictable, hence providing staging from short time during no water flow time in the
river bed is non-operational in case of river
heavy water flow time.

Setting up base for staging in river bed is No Staging required as it is Precast.


very huge work and it requires special
technical requirements and time.

During the construction of existing The proposed casting yard is in the river of
bridges, the bed level was not deep but due bank only which saves transportation time.
to continues scouring in past years. The
level has been decreased which in results
increased height staging requirement

ECO SPACE INFRASTRUCTURE PRIVATE LIMITED