Professional Documents
Culture Documents
(Assignment #1)
JD - II
FACTS:
On October 14, 1997, PGSMC entered into a Contract of Lease with Worth
Properties, Inc. (Worth) for use of the latter's property as the former's
warehouse building to house the LPG manufacturing plant. However, after
the installation of the plant, the initial operation could not be conducted as
PGSMC encountered financial difficulties affecting the supply of materials,
thus forcing the parties to agree that KOGIES would be deemed to have
completely complied with the terms and conditions of the March 5, 1997
contract.
For the remaining balance for the installation and initial operation of the
plant, PGSMC issued two postdated checks. When KOGIES deposited the
checks, these were dishonored for the reason "PAYMENT STOPPED." Thus,
on May 8, 1998, KOGIES sent a demand letter to PGSMC threatening
criminal action for violation of Batas Pambansa Blg. 22 in case of
nonpayment.
On May 14, 1998, PGSMC replied that the two checks it issued KOGIES were
fully funded but the payments were stopped for reasons previously made
known to KOGIES.
On June 1, 1998, PGSMC informed KOGIES that PGSMC was canceling their
Contract on the ground that KOGIES had altered the quantity and lowered
the quality of the machineries and equipment it delivered to PGSMC, and
that PGSMC would dismantle and transfer the machineries, equipment, and
facilities installed in the Carmona plant. Five days later, PGSMC filed before
the Office of the Public Prosecutor an Affidavit-Complaint for Estafa against
Mr. Dae Hyun Kang, President of KOGIES.
On June 15, 1998, KOGIES wrote PGSMC informing the latter that PGSMC
could not unilaterally rescind their contract nor dismantle and transfer the
machineries and equipment on mere imagined violations by KOGIES. It also
insisted that their disputes should be settled by arbitration as agreed upon in
Article 15, the arbitration clause of their contract.
On June 23, 1998, PGSMC again wrote KOGIES reiterating the contents of its
June 1, 1998 letter threatening that the machineries, equipment, and
facilities installed in the plant would be dismantled and transferred on July 4,
1998. Thus, on July 1, 1998, KOGIES instituted an Application for Arbitration
before the Korean Commercial Arbitration Board (KCAB) in Seoul, Korea
pursuant to Art. 15 of the Contract as amended.
On July 9, 1998, PGSMC filed an opposition to the TRO arguing that KOGIES
was not entitled to the TRO since Art. 15, the arbitration clause, was null
and void for being against public policy as it ousts the local courts of
jurisdiction over the instant controversy.
The trial court denied the application for preliminary injunction and
declaredthe arbitration agreement null and void. Korea Tech moved to
dismiss the counterclaims for damages.
Korea Tech filed a petition for certiorari before the Court of Appeals (CA).
The court dismissed the petition and held that an arbitration clause which
provided for a final determination of the legal rights of the parties to the
contract by arbitration was against public policy. Further appeal was made to
the Supreme Court by way of a petition for review.
ISSUE:
HELD:
Established in this jurisdiction is the rule that the law of the place where the
contract is made governs. Lex loci contractus. The contract in this case
was perfected here in the Philippines. Therefore, our laws ought to govern.
Nonetheless, Art. 2044 of the Civil Code sanctions the validity of mutually
agreed arbitral clause or the finality and binding effect of an arbitral award.
Art. 2044 provides, Any stipulation that the arbitrators award or decision
shall be final, is valid, without prejudice to Articles 2038, 2039 and 2040.
It has not been shown to be contrary to any law, or against morals, good
customs, public order or public policy. The arbitration clause stipulates that
the arbitration must be done in Seoul, Koreain accordance with the
Commercial Arbitration Rules of the KCAB, and thatthe award is final and
binding. This is not contrary to public policy. The Court finds no reason why
the arbitration clause should not be respected andcomplied with by both
parties.
This ruling is consonant with the declared policy in Section 2 of the ADR Act
that “the State (shall) actively promote party autonomy in theresolution of
disputes or the freedom of the parties to make their ownarrangements to
resolve their disputes.” Citing Section 24 of the ADR Act, the Court said the
trial court does not have jurisdiction over disputes that areproperly the
subject of arbitration pursuant to an arbitration clause. In the earlier case of
BF Corporation v. Court of Appeals and Shangri-la Properties, Inc., where
the trial court refused to refer the parties to arbitration notwithstanding the
existence of an arbitration agreement between them, the Supreme Court
said the trial court had prematurely exercised its jurisdiction over the case.
FACTS:
Parties entered into another agreement named “Agreement for the Execution
of Builders Work for the EDSA Plaza Project” (3rd agreement) that would
cover the construction work on said project as of May 1, 1991 until its
eventual completion. Upon SPI's initiative, the parties' respective
representatives met in conference but they failed to come to an agreement.
Because of this, BF filed with the RTC of Pasig a complaint for the collection
of the balance due under the construction agreement. Named Defendants
therein were SPI and members of its board of directors.
The RTC found that the arbitration clause did exist, however the lower court
denied motion to suspend proceedings and ruled in favor of BF. This was
because: (1) despite the fact there was an arbitration agreement, the
Conditions of Contract only the initials of Bayani Fernando was present,
while no signature on the part of SPI; (2) There were no signed documents
to prove SPI’s claims thus there is serious doubt to the validity of the
arbitration clause found in the Conditions of Contract; and (3) Assuming that
the arbitration clause was valid and binding, it was too late for SPI to invoke
arbitration because the demand should have been made before the time of
final payment except as otherwise expressly stipulated in the contract. The
court found that the project was to be completed on Oct 31, 1991 and any
delays would incur 80K for each day of delay from Nov 1, 1991 with liquefied
damages up to a maximum of 5% of the total contract price the court found
out that the project was completed in accordance with the agreement and
SPI had took possession and started operations thereof by opening the same
to the public. BF billed SPI the total amount of P110,883,101.52 contained in
a demand letter sent on Feb 17, 1993. Instead of paying the amound
demanded, SPI set up its own claim of P220,000,000.00 and scheduled a
conference on that claim for July 12, 1993. The conference took place but
was futile.
SPI filed a motion for reconsideration but was denied because of lack of
merit and directed the other defendants to file their responsive pleading
within the reglementary period.
Instead of filing an answer to the complaint, SPI filed a petition for Certiorari
under Rule 65 before the Court of appeals. The Court of Appeals granted the
petition and annulled and set aside the orders and stayed the proceedings in
the lower court.
According to the contract the project manager and the contractor should
coordinate with the owner, should there be failure to resolve differences,
dispute shall be submitted for arbitration. Although it was only the initials of
Bayani Fernando and De La Cruz present and none from SPI, it does not
affect its effectivity. BF categorically admitted that the document is the
agreement bewtween the parties, the initial signature of BF representative to
signify conformity to arbitration is no longer necessary. The parties should
be allowed to submit their dispute to arbitration in accordance with their
agreement. Demand for arbitration was made within a reasonable time after
the dispute has arisen and attempts to settle amicably has failed. This was
evidenced by the fact that such demands were acted upon only months.
ISSUE:
Whether the contract for the construction of the EDSA Plaza between
petitioner BF Corporation and respondent Shangri-la Properties, Inc.
embodies an arbitration clause in case of disagreement between the parties
in the implementation of contractual provisions.
HELD:
The Court finds that, upon a scrutiny of the records of this case, these
requisites were complied with in the contract in question. The Articles of
Agreement, which incorporates all the other contracts and agreements
between the parties, was signed by representatives of both parties and duly
notarized. The failure of the private respondents representative to initial the
`Conditions of Contract would therefore not affect compliance with the
formal requirements for arbitration agreements because that particular
portion of the covenants between the parties was included by reference in
the Articles of Agreement. Petitioners contention that there was no
arbitration clause because the contract incorporating said provision is part of
a hodge-podge document, is therefore untenable. A contract need not be
contained in a single writing. It may be collected from several different
writings which do not conflict with each other and which, when connected,
show the parties, subject matter, terms and consideration, as in contracts
entered into by correspondence.
The Supreme Court thereby affirms the decision of the Court of Appeals.
FACTS:
On May 10, 1995, the majority of MCHC's Board of Directors decided not to
re-elect respondent Zosa as President and Chief Executive Officer of MCHC
on account of loss of trust and confidence. Nevertheless, respondent Zosa
was elected to a new position as MCHC's Vice-Chairman/Chairman for New
Ventures Development.
On September 26, 1995, respondent Zosa communicated his resignation for
good reason from the position of Vice-Chairman under paragraph 7 of the
Employment Agreement on the ground that said position had less
responsibility and scope than President and Chief Executive Officer. He
demanded that he be given termination benefits as provided for in the
Employment Agreement.
petitioners filed a motion to dismiss because (1) the trial court has no
jurisdiction over the instant case since respondent Zosa's claims should be
resolved through arbitration; and (2) the venue is improperly laid since
respondent Zosa, like the petitioners, is a resident of Pasig City and thus,
the venue of this case, granting without admitting that the respondent has a
cause of action against the petitioners cognizable by the RTC, should be
limited only to RTC-Pasig City.
RTC Cebu City denied petitioners motion to dismiss upon the findings that
(1) the validity and legality of the arbitration provision can only be
determined after trial on the merits; and (2) the amount of damages
claimed, which is over P100,000.00, falls within the jurisdiction of the RTC.
Petitioners filed a motion for reconsideration which was denied.
To appeal, MCMC and MCHC filed Rule 45 Petition alleging that RTC erred in
ruling that the manner of selection of the panel arbitrators is void insofar as
MCMC and MCHC represent the same interest and that Zosa is estopped
from questioning the validity of the arbitration agreement as he already
designated his own arbitrator.
ISSUE:
HELD:
Even if procedural rules are disregarded, and a scrutiny of the merits of the
case is undertaken, the Court finds the trial court’s observations on why the
composition of the panel of arbitrators should be voided, incisively correct so
as to merit our approval. Thus,
“From the memoranda of both sides, the Court is of the view that the
defendants [petitioner] MCMC and MCHC represent the same interest. There
is no quarrel that both defendants are entirely two different corporations
with personalities distinct and separate from each other and that a
corporation has a personality distinct and separate from those persons
composing the corporation as well as from that of any other legal entity to
which it may be related. But as the defendants [herein petitioner] represent
the same interest, it could never be expected, in the arbitration proceedings,
that they would not protect and preserve their own interest, much less,
would both or either favor the interest of the plaintiff. The arbitration law, as
all other laws, is intended for the good and welfare of everybody. In fact,
what is being challenged by the plaintiff herein is not the law itself
but the provision of the Employment Agreement based on the said
law, which is the arbitration clause but only as regards the
composition of the panel of arbitrators.
“From the foregoing arbitration clause, it appears that the two (2)
defendants [petitioners] (MCMC and MCHC) have one (1) arbitrator each to
compose the panel of three (3) arbitrators. As the defendant MCMC is the
Manager of defendant MCHC, its decision or vote in the arbitration
proceeding would naturally and certainly be in favor of its employer and the
defendant MCHC would have to protect and preserve its own interest; hence,
the two (2) votes of both defendants (MCMC and MCHC) would
certainly be against the lone arbitrator for the plaintiff [herein
defendant]. Hence, apparently, plaintiff [defendant] would never get or
receive justice and fairness in the arbitration proceedings from the panel of
arbitrators as provided in the aforequoted arbitration clause. In fairness and
justice to the plaintiff [defendant], the two defendants (MCMC and MCHC)
[herein petitioners] which represent the same interest should be considered
as one and should be entitled to only one arbitrator to represent them in the
arbitration proceedings. Accordingly, the arbitration clause, insofar as the
composition of the panel of arbitrators is concerned should be declared void
and of no effect, because the law says, “Any clause giving one of the parties
power to choose more arbitrators than the other is void and of no effect”
(Article 2045, Civil Code).
FACTS:
RTC denied the motion on the ground that the dispute did not involve the
interpretation or implementation of the agreement and was, therefore, not
covered by the arbitral clause. Also, the RTC ruled that the take over of
some work items by the respondent was not equivalent to termination but a
mere modification of the subcontract.
ISSUE:
HELD:
2. Yes. The instant case involves technical discrepancies that are better left
to an arbitral body that has expertise on those areas. The Subcontract has
the Arbitral clause stating that the parties agree that “Any dispute or conflict
as regards to interpretation and implementation of this agreement which
cannot be settled between the parties amicably shall be settled by means of
arbitration.”
Within the scope of the Arbitration clause are discrepancies as to the amount
of advances and billable accomplishments, the application of the provision
on termination, and the consequent set-off expenses. Also, there is no need
for prior request for arbitration. As long as the parties agre to submit to
voluntary arbitration, regardless of what forum they may choose, their
agreement will fall within the jurisdiction of the CIAC, such that, even if they
specifically choose another forum, the parties will not be precluded form
electing to submit their dispute before the CIAC because this right has been
vested upon each party by the law.
2. Clearly, there is no more need to file a request with the CIAC in order to
vest it with jurisdiction to decide a construction dispute.
FACTS:
Fiesta World Mall Corporation, petitioner, owns and operates Fiesta World
Mall located
Under this Contract, respondent will construct, at its own cost, and operate
as owner a power plant,and to supply petitioner power/electricity at its
shopping mall in Lipa City.
The complaint further alleges that respondent constructed the power plant in
Lipa City at a cost of about P130,000,000.00. In November 1997, the
power plant became operational and started supplying power/electricity to
petitioner’s shopping mall in Lipa City. In December 1997, respondent
started billing petitioner.
From November 10, 1998 until May 21, 1999, petitioner personally
shouldered the cost of fuel. Petitioner also disputed the amount of energy
fees specified in the billings made by respondent because the latter failed to
monitor, measure, and record the quantities of electricity delivered by taking
photographs of the electricity meter reading prior to the issuance of its
invoices and billings, also in violation of the Contract.
7.4 Disputes
In its Order dated October 3, 2000, the trial court denied petitioner’s motion
for lack of merit.
On December 12, 2001, the appellate court rendered its Decision dismissing
the petition and affirming the challenged Orders of the trial court.
ISSUE:
Whether the filing with the trial court of respondent’s complaint is premature
HELD:
YES, the filing with the trial court of the complaint is premature.
It is clear from the records that petitioner disputed the amount of energy
fees demanded by respondent. However, respondent, without prior recourse
to arbitration as required in the Contract, filed directly with the trial court its
complaint, thus violating the arbitration clause in the Contract.
It bears stressing that such arbitration agreement is the law between the
parties. Since that agreement is binding between them, they are expected
to abide by it in good faith. And because it covers the dispute between them
in the present case, either of them may compel the other to arbitrate. Thus,
it is well within petitioner’s right to demand recourse to arbitration.
We cannot agree with respondent that it can directly seek judicial recourse
by filing an action against petitioner simply because both failed to settle
their differences amicably. Suffice it to state that there is nothing in the
Contract providing that the parties may dispense with the arbitration clause.
Article XXI on jurisdiction cited by respondent, i.e., that “the parties hereto
submit to the exclusive jurisdiction of the proper courts of Pasig City” merely
provides for the venue of any action arising out of or in connection with the
stipulations of the parties in the Contract.