Professional Documents
Culture Documents
4 ONGC v. Saw Pipes (2003) 5 wherein a contract has provisions for liquidated
SCC 705 damages, such amount can be received in totality
Relied on Kailash Nath only if the amount of damages suffered by the
Associates v. Delhi aggrieved party is similar to such pre-established
Development Authority and amount of damages. The court further observed
Another (2015), that the quantum of damages awarded by the court
should at no point exceed the amount mention in
the contract in the form of liquidated damages
MSK Projects (I) (JV) Ltd. Even in the presence of pre-determined sum of
v. State of Rajasthan (2011) reward as liquidated damages, the court will take
10 SCC 573 into consideration factors such as mitigation of
losses, reasonability of the sum, and other facts and
circumstances so as to ensure that the aggrieved
party is compensated adequately but not over
compensate so as to prevent any occurrence of
profit to the aggrieved party as a result of breach of
the said contract.
5 DDA v. Naraindas R. Israni There is no gainsaying that the amount of
(2007 Delhi HC) compensation payable under Clause 10CC is
limited to the increase in the prices of materials
and stores and/or wages of labour required for
execution of the work. The clause does not either
forbid the contractor from making a claim nor does
the same provide for any formula or mechanism
for determination of compensation on account of
factors other than those that are specifically
mentioned in the clause. This would necessarily
mean that if in addition to increase in the prices of
materials and stores and wages of labour required
for execution of the work, the contractor suffers
any damages on any other account as for instance
on account of idle plants and machinery,
scaffolding etc. or on account of blocked capital
resulting in loss of profit or staff either posted on
the work site or otherwise, he can make a suitable
claim for payment on that account. Any such claim
arising out of a breach of the agreement executed
between the parties can be examined and awarded
by the arbitrator depending on the evidence that the
contractor may adduce to prove any such loss.