HINDALCO INDUSTRIES LIMITED

Facility / Process Change Management

Date: 01/11/21
Name of the initiator: Ravi Singh
Department: CPP-OPR

PLANT: Hindalco Mahan(CPP)


LOCATION: Boiler
AREA: Boiler
COST CENTRE: N/A
SUBJECT (Title of Change) Oil gun scavenging valve time increase to 60 s

PRESENT SCHEME (Ref. Oil gun scavenging time is 10 s and gun scavenging
Document Nos. with Rev No.) sequence and timer is 180 s

OBJECTIVE FOR PROPOSING Oil gun scavenging time is very less and sequence timer
THE CHANGE can be reduced for quick availability of oil gun.

PROPOSED REVISED SCHEME


(Revised Doc. No.) To set the scavenging valve timer to 60 S & sequence timer
to 120 S.

ESTIMATED COST & BENEFIT Cost of implementation – NIL


ANALYSIS Advantages-
1. Reduction in chocking of oil guns.
2. Reduction in frequency of cleaning of oil guns.
3. Better oil gun efficiency.
4. Oil saving if trial period is done monthly based on reliability.

ATTACHEMENT (Drawing / N/A


sketch / P&IDs) if any:
Head- Operation Remarks if any:

Receiving date:
Head – Electrical & Remarks if any:
Instrumentation

Receiving date:
Head-Technical Services Remarks if any:

Receiving date:
Plant Head - CPP Remarks if any:

Receiving date:
Approved / Not Approved

Logic –