Professional Documents
Culture Documents
Sub structure: Sub-structure or Foundation is the lower portion of the building, usually
located below the ground level, which transmits the loads of the super-structure to the
supporting soil. A foundation is therefore that part of the structure which is in direct contact
with the ground to which the loads are transmitted.
Requirements Of Foundation:
1. The foundation of sub-structure distributes the load of the building evenly on the soil
in such a way that at not below the foundation the soil pressure exceeds the maximum
allowable bearing capacity of soil.
2. It helps in strengthening the building against the lateral forces caused due to tornado,
earthquake, etc.
3. It provides strong surface for the construction of proposed structure.
4. To provide safety to the structure from flow of water and seepage
Purposes of foundation:
1. To distribute loads of the structure over a large bearing area so as to bring intensity of
loading within the safe bearing capacity of the soil lying underneath.
2. To load the bearing surface at a uniform rate so as to prevent unequal settlement.
3. To prevent the lateral movement of the supporting material.
4. To secure the level and firm bed for building operations.
5. To increase the stability of the structure as a whole.
Factors affecting selection of foundations.
1. Types and intensity of loads acting on various parts of the structure which may be dead
load, live load, wind load, snow load, etc.
2. Nature and bearing capacity of the soil on which the structure directly rests.
Precast concrete:
Precast refers to the process of construction in which a concrete element is cast somewhere
other than where it is to be used. The other place may be somewhere else on the building site
or away from the site, probably in a casting yard or factory. The precast element may be pre-
stressed, may be of ordinary reinforced concrete, or may even be without reinforcement
Insitu construction:
“A process where concrete is poured into forms or moulds in the actual position in which the
concrete will permanently remain after the forms have been removed”
Before concrete is poured, formwork must be erected. Since the appearance of cast-in-
place concrete is directly dependent upon the quality of formwork, it means that
formwork must be coated with release agents to avoid the concrete sticking to
formwork.
In in-situ concrete construction the production of concrete is carried out on site and it
means large volumes of plant and equipment are to be hired or purchased and
operated. The cost of plant and machinery contributes greatly to the total cost of the
construction.
The fact that concrete production is done on site makes in-situ concrete construction
relatively slow as compared to precast or steel construction.
Structures built of in-situ concrete are said to offer a monolithic architectural
character. The monolithic nature means there is an even distribution of loads in all
directions. The structures are also rigid and therefore need no extra structural
resistance. However, because Insitu structures are built without movement joints there
is a likelihood of built-up stresses which may cause failure of concrete. Movement
joints are vital as they open and close up to relieve stresses in the concrete.
Longer-span portal frames can be cast in place using in-situ concrete.
The primary benefit of cast-in-place concrete is its high level of strength.
Cast-in-place concrete is appropriate for basement walls and home foundations. It is
also relatively resistant to structural damage in the event of an earthquake, flood or
other natural disaster.
Builders can make cast-in-place concrete even stronger by using steel reinforcement
bars, or rebar, which is inserted in the form before the concrete is poured in.