You are on page 1of 6

Nowsath Mem Unit-2

7ME-03 OPERATION RESEARCH QUESTION


1. The mathematical technique for finding the best use of limited resources in
an optimum manner is known as:-
a) Operation research b) Linear programming
b) Network analysis d) Queuing theory

Ans:- Linear programming

2. The linear programming technique can be applied successfully to industries


like:-
a) Iron and steel b) Banking
b) Food processing d) All of above

Ans:- All of above

3. The simplex method is basic method for:-


a) Value analysis b) Operation research
b) Linear programming d) Model analysis

Ans:- Linear programming

4. Graphical method, Simplex method and transportation method are


connected with:-
c) Value analysis b) Operation research
d) Linear programming d) Model analysis

Ans:- Linear programming

5. Direct cost
a) is directly proportional to the duration of time of an event
b) Is inversely proportional to the duration of time of an event
c) Is associated with total project time
d) All of the above
Ans:- Is inversely proportional to the duration of time of an event

6. PERT is-
a) Program evalution and review technique
b) Progress evalution and review test
c) Project evalution and review technique
d) Project estimation and review technique

Ans- Program evalution and review technique

7. The time which result in the least possible direct cost of an activity is known
as-
a) Normal time b) Slow time
b) Crash time d) Standard time

Ans- Slow time

8. CPM is
a) Time oriented technique b) Event oriented technique
b) Activity oriented technique d) Target oriented

Ans- Activity oriented technique

9. The probability distribution of activity times in PERT follows-


a) Normal b) Binomal
b) Beta d) Exponential

Ans- Beta

10.The probability distribution of project completion in PERT follows


a) Normal b) Binomial

c)Beta d) Gaussian

Ans- Gaussian

11.Critical activities are those for which-


a) Float=0 b) Float=+1
c)Float<1 d) Float>1

Ans- Float=0

12.In linear programming shadow prices are-


a) Cost of brought out items b)Max cost per item
b) Value assigned per unit d) Lowest sale prices

Ans- Value assigned to one unit

13.The value of base variable in the assignment model is-


a) 2 or 4 b) 1or 0
b) 1 or 2 d) 0 or 4

Ans- 1 or 2

14. The artificial variable are made to leave the base and never to enter in the
further iteration by the application-
a) Big M method b) Two phase method
b) Simplex method d) Both a and b

Ans- d

15. In the simplex method the variable which have not been assigned the value
zero, during an iteration, are called-
a) Basic variable b) Artificial variable
c) Actual variable d) None of the above

Ans- Basic variable

16.Limitation of linear programming model are based on criterian of-


a) Proportionality b) Additivity
b) Divisibility d) All of above

Ans- All of above

17. Simulation is basically a technique which is used-


a) Optimisation b) Testing alternatives
b) Cost minimization d) Computerisation
Ans- b

18.Simulation is used-
a) To analyse and evaluate a system performance
b) To accommodate a great degree of complexity
c) To determine the system outcome
d) All of above

Ans- All of above

19.Critical activity has-


a) Max float b) min float

c)Zero float d) None of above

Ans-c

20. Critical path moves along the activities having total float of-
a) Positive value b) negative value

c)Zero value d) Same value

Ans- c

21.In the graphical method of linear programming problem every corner of the
feasible polygon indicates –

(a) a basic feasible solution (b) optimum solution

(c) a & b (d) none of above

Ans: (a)

22.In an linear programming model there are four discision variable and three
constraints. During an iteration by simplex method the cofficien of base variable
would form

(a) an identity metrix (b) slack variable

(c)basic solution (D) none


Ans: a

23.A linear programming problem is called so,because in that problem

(a)all the functions expressing constraints are linear

(b)the objective function also linear

(c)both a& b

(d)none of the above

24.The value of base variable in the assignement variable is

(A)2 or 4

(b)1 or 0

(C)1 or 2

(d)0 or 4

25.Limitation of linear programming models are based on criteria of

(A)proportionality

(b)additive

(c)divisibility

(D)all of above

26.PERT is

(a)activity oriented

(b)event oriented

(C)cost oriented

(d)none of above

You might also like