Professional Documents
Culture Documents
Production planning
categories.
Scheduling. Sequencing tool
Job/ A B C D E
Mach
M1 5 7 6 9 5
M2 2 1 4 5 3
M3 3 7 5 6 7
Scheduling. Sequencing
Solution.
Find the
4. Minimum time on Machine M1 = 5hrs.
5. Maximum time on Machine M2 = 5hrs.
6. Minimum time on Machine M3 = 3hrs.
Scheduling. Sequencing
Then compare
Min time on M1 is it(> or =) Max. time on M2.
Or
Min time on M3 is it(> or =) Max. time on M2.
If any one of the condition is true, the you
can proceed ahead, or else there is no
optimal solution for this problem.
Scheduling. Sequencing
If
any of the condition is satisfied,
Then we need to add various jobs on M1 and
M2 first and after that add jobs on M2 and
M3.
Jobs-> A B C D E
Mach.
M1&M2 7 8 10 14 8
M2&M3 5 8 9 11 10
Scheduling. Sequencing
E B D C A
Scheduling. Sequencing
Solution
Class assignment.
JOB/ A B C D E F
Mach.
M1 4 8 3 6 7 5
M2 6 3 7 2 8 4
M3 8 9 9 8 8 9
Scheduling. Gantt Chart tool
Gantt Charts.
Gives the details about planned production
and actual performance over a period of time
Its an imp. tool to schedule a project and
represent its progress report.
It is a rectangular chart divided by parallel
horizontal and vertical lines.
Scheduling. Gantt Chart tool.
Rules observed.
Situation.
Let there be an operation A which should
start on 5th day of a month, finish on 14th day,
and another operation should start on 9th day
and finish on 20th day of the same sequence.
It is observed that only 50% of A work is
completed on 11th day while operation B was
only 30% complete up to 11th day. Draw
Gantt chart for the same.
Scheduling.
Classassignment.
Draw Gantt chart for situation no.1 in
sequencing tool.
PROBLEM
Scheduling. Network Analysis.
Network
Mgt has to plan variety of tasks and
situation.
Some are repetitive and others are NOT.
Tech of sequencing and Gantt chart cannot
be applied as these task are complicated.
These non-repetitive and complicated tasks
have special characteristics.
Scheduling. Network Analysis.
Network analysis.
Study of Network Diagrams is known as
Network Analysis.
Technique of network analysis in study of
project is one of the most promising strategy.
These techniques are beneficial and effective
in closing the gap between the PROMISE
and PERFORMANCE.
Scheduling. Network Analysis.
Objectives.
2. To complete the project in stipulated time.
3. OUR
4. Min of cost and time required.
5. Min of idle resources and inventory.
6. Identify bottle necks and focus on critical
activity.
7. Reduce the cost of setup and changeovers.
Scheduling. Network Analysis.
Applications of Networks.
Basically applied on large-scale
complicated projects involving admin
problems.
3. Const. of building, dam, factories, roads.
4. Manufacturing of ships airplanes.
5. Public works and defense operations.
6. In factories with voluminous production.
Scheduling. Network Analysis.
PERT,
Objectives of CPM
2. Determine route between the operations.
3. Locate obstacles and difficulties involved in
production process.
4. Assign starting time and finishing time for
each operation.
5. Find critical and non-critical path and min
time duration.
Scheduling. NW. CPM
Advantages of CPM
2. It is analytical and helps to achieve the
project objectives.
3. Identify the critical element and pay more
attention to it.
4. Avoid waste of time, money and energy on
unimportant activity.
5. It paves a Standard method for calculating
costs, plans and schedules.
Scheduling. NW. CPM
Features of PERT
2. Draws the network diagram for project.
3. 3 time estimates are used.
Viz. Optimistic, Normal and Pessimistic.
5. The 3 time estimates are used to calculate
the expected time of each activity.
6. Critical path and Slack time are computed.
Scheduling. NW. PERT
Contd..
2. The 3 time estimates are given by person in
charge of operation, which are based on
Experience and Judgment.
3. The time are assumed to follow beta
distribution.
Scheduling. NW. PERT
Mean = t1 + 4t2 + t3 / 6
with
Variance = (t3-t1/6)2
Scheduling. NW. PERT
Limitations of PERT
Expected time and variances are only
approx. values which may not be true.
The assumption of beta distribution is
difficult to be valid in practice.
Scheduling. Run-Out Approach
RUN-OUT Approach
This method is applicable to production that
is geared up to inventory level.
It is demand oriented and tries to minimize
stock out by assigning the highest priority to
items, which are in danger of running out.
Calculation is simple.
Method. (C on board)
Loading.
LOADING
Management must know when a particular
machine is available for operation.
For this, info on machines and list of works is
made.
Evaluation done by planning staff, regarding
capacity and its work load.
Loading.
Definition
Objectives of loading.
2. Plan new work order on basis of spare
capacity.
3. Balance the workload.
4. Maintain the delivery promises.
5. To check the feasibility of production
programs.
Loading. Devices.
Loading Devices.
Machine loading.
Use the info from schedules to prepare the
machine load chart.
It gives the time for which the machine is
busy for different works.
Shows the machine capacity and spare
capacity to avoid it and reduce the idle
resource. Ultimately reduce the costs.
Loading. Load Charts.
Load Charts.
Load chart shows the work assigned to
various departments, machines, components
and tools.
During the period of heavy load the
information of the load chart is used for the
following purposes.
Loading. Load Charts.
Production Management.
Production Planning.
Production planning involves,