You are on page 1of 5

PTI Journal Viewpoints

THE NEW ACI STANDARD SPECIFICATION FOR


UNBONDED TENDONS

By

KEN BONDY

Authorized reprint from: August 2015 issue of the PTI Journal


Copyrighted © 2015, Post-Tensioning Institute
All rights reserved.
VIEWPOINTS

THE NEW ACI STANDARD SPECIFICATION FOR


UNBONDED TENDONS

BY KEN BONDY

INTRODUCTION ment to grip the strand. At the stressing anchorage, the


The American Concrete Institute (ACI) recently tendon sheathing was removed to allow the unsheathed
published a new Standard, “Specification for Unbonded strand to pass through the anchorage, resulting in a length
Single-Strand Tendon Materials (ACI 423.7-141).” This is of exposed unsheathed strand (shorter than at the fixed
an extremely important document with major ramifications anchorage) behind the stressing anchorage. This removed
for the post-tensioning (PT) industry. It is a referenced portion of the tendon sheathing was never replaced.
standard in Section 3.2.2 of the ACI Building Code (ACI Some of the early encapsulation systems still employed
318-142). As a referenced part of the Code, the Specifica- the use of the “pull” system, which required long and large-
tion becomes law when ACI 318 is adopted by a munici- diameter sleeves to cover the strand that was exposed
pality. This article focuses on Section 6.5.2(c) in the new where the tendon sheathing had been removed. These
Specification,1 dealing with encapsulated systems, which long and large-diameter sleeves resulted in a potential
are now required to be used in all buildings governed by collection point for water. However, improvements over
ACI 318 and ACI 350. Section 6.5.2 is repeated herein in the past several years have resulted in encapsulation
its entirety: systems that use a “push” system for wedge seating at fixed
6.5.2—Connection component anchorage and sleeves that have an inside diameter only
Any component used to connect the sheathing to any anchorage a few millimeters larger than the outside diameter of the
or coupler enclosure shall conform to the following: tendon sheathing. The push-wedge seating at the fixed
(a) Have a watertight, mechanical connection to the anchorage requires that the sheathing only be removed in
anchorage protection or coupler enclosure and a the short length where the wedge is in contact with the
watertight connection at the tendon sheathing. strand. At stressing anchorages, the tendon sheathing
(b) Have a minimum 4 in. (100 mm) overlap between extends through the anchorages and is cut at the jobsite
the end of the extruded sheathing covering the close to the back of the anchorage. Therefore, in the encap-
prestressing steel and the end of the sleeve. sulation systems currently used, there is normally only a
(c) W
 ithin the connecting component or enclosure, short length of exposed strand within the transition tube,
either the prestressing steel shall be covered by resulting from sheathing material shrinkage and handling
sheathing for its full length, or the annular space of the tendons during installation.
between the sleeve and the strand shall be filled Let us return now to the main topic. In the previous
with PT coating in conformance with 5.2. edition of the Specification (ACI 423.7-073), the equiva-
Subsection 6.5.2(c) is underlined because it is the lent section for encapsulated systems is repeated as follows,
subject of this discussion. This part of the Specification with the relevant subsection underlined:
has a long and tortured history, which will be documented 2.5.2.1—Sleeves to anchorages
herein. Some background on the development of encap- Sleeves used to connect the sheathing to the anchorage of
sulated anchorages is useful in understanding the issue. encapsulated systems shall:
Before encapsulated anchorages were developed, the (a) 
Meet or exceed the same requirements as the
normal procedure was to “pull” the wedge into the fixed sheathing for durability during fabrication, trans-
anchorage, which required removing approximately 12 in. portation, handling, storage, and installation;
(300 mm)of tendon sheathing to allow the plant equip- (b) Have 0.050 in. (1.27 mm) minimum thickness;

PTI JOURNAL | August 2015 75


VIEWPOINTS
(c) Have a positive mechanical connection to the format with no Commentary, so the wiggle-room wording
anchorage at all stressing, intermediate, and of Section R2.5.2.1(e) was no longer available. This
fixed ends; problem was first addressed by the PTI Committee M-10,
(d) Have a minimum 4 in. (100 mm) overlap between Unbonded Tendon, at its meeting in San Diego, CA, on
the end of the extruded sheathing covering the Oct. 4, 2007, when a Task Group was formed to look into
prestressing steel and the end of the sleeve; the “free of voids” problem and suggest a solution. The
(e) Be translucent or have another method of verifying that Task Group reported back to PTI Committee M-10 in their
the post-tensioning coating material is free of voids; next meeting in St. Louis, MO, on May 6, 2008, saying that
(f) Be translucent or have other method of verifying the word “void” could not be defined or quantified in this
overlap with sheathing; and context and should not be used in the Specification. The
(g) Have sleeves on stressing side of intermediate Task Group was dissolved, with thanks, at that meeting
anchorages long enough to cover sheathing removed and the issue was referred to PTI Committee DC-70,
during stressing and have required 4 in. overlap. Special Topics, for their recommendations.
ACI 423.7-07 included a Commentary to the Speci- PTI Committee DC-70 is unique among PTI technical
fication. The Commentary to the underlined Section committees, which can be seen from its Mission Statement:
2.5.2.1(e) stated: “Review and develop recommendations on
R2.5.2.1(e)—The requirement that prohibits voids may be topics that are not within the scope of other
satisfied by filling the sleeves with post-tensioning coating. Transi- committees or require special attention.”
tion components, such as sleeves, at anchorages and couplers should At the time this issue was deliberated within PTI
be designed to be void-free. Some small bubbles and air spaces are Committee DC-70, the eight members of the committee
normal and unavoidable in the fabrication and assembly process had a combined total of over 300 years of experience in
and should not normally be considered as “voids” in the context of the design and construction of post-tensioned concrete.
this section. The membership included three PTI Legends, eight PTI
ACI 423.7-07 was heavily influenced by PTI’s “Speci- Fellows, and two PTI Presidents. There simply was no
fication for Unbonded Single Strand Tendons,” published more credible place in which to resolve this issue.
in 2000,4 with cross-membership (including the author) PTI Committee DC-70 studied the problem at length,
between ACI Committee 423 and the PTI Unbonded and reported its recommended wording for this Specification
Tendon Committee (now PTI Committee M-10). Section at Committee M-10’s meeting in Portland, OR,
Section 2.2.6.2 in PTI M10.2-004 is almost identical to on May 4, 2009. The recommended change to the relevant
Section 2.5.2.1 of ACI 423.7-07. 423.7-07 Section was as follows:
Committee members who contributed to the writing “Within the connecting component or enclosure,
of both PTI M10.2-004 and ACI 423.7-07 were well aware prestressing steel shall be either covered by
of the problem with the impossible term “free of voids,” sheathing for its full length, or be in full contact
which appeared in the mandatory portion of both documents with PT coating in conformance with X.X where
(it was “absence of voids” in the PTI Specification4). sheathing is not present.”
Obviously no material is completely free of voids, and PTI Committee DC-70 commented on its recommen-
interpreted literally, this could mean that the Specifica- dation with a footnote: “The word ‘void’ is not used. The
tions were unenforceable because no connection compo- word ‘sleeve’ is not used. The specification states what we
nent could satisfy them. Attempts were made to establish want, not what we don’t want.”
a tolerance on “voids,” but each failed to reach a consensus This PTI Committee DC-70 recommendation came
agreement, mainly due to the impossibility of measuring after much discussion among its highly experienced
and/or quantifying the amount of voids present in a sleeve. membership. I am a member of PTI Committee DC-70,
However, it was felt that the ACI 423.7-07 Commentary to I have considerable background in the specific issue, and I
Section 2.5.2.1(e) (and a similar Commentary statement was heavily involved in the discussion. My contribution is
in PTI M10.2-004) provided sufficient wiggle room for summarized as follows:
relief from the “free of voids” requirement. In the middle of the 1960s, long before encapsulated
That reasoning changed in a big way when ACI 423.7-07 anchorages were introduced, I was employed by Atlas
was revised. Sometime after 423.7-07 was developed, ACI Prestressing Corp., the company that introduced the
decided to write all of its future Specifications in ASTM wedge/strand post-tensioning system to the industry. On

76 August 2015 | PTI JOURNAL


VIEWPOINTS
some of the early Atlas projects in Los Angeles, CA, the corrosion resistance is provided in the connectors if it can
city inspectors would question the fact that the end of the be visually verified that the strand is simply in contact with
tendon sheathing did not extend to the back side of the PT coating for its full unsheathed length.
stressing or fixed anchorages, leaving a short portion of The revisions to ACI 423.7-07 proceeded within ACI
strand exposed with no sheathing (as discussed previously). Committee 423 in ASTM format, including the following
We tried to justify this by explaining that the PT coating wording of Section 6.5.2(c), which incorporated the DC-70
(we called it grease back then) was still present on the recommendation:
strand in this exposed length, and the grease provided the 6.5.2(c)—Within the connecting component or enclosure,
primary corrosion protection for the strand. The inspectors prestressing steel shall be either covered by sheathing for its full
would counter with, “…that’s fine, but what if somebody length, or be in full contact with PT coating in conformance with
steps on the exposed strand and wipes off the grease?” X.X where sheathing is not present.
We had no satisfactory answer to that, so we conceived an ACI 423.7-07, with that wording, was approved by the
in-house testing program, observed by the city inspectors, full ACI Committee 423 and the ACI Technical Activities
to address it and see if it was a valid concern. Committee (TAC). After ACI Committee 423 and TAC
We obtained a number of strand samples with PT approval, the document was put out to public comment
coating, which had been applied in our fabrication process. (part of the ACI Standardization process). A comment was
On some of the samples, we vigorously removed the PT received (from an individual outside of the PT industry)
coating using shop rags. We dug the rags into the interstices who disagreed with the “full contact” requirement, and
between the wires, removing as much grease as we could felt that the connecting components should be fully filled
until there was no visual evidence that there was ever any with PT coating. In a virtual meeting to resolve responses
grease on the strand. The inspectors agreed that this was to public comments, held on Sept. 11, 2014, Joint ACI-
more than the equivalent of a field worker stepping on the ASCE Committee 423, after much discussion and some
short exposed length of strand in the field. We then ran dissent among the members, voted to revise the wording
salt fog tests (ASTM B117*) on samples with undisturbed of Section 6.5.2(c) to the following, which is the way it
PT coating of normal thickness, and samples with the PT currently appears in the published version of ACI 423.7-141:
coating intentionally removed as described. The results of 6.5.2(c)—Within the connecting component or enclosure,
the salt fog tests were the same on all the samples. After either the prestressing steel shall be covered by sheathing for its full
1000 hours of salt fog exposure, the visible corrosion length, or the annular space between the sleeve and the strand shall
product (in accordance with ASTM D610) on the undis- be filled with PT coating in conformance with 5.2.
turbed samples was indistinguishable from the visible So after 8 years and many hundreds of hours of discus-
corrosion product on the samples where PT coating had sion within several PTI and ACI committees, we have
been intentionally and vigorously removed, and both come full circle. One public comment from one individual,
passed the tests. from outside the PT industry, has reversed years of discus-
We concluded from these tests, and the city inspectors sion, deliberation, voting, and approvals from the most
agreed, that the short length of exposed and greased strand experienced minds in the industry, and we are now back
behind the anchorages would not affect the functionality to filling the sleeves with PT coating, with an implication
or performance of the tendons, and that issue was forever that the PT coating must be free of voids.
put to bed. I have been deeply involved in the entire process
In the PTI Committee DC-70 discussions, I used the described previously (Chair of PTI Committee M-10
results of these old tests to support the argument that a at the relevant times, and a member of PTI Committee
short length of strand, which is visually verifiable to be in DC-70 and Joint ACI-ASCE Committee 423 at all times)
contact with PT coating, will have corrosion resistance and I have the following personal opinions, comments,
equivalent to the same length of strand with the thickness of and recommendations:
PT coating normally applied in fabrication of the tendon. Filling the connecting components with PT coating
In other words, it is not necessary to completely fill the is not necessary for corrosion protection of the strand.
connecting components with PT coating. Adequate Acceptable corrosion protection of any exposed strand
within the sleeve of an encapsulated anchorage is achieved
*
One of the tests required by ACI 423.7-14 for approval of PT coating,
if the exposed strand can be seen to be in contact with PT
along with ASTM D610 (See Table 7.2.1, Test #5) coating for its full length.

PTI JOURNAL | August 2015 77


VIEWPOINTS
Filling sleeves at the jobsite is a time-consuming, REFERENCES
unnecessary step that is problematic during construction 1. Joint ACI-ASCE Committee 423, "Specification for
and can lead to long-term problems if the sleeves are overfilled. Unbonded Single-Strand Tendon Materials (ACI 423.7-07),"
While the wording of Section 6.5.2(c) does not American Concrete Institute, Farmington Hills, MI, 2007,
contain the offensive term “free of voids,” the requirement 21 pp.
that the components be “filled with PT coating” implies 2. ACI Committee 318, "Building Code Requirements
that and puts the tendon supplier at some risk, either of for Structural Concrete (ACI 318-14) and Commentary,"
system approval or subsequent litigation. American Concrete Institute, Farmington Hills, MI, 2014,
519 pp.
The PTI Committee DC-70 recommendation eliminates 3. Joint ACI-ASCE Committee 423, "Specification for
the possibility that the Specification could be used for Unbonded Single-Strand Tendon Materials (ACI 423.7-14),"
proprietary reasons. Filling the connecting components American Concrete Institute, Farmington Hills, MI, 2014,
with PT coating, albeit unnecessary, may present diffi- 8 pp.
culties for some otherwise fully functional encapsulation 4. PTI Committee M-10, "Specification for Unbonded
systems. The “full contact” recommendation from PTI Single Strand Tendons (PTI M10.2-00)," Post-Tensioning
Committee DC-70 solves the problem. Institute, Farmington Hills, MI, 2000, 36 pp.
In conclusion, I would strongly urge the members of
the PTI Committee M-10 and Joint ACI-ASCE Committee
Ken Bondy has specialized in the design and construc-
423 to reconsider the wording of this subsection and
return it to the fully adequate, workable, non-proprietary,
tion of post-tensioned concrete buildings for 50 years.
and risk-free wording recommended by the PTI Special He is a Charter Officer and Director of the Post-
Topics Committee. Tensioning Institute (1976), a PTI Legend, Past Pres-
ident, Fellow, Lifetime Member, and former member of
the Technical Advisory Board (TAB). Now retired, he
is a licensed civil and structural engineer in California
and has been licensed in many other states.

Purchase Publications and Register for Events


on the PTI Store
The PTI Store makes it easier than ever to find the events and publications that interest you most. In
addition, when purchasing a publication, you will have the ability to select the quantity, format (print or
digital), and purchase additional licenses for digital publications—all with a simplified drop-down menu.

.6-15 PTI DC35.1-14


PTI M10

ed Recommendations
Unbond
ation for ons for Prestressed
Specific
rand Tend und
Single St ro Rock and Soil Anchors
Used for
Constru
Slab-on-G
ction http://www.post-tensioning.org/store

78 August 2015 | PTI JOURNAL

You might also like