PT PLN (PERSERO) No Formulir :

Revisi : 00
UNIT INDUK PEMBANGKITAN SUMATERA BAGIAN UTARA Tanggal : 27 - 10 - 2017
UNIT PELAKSANA PEMBANGKITAN NAGAN RAYA Halaman :
LAMPIRAN KURVA - S

Kurva S - Simple Inspection PLTU Unit 2


28 September - 24 November 2021
100%

90%

80%

70%
Progress Pekerjaan (%)

60%

50%

40%

30%

20%

10%

0%
Hari ke- 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58
Rencana 0.1 0.2 0.3 1.1 1.9 4.3 8.4 12. 15. 19. 24. 28. 32. 36. 41. 45. 49. 53. 57. 60. 64. 68. 71. 74. 78. 81. 84. 87. 89. 90. 90. 91. 91. 92. 92. 92. 93. 93. 94. 94. 95. 96. 96. 96. 97. 97. 97. 97. 97. 97. 97. 97. 97. 98. 98. 99. 99. 100
Realisasi 0.1 0.2 0.3 1.1 2.2 4.7 8.6 12. 16. 22. 27. 29. 34. 37. 42. 45. 50. 55. 58. 60. 65. 69. 72. 75. 78. 81. 84. 87. 89. 90. 90. 91. 91. 92. 92. 93. 93. 93. 94. 95. 95. 95. 96. 96. 96. 96. 96. 96. 97. 97. 97. 97. 97. 97. 97.

Prosentase Progress Pekerjaan


Rencana : 98.50%
Realisasi : 97.84%
Lagging : -0.66%