Question Q. 1 -------- is a series of related activities which result in some product or services.
A (a) Network
C (c) assignment
Answer a
Marks 1
Unit 4
Id 2
Q. 2 Any activity which does not consume either any resource or time is called
Question activity.
A (a) Predecessor
B (b) Successor
C (c) Dummy
D (d) End
Answer c
Marks 1
Unit 4
Id 3
Q. 3 An activity which must be completed before one or more other activities start
Question is known as activity.
A (a) Predecessor
B (b) Successor
C (c) Dummy
D (d) End
Answer a
Marks 1
Unit 4
Id 4
Q. 4 Activities that cannot be started until one or more of the other activities are
Question completed, but immediately succeed them are called ----------- activities
A (a) Predecessor
B (b) Successor
C (c) Dummy
D (d) End
Answer a
Marks 1
Unit 4
Id 5
Q. 5 An event which represents the beginning of more than one activity is known as
Question --------event.
A (a) Merge
B (b) Net
C (c) Burst
Answer c
Marks 1
Unit 4
Id 6
Question Q. 6----------- is that sequence of activities which determines the total project time.
Answer b
Marks 1
Unit 4
Id 7
Answer c
Marks 1
Unit 4
Id 8
A (a) EST
B (b) EFT
C (c) LST
D (d) LFT
Answer a
Marks 1
Unit 4
Id 9
(b) is the amount of time a task may be delayed without changing the overall
B project completion time.
D (d) is the latest time an activity can be started without delaying the entire project.
Answer b
Marks 1
Unit 4
Id 10
Q. 10 An activity has an optimistic time of 15 days, a most likely time of 18 days, and
Question a pessimistic time of 27 days. What is its expected time?
A (a) 60 days
B (b) 20 days
C (c) 18 days
D (d) 19 days
Answer d
Marks 1
Unit 4
Id 11
Q. 11 An activity has an optimistic time of 11 days, a most likely time of 15 days, and
Question a pessimistic time of 23 days. What is its variance?
A (a) 16.33
B (b) 15.6
C (c) 4
D (d) 2
Answer c
Marks 1
Unit 4
Id 12
Answer c
Marks 1
Unit 4
Id 13
A (a) Arrow
B (b) Node
D (d) Arcs
Answer b
Marks 1
Unit 4
Id 14
Q. 15 The earliest start (ES) of an activity is the ----------- earliest finish (EF) of the
Question immediate
Answer d
Marks 1
Unit 4
Id 15
A (a) Binomial
B (b) Normal
C (c) Chi-square
D (d) Beta
Answer d
Marks 1
Unit 4
Id 16
Answer b
Marks 1
Unit 4
Id 17
Question Q. 18 CPM is :
Answer c
Marks 1
Unit 4
Id 18
A (a) is 10.
B (b) is 12.
C (c) is 15.
Answer c
Marks 1
Unit 4
Id 19
Q. 20 Activities K, M and S immediately follow activity H, and their latest start times
Question are 14, 18, and 11. The latest finish time for activity H
A (a) is 11.
B (b) is 14.
C (c) is 18.
Answer a
Marks 1
Unit 4
Id 20
A (a) is any path that goes from the starting node to the completion node.
Answer d
Marks 1
Unit 4
Id 21
(a) Optimistic time estimate is an estimate of the minimum time an activity will
A require.
(b) Optimistic time estimate is an estimate of the maximum time an activity will
B require.
(c) Most likely time estimate is an estimate of the maximum time an activity will
C require.
(d) Pessimistic time estimate is an estimate of the minimum time an activity will
D require.
Answer a
Marks 1
Unit 4
Id 22
Q. 23 At the completion of the forward and backward passes, the slack for an
Question activity is given by the
Answer d
Marks 1
Unit 4
Id 23
Q. 24 A project has three paths: A--B—C has a length of 25 days. A—D—C has a
length of 15 days. A—E--C has a length of 20 days. Which of the following
Question statements is correct?
Answer c
Marks 1
Unit 4
Id 24
B (b) is the latest time an activity can be started without delaying the entire project.
(c) is the amount of time a task may be delayed without changing the overall
C project completion time.
Answer c
Marks 1
Unit 4
Id 25
(b) the network contains two or more activities that have identical starting and
B ending events.
Answer b
Marks 1
Unit 4
Id 26
Question Q. 27 PERT analysis computes the variance of the total project completion time as
B (b) the sum of the variances of all activities on the critical path.
C (c) the sum of the variances of all activities not on the critical path.
D (d) the variance of the final activity of the project.
Answer b
Marks 1
Unit 4
Id 27
Answer c
Marks 1
Unit 4
Id 28
A (a) 25
B (b) 9
C (c) 3
D (d) 5
Answer c
Marks 1
Unit 4
Id 29
Q. 30 Activities A and B are both 6 days long and the only immediate predecessors
to activity C. Activity A has ES=8 and LS=8 and activity B has ES=7 and LS=10. What is
Question the ES of activity C?
A (a) 14
B (b) 15
C (c) 16
D (d) 13
Answer a
Marks 1
Unit 4
Id 30
B (b) Have a duration equal to the shortest non-dummy activity in the network.
D (d) Are used when two activities have identical starting and ending events.
Answer d
Marks 1
Unit 4
Id 31
Answer b
Marks 1
Unit 4
Id 32
Q. 33----- is the duration by which an activity can be delayed without delaying the
Question project.
Answer a
Marks 1
Unit 4
Id 33
A (a) EST
B (b) EFT
C (c) LST
D (d) LFT
Answer b
Marks 1
Unit 4
Id 34
Question Q. 35 Generally PERT technique deals with the project of
Answer d
Marks 1
Unit 4
Id 35
Q. 36 The activity which can be delayed without affecting the execution of the
Question immediate e'ici,E.:eciilg activity determined by
Answer b
Marks 1
Unit 4
Id 36
A (a) two parallel activities have the same tail and head events
(b) the chain of activities may have common event yet be independent by
B themselves
Marks 1
Unit 4
Id 37
A (a) 1
B (b) 5
C (c) 120
D (d) 2
Answer c
Marks 1
Unit 4
Id 38
Answer b
Marks 1
Unit 4