Professional Documents
Culture Documents
Project Crashing
Example Problem
3-2
Probabilistic Activity Times
a m b
3-3
Probabilistic Activity Times
3-4
Probabilistic Activity Times
Critical path: 1- 2 – 4 -7
9 months
Figure 3.2. Normal Distribution of Network Duration
3-8
Probability Analysis of a Project Network
What is the probability that the new order processing system will
be ready by 10 months?
µ = 9 months
2 = 0.36 = 0.6 months
Z = (x-)/ = (10 -9)/0.6 = 1.67
Z value of 1.67 corresponds to probability of 0.9525 in Table 3.2.
Probability of completing project in 10 months or less = 0.9525.
3-9
Probability Analysis of a Project Network
Table 3.2
3-10
Probability Analysis of a Project Network
10 months)
9
months
10 months
3-12
Probability Analysis of a Project Network
8 months) = .0475
.4525
8 9
months months
Figure 3.4. Probability the Network will be completed in 8 months
or less.
3-13
Project Crashing
3-14
Project Crashing
Cashing Process
3-15
Project Crashing
Prepare data
3-17
Project Crashing
Crash cost & crash time have a linear relationship:
Total Crash Cost $2000
Total Crash Time 5 weeks
$400 / wk
Figure 3.6
3-18
Project Crashing
Prepare data
Critical path: 1 – 2 – 4 - 7
1-19
Project Crashing
2 C4 = $7.000
C1 = $400
4
1 C7 = $7.000
Cashing required
1. Cashing in Critical path activities
2. In Alowable cash time
3. Minimum cost activity
3-21
Project Crashing
Implement Cashing
Project Period Cum.
Act. 1 2 3 4 5 6 7
time cost cost
36 0 0
35 400 400 1
34 400 800 2
33 400 1200 3
32 400 1600 4
31 400 2000 5
30 500 2500 5 1
29 500 3000 5 2
28 500 3500 5 3
27 7000 10500 5 3 1
26 7000 17500 5 3 2
25 7000 24500 5 3 3
24 7000 31500 5 3 3 1
3-22
Project Crashing
Project data
Normal Cach Allowab Cask
Prioritie Normal Cash
Activity time time le Cash Cost per
s Cost Cost
(weeks) (weeks) time Week
1 - 3 1 120 100 2 $10
2 1 2 1 60 56 1 $4
3 1 3 1 80 72 2 $4
4 2, 3 2 1 120 110 1 $10
C2 = $4
Net work 2
C1 = $10 2 C4 = $10
1 4
C3 = $4
3 2
3
3
3-23
Project Crashing
3
3-24
Project Crashing
3-26
Example Problem
3-27
Example Problem
Solution
Step 1: Compute the expected activity times and variances.
2
b -
a
t a 4m b v
6 6
3-28
Example Problem
Step 2: Determine the earliest and latest activity times & slacks
3-29
Example Problem
3-30
Example Problem
3-31
Home work
Precedence Relationships Chart
Immediate
Activity Optimistic Most Likely Pessimistic
predecessor
A - 76 86 120
B A 12 15 18
C B 4 5 6
D G 15 18 33
E D 18 21 24
F A 16 26 30
G C, F 10 13 22
H D 24 28 32
I A 22 27 50
J D, I 38 43 60
a. Find Critical Path?
b. Percentage of that we finish the project longer than mean-time 2 units?
3-32
Home work