D=EF-ES
BANAGALURU BRANCH Select the code for the correct answer from
AEE-KPSC/AE-KPWD the options given below:
a) (A) and (C) only
b) (A) and (B) only
Q-1) The area under Beta- Distribution c) (C) only
curve divided into two equal parts by: d) (A), (B) and (C)
a) Optimistic time b) Most likely time
c) Pessimistic time d) expected time Q-7) The optimistic , most likely and
pessimistic estimate for an activity are 4
Q-2) Select the incorrect statement. days, 11 days and 12 days respectively. The
a) Earliest time of an activity is the early expected completion time of this activity is:
event time of the node it leaves. a) 9 days b) 10days
b) Latest finish of an activity is the late c) 11 days d) 12 days
event time of the node it enters.
c) Latest start of an activity is its latest Q-8) Which one of the following is a point
finish minus its duration. in time when certain conditions have been
d) None of these fulfilled, such as the start or completion of
one or more activities?
Q-3) Which of the following is not a PERT a) Activity b) Network
event? c) Event d) Node
a) Site investigation started
b) Sessional work completed Q-9) Which one of the following does have
c) Bus starts from Bangalore some limitations when applied to detailed
d) Class being attended engineering design work during early stages
of a project?
Q-4) Sensitivity Analysis is a study of a) CPM b) PERT
a) Comparison of loss and profit c) Dummy activity d) Estimate
b) Comparison of assets and liabilities
c) Change in output to change in input Q-10) In the critical path of construction
d) Economics of the cost and benefits of the planning free float can be:
project a) Greater than the total float
b) Equal to the total float
Q-5) In PERT Analysis, the time estimates c) Greater than the independent float
of activities and probability of their d) Less than the independent float
occurrence follow:
a) Normal Distribution curve Q-11) Utility in economics means
b) Poisson’s Distribution curve a) Power to satisfy a want
c) Beta Distribution curve b) Usefulness
d) None of these c) Willingness of a person
d) Consumption
Q-6) If D is the duration ES and EF are the
earliest start time and earliest finish time, LS Q-12) The difference between people with
and LF are the latest start time and latest access to computers and the internet and
finish time , then the following relation(s) those without this access is known as the:
hold(s) good: a) Digital Divide b) Internet Divide
(A). EF=ES + D c) Web divide d) Cyberway divide
(B). LS=LF-D
Q-13) Mile stone charts were invented in the a) Ordinary measurement book
year? b) Standard measurement book
a)1910 b) 1920 c) 1930 d)1940 c) Check measurement book
d) Running measurement book
Q-14) Sinking fund is:
a) the fund for rebuilding a structure when
its economic life is over Q-21) The value of the property at the end
b) raised to meet maintenance costs
of the useful life period is known as:
c) the total sum to be paid to the municipal
authority by the tenants a) Book value b) Junk value
d) a part of the money is kept in reserve for c) Salvage value d) none of these
providing additional structures and
structural modifications.
Q-22) Head of the circle of PWD is:
Q-15) In PERT analysis, event means a) AEE b) EE c) SE d) CE
a) Start or finish of a task
b) Time taken for a task Q-23) Document containing detailed
c) End of an activity description of all the items of work together
d) Work involved in the projects with their current rates is called:
a) Tender b)Analysis of rates
Q-16) Functional organisation system of
working was introduced by: b) Schedule of rates d)Abstract estimate
a) F.W.Taylor b)Henry Gantt Q-24) the purpose of performing a backward
c) M.R.Walker d)J.E. Kelly pass is to

Q-17) While doing cost analysis. If the a) determine the critical path
standard deviation is high, it would generally b) determine where there is slack
lead to: c) determine the latest finish time
a) High level of uncertainty d) None of these
b) Lower level of uncertainty
c) Increased costs Q-25) The purchase price of a machine is
d) Reduced costs Rs.25,000/-.The machine has a working life
of 35000 hours and at the end of the working
Q-18) Which of the following is a life, the machine can be sold for Rs.7,500/-
construction estimate? as scrap. The depreciation charge on the
a) Initial feasibility estimate machine is constant. How much will be the
b) Conceptual preliminary budget per hour depreciation charge on this
c) Definite estimate machine?
d) All of these a)Rs.0.21 b) Rs.0.50
c) Rs.0.72 d) Rs.0.72
Q-19) If an activity lies on the critical path,
its total float will be: KEY
a) Positive b)Negative 1-D 2-D 3-D 4-C 5-C 6-D 7-B 8-B
c) Zero d) cannot be determined 9-A 10-C 11-B 12-A 13-D 14-A 15-A
Q-20) Which of the following measurements 16-A 17-A 18-D 19-C 20-D 21-C 22-C
is not used in PWD? 23-C 24-C 25-B