selecting bell-and-spigot (lap) joints or rubber ring jointed pipe.
Butt-welded pipe is the preferred
method in these areas. c) Specially designed flexible joints shall be provided at all junctions between pipes and rigid structures (such as reservoirs, pump stations, bridges, and buildings) where pipe flexibility alone is not adequate to accommodate movement. d) Where structures are closely spaced such as at pump stations, base isolation of the area may be considered where minor actions are expected. Connecting to the base isolation area requires a flexible connection. e) Flexible connections or other mechanical joints must not be located under any structures and must be accessible for repair or replacement. f) Acceptable fuse locations must be designed where service breaks can be easily repaired to minimise disruption instead of compromising key infrastructure such as pump stations, plants and valve stations.
12. Maintaining structural integrity against corrosion
12.1 Corrosion protection systems
12.1.1 Tape systems
a) Buried steel pipe shall be tape wrapped with an accepted system to protect the pipe material in the buried environment. b) Pipe transitioning into chambers shall be wrapped a minimum of 150mm past the chamber wall and overlapping onto the painted surface. c) Pipe transitioning to an above surface pipe shall be wrapped at least 200mm past the soil to surface interface and onto the painted surface. The tape system shall be over-layered with a UV-stabilised tape system over the existing tape to 200mm into the buried section and a minimum of 50mm onto the painted steel.
12.1.2 Paint systems
a) Steel pipe that is exposed, such as in chambers or on pipe bridges shall be painted with a suitable epoxy corrosion protection system. b) The appropriate system shall be determined with input from a coatings engineer and identify the site specific macro and micro environments. The designer must complete the project schedule in the Material Supply standard and provide this to the coating supplier to support the coating selection.
12.1.3 Cathodic protection systems for metallic pipes
a) For the electrical design of cathodic protection systems refer to the Watercare electrical design standard. The design must be determined with considerations to the site ground conditions and in consultation with a cathodic protection designer. b) All joints of steel pipelines shall be electrically bonded. c) Isolation joints and test stations shall as far as practicable be located at main line valve installations. d) Anode beds shall as far as practicable be near main line valve installation.
12.1.4 Internal corrosion protection
a) Internal corrosion protection of pipe and fittings must consider the whole of life of the asset and choosing the appropriate method that considers re-application or repair of the lining system. b) Metallic pipe is typically protected using a concrete lining solution.
Ver.1.1 This is an electronic ESF document that
is uncontrolled when copied or printed Page 68 of 70