Professional Documents
Culture Documents
UNIT: 1
A market survey indicates that during the month of July there will be a demand of
20,000 bottles of A, 40,000 of B and 44,000 bottles of C. The operating cost for plants of
G and J are 600 and 400 monetary units for how days each plant be run in July so as to
minimize the production cost, while still meeting the market demand? Formulate this
problem as an LPP and solve that using graphical method?
6. A diet for sick person must contain at least 4,000 units of vitamins, 50 units of minerals
and 1400 calories two foods A and B are available at the cost of Rs 4 and Rs3 per unit
resp. If one of A contains 200 units of vitamins, 1 unit of mineral and 40 calories and 1
unit of food B contains 100 unit of vitamins, 2 units of minerals and 40 calories.
Formulate this problem as an LPP and solve that using graphical method to find
combination of foods to be used to have least cost.
Examples on mixed constraints on LP problems
7. A firm plans to purchase at least 200 quintals of scrap containing high quality metal X
and low quality metal Y. It decides that the scrap to be purchased must contain at least
100 quintals of metal X and not more than 35quantials of metal Y. The firm can purchase
the scrap from 2 suppliers (A and B) in unlimited quintals. The percentage of X and Y
metals in terms of weight in the scrap supplied by A and B is given below:
Metal Supplier Supplier
s A B
X 25% 75%
Y 10% 20%
The price of A’s scrap is RS-200 per quintal and that of Bis 400 per quintal. The firm
wants to determine the quintals that it should buy from the 2 suppliers so that the total
cost is minimized.
8. Use the graphical method to solve the following problem
Minimize Z=20x1+10x2
Subject to constraints
(i) x1+2x2≤40
(ii) 3x1+x2≤30
(iii) 4x1+3x2≥60 x1, x2≥0
9. A firm makes two products X and Y has a total production capacity of tones per day.
Both X and Y requires the same production capacity. The firm has a permanent contract
to supply at least 2 tones of X and at least 3 tones of Y per day to another company.
Each tones of X requires 20 machine hours of production time and each tone of Y
requires 50 machine hours of production time. The daily maximum possible no of
machine hours is 360. All of the firms output can be sold. The profit made is Rs80 per
ton of X and Rs 120 per ton of Y. Formulate this problem as an LP model and solve it by
usin
10. g graphical method to determine the production schedule that yields the max profit.
UNIT 2
SIMPLEX LPP ALGORITHM
1. Express LPP in standard form by introducing slack or surplus and artificial variables.
Assign coefficient Cj to the objective function.
2. Write the initial simplex table and obtain initial basic feasible solution.
3. Compute Zj and Cj –Zj values.
4. Is the prob of max or min
a. If maximization, Select key col with largest +ve Cj-Zj value.
b. If minimization, Select key col with most –ve Cj-Zj value.
5. Select key row with min non-negative bj/aij. If all rations are –ve or infinity the current sol
is unbounded and stop computations.
6. Identify key element at the intersection of key row and key col.
7. Divide all elements of key row by key elements to get modified key row for next simplex
table.
8. Write the new simplex table by performing elementary row operations for remaining
rows.
Ra (new) = Ra (old) – X Rkey (old)
Ra (new) = Ra (old) – (No. in key row X Rkey (new)
9. Compute Zj and Cj-Zj
10. Cj-Zj≤0 (Maximization) Yes optimal sol
No repeat step 4
Cj-Zj≥0 (minimization) Yes optimal sol
No repeat step 4
Transportation problem
1. A company has three production facilities S1, S2 and S3 with production capacity of 7, 9
and 18 minutes (in 100s) per week of production resp. These units are to be shipped
four warehouses D1, D2, D3 and D4 with requirement of 5, 6, 7 and 14 minutes (in 100s)
per week resp. The transportation cost is(in rupees) per unit between factories to
warehouses are given in table below
D D D D Supply
1 2 3 4 (availability)
S1 19 30 50 10 7
S2 70 30 40 60 9
S3 40 8 70 20 18
Demand
5 8 7 14 34
(Requirement)
Formulate this transportation problem as an LP would to minimize the total
transportation cost.
2. Use North-West corner method to find an initial basic feasible solution to the
transportation problem using data of example1
Least cost method (LCM)
3. Use LCM to find initial basic feasible solution to the transportation problem using the
data of example1
Vogel’s Approximation Method (VAM)
4. Use VAM to find the initial basic feasible solution to transportation problem using the
data of example1
5. A dairy firm has three plants located in a state. The dairy milk production at each plant
as follows: plant1: 6 million liters, plant2: 1 million liters,plant3: 10 million liters. Each
day the firm must fulfill the needs of its four distribution centers. The minimum
requirement of each center as follows
Distribution center1: 7 million liters
Distribution center2: 5million liters
Distribution center3: 3million liters
Distribution center4: 2 million liters
Cost (in 100s) of shipping one million liter from each plant to each distribution center is
given in the following table
Plan Distribution
t center
D1 D2 D3 D4
P1 2 3 11 7
P2 1 0 6 1
P3 5 8 15 9
Find the initial basic feasible solution for given problem by using following methods
North West corner rule, LCM & VAM
Job No. of
pages
P 199
Q 175
R 145
S 298
T 178
4. A company operates in four territories and four salesmen available for an assignment.
The territories are not equally rich in their potential. It is estimated that a typical
salesman operating in each territory would bring in the following annual sales
Territory I II III IV
Annual sales 1,26,000 1,05,000 84,000 63,000
(Rs)
The four salesmen also differ in their ability. It is estimated that working under same
conditions their salary sales would be proportionately as follows.
Salesman A B C D
proportion 7 5 5 4
If the criterion is maximum expected total sales the intuitive answer is to assign the best
salesman to the richest territory the next best salesman to the second richest, and so on
verify this answer by the assignment technique.
5. A marketing manager has five salesmen and five sales districts considering the
capabilities of the salesmen and the nature of districts ,the marketing manager
estimates that the sales per month ( in hundred rupees) for each salesmen in each
district would be follows
SALESMEN/District
A B C D E
s
1 32 28 40 28 40
2 40 24 28 21 36
3 41 27 33 30 37
4 22 38 41 36 36
5 29 33 40 35 39
Find the assignment of salesmen to district that will result in max sales.
6. In the modification of a plant layout of a factory four new machines M1,M2,M3, and M4
are to be installed I machine shop. There are five vacant places A, B, C, D, and E available
because of limited space machine M2 cannot be placed at C and M3 cannot be placed at
A. The cost of locating a machine of a place (in hundred rupees) is as follows.
MACHINE/Locatio A B C D E
n
M1 9 11 15 10 11
M2 12 9 - 10 9
M3 - 11 14 11 7
M4 14 8 12 7 8
Find the optimal assignment schedule.
7. An airline company has drawn up an new flight a no . out of 10. The higher the no , the
greater is the preference . A few of these flights are unsuitable to some pilots during to
domestic reasons.There have been marked with X
PILOT/Flight
1 2 3 4 5
Number
A 8 2 X 5 4
B 10 9 2 8 4
C 5 4 9 6 X
D 3 6 2 8 7
E 5 6 10 4 3
What should be the allocation of the pilots to flights in order to meet as many
preferences as possible?
8. A city corporation has decided to carry out road repairs on four main arteries of the city.
The govt has agreed to make a special grant of Rs.50 lakhs towards the cost with a
condition that the repairs are done at the lowest cost and quickest time. If the
conditions warrant, a supplementary taken grant will also be considered favorably .the
corporation has floated tenders and five contractors have sent in their bids.in order to
expedite work one road will be awarded to only one contractor.
CONTRACTORS/ROAD/ COST OF REPAIRS (RS. IN R R
R1 R4
LAKH) 2 3
1 1
C1 9 15
4 9
C2 7 1 2 19
7 0
1 2
C3 9 18
8 1
1 1
C4 10 19
2 8
1 2
C5 10 16
5 1
(a) Find the best way of assigning the repair work to the contractors and the costs.
(b) If it is necessary to seek supplementary grants, what should be the amount sought?
(c) Which of the five contractors will be unsuccessful in his bid?
Travelling Salesman Problem:
9. A travelling salesman has to visit five cities. He wishes to start from a particular city, visit
each city once and then return to his starting point. The travelling cost (in ‘000Rs) of
each city from a particular city is given below.
From City/To
A B C D E
City
A ~ 2 5 7 1
B 6 ~ 3 8 2
C 8 7 ~ 4 7
D 12 4 6 ~ 5
E 1 3 2 8 ~
What should be the sequence of visit of the salesman so that the cost is minimum?
10. ABC Ice Cream Company has a distribution depot in Greater Kailash part I for distributing
ice-cream in South Delhi. There are four vendors located in different parts of South-Delhi
(call them A, B, C and D) who have to be supplied ice-cream every day. The following
matrix displays the distances (in Kms) between the depot and the four vendors.
Vendor Vendor Vendor Vendor
From/To Depot
A B C D
Depot - 3.5 3 4 2
A 3.5 - 4 2.5 3
B 3 4 - 4.5 3.5
C 4 2.5 4.5 - 4
What D 2 3 3.5 4 -
route
should the company van follow so that the total distance travelled is minimized?
Unit 4
Project Management
1. An assembly is to be made from two parts X and Y. Both parts must be turned on a lathe.
Y must be polished whereas X need not be polished. The sequence of activities together
with their predecessors is given below.
Activit Predecessor
y activity
A -
B A
C A
D B
E B, C
F E
G D, F
H G
Draw a network diagram of activities for the project.
2. Listed in the table are the activities and sequencing necessary for a maintenance job on
the heat exchanges in a refinery.
Activit Predecessor
y Activity
A -
B A
C B
D B
E B
F C
G C
H F, G
I D, E, H
J I
Draw a network diagram of activities for the project.
3. Listed in the table are the activities and sequencing necessary for the completion of a
recruitment procedure for management trainers (MT) in an organization.
Activit Predecessor
y activity
A -
B A
C A
D C
E B
F C
G D, E
H G
I H
J F
K I, J
L K
M L
N J
O M, N
Draw a network diagram of activities for the project.
Critical Path Method (CPM)
4.
Activit Predecessor
y activity
A -
B A
C B
D A
E D
F E
G -
H G
I J, H
J -
K A
L C, K
M I, L
(a) Draw arrow diagram for this project.
(b) Indicate the critical path.
(c) For each non critical activity calculate total and free float.
5. Renovation of a project
Activity Duration (weeks) Immediate predecessors
A 14 -
B 4 A
C 2 B
D 1 C
E 2 A
F 3 E
G 2 E
H 4 E
I 3 H, L
J 12 K
K 4 D, F, G
L 2 J
M 2 H, L
a. Draw the network diagram showing the interrelations between the various activities
of the project.
b. Cal the minimum time that the renovation can take from the design stage.
c. Find the effect on the overall duration of the project if the estimates or tenders can
be obtained in two weeks from the contractors by reducing their nos.
d. Cal the independent float that is associated with the non-critical activities in the
network.
Project Evaluation Review Technique (PERT)
6. The following network diagram represents activities associated with a project.
Activities optimistic time (to) pessimistic time (tp) most likely time(tm)
A (1-2) 5 10 8
B (1-3) 18 22 20
C (1-4) 26 40 33
D (2-5) 16 20 18
E (2-6) 15 25 20
F (3-6) 6 12 9
G (4-7) 7 12 10
H (5-7) 7 9 8
I (6-7) 3 5 4
(a) Expected completion time and variance of each activity.
(b) The earliest and latest expected completion times of each event.
(c) Critical path.
(d) The prob of expected completion time of the project if the original scheduled time of
completing the project is 41.5 weeks.
(e) The duration of the project that will have 95% chance of being completed.
7.
activit
Estimated Duration (weeks)
y
(i-j) Optimistic Most likely Pessimistic
1-2 1 1 7
1-3 1 4 7
1-4 2 2 8
2-5 1 1 1
3-5 2 5 14
4-6 2 5 8
5-6 3 6 15
(a) Draw the n/w diagram of the activity in the project
(b) Find expected duration and variance for each activity. What is the expected project
length?
(c) Calculate the variance and standard duration of the project length. What is the prob
that the project will be completed?
a. At least 4 weeks earlier than expected time
b. No more than 4 weeks later than expected time
(d) If the project due date is 19weeks, what is the prob of no meeting the due date
Z: 0.50 0.67 1.00 1.33 2.00
Prob: 0.3085 0.2514 0.1587 0.0918 0.0228
Crashing
8.
Activit
Normal Crash
y
Time Cost Time Cost
(weeks) (Rs) (weeks) (Rs)
1-2 3 300 2 400
2-3 3 30 3 30
2-4 7 420 5 580
2-5 9 720 7 810
3-5 5 250 4 300
4-5 0 0 0 0
5-6 6 320 4 410
6-7 4 400 3 470
6-8 13 780 10 900
7-8 10 1000 9 1200
Total 4220
Indirect cost is Rs 50 per week
(a) Draw the network diagram for the project and identify the critical path
(b) What are the normal project duration and association cost.
(c) Find out the total float associated with non-critical activities
(d) Crash the relevant activities and determine the optimal project completion time and
cost
9.
Activit
Immediate Normal Crash
y
Predecesso
Time Cost (Rs. Time Cost(Rs
r
(Weeks) ‘000) (Weeks) ‘000)
A - 10 20 7 30
B - 8 15 6 20
C B 5 10 4 14
D B 6 11 4 15
E B 8 9 5 15
F E 5 5 4 8
G A,D,C 12 3 8 4
73000
The indirect cost is Rs 400 per day. Find the optimum duration and the associated min
project cost.
10.
Activit Time Direct Cost(Rs
Immediate
y (months) ‘000)
Predecesso
Norma Cras
r Normal Crash
l h
A - 4 3 60 90
B - 6 4 150 250
C - 2 1 38 60
D A 5 3 150 250
E C 2 2 100 100
F A 7 5 115 175
G A,B,E 4 2 100 240
713
Indirect cost vary as follows,
Months: 15 14 13 12 11 10 9 8 7 6
Cost (Rs): 600 500 400 250 175 100 75 50 35 25
(a) Draw an arrow diagram for the project
(b) Determine the project duration that will result in min total cost.
UNIT 5
QUEING THEORY
1. Consider a situation in which the mean arrival rate is one customer every 4 min and the
mean service time is 2 ½ min. if the waiting cost is rs.5 per unit per min and the min cost
of servicing one unit is Rs 4.find the min cost servicing rate.
2. On an average 6 customers reach a telephone booth every hour to make calls.
Determine the probability that exactly 4 customers will reach in 30 min periods
assuming that arrivals follow poison distribution.
3. In a bank 20 customers on the average are served by a cashier in an hour. If the service
time has exponential distribution, what is the probability that
a. It will take more than 10 min to serve a customer?
b. A customer shall be free within 4 min?
4. A person repairing radios finds that the time spent on the radio sets has exponential
distribution with mean 20 minutes. If the radios are repaired in the order in which they
come in and their arrival is approximately Poisson with an average rate of 15 for 8 hour
day, what is the repairman’s expected idle time each day? How many jobs are ahead of
the average set just brought in?
5. Arrival rate of telephone calls at a telephone booth are according to Poisson distribution
with an average time of 9 min between two consecutive arrivals.the length of telephone
call is assumed to be exponentially distributed with mean 3 min.
a. Determine the probability that a person arriving at the booth will have to
wait
b. Find the average queue length that is formed from time to time
c. The telephone company will install a second booth when convinced that an arrival
would expect to have to wait at least four minutes for the phone.find the increases
in flow rate of arrivals which will justify second booth.
d. What is the probability that an arrival will have to wait for more than 10 min the
phone is free?
e. What is the probability that he will have to wait for more than 10 minutes before the
phone is available and the call is also attempted?
f. Find the fraction of a day that the phone will be in use?
6. On an average 96 patients per 24 hours day require the service of an emergency clinic.
Also on the average a patient requires10 minutes of action attention. Assume that the
facility can handle only one emergency at a time. Suppose that it costs the clinic Rs.100
per patient treated to obtain an average servicing time of 10 minutes and that each
minute of decrease in this average time could cost the clinic Rs.10 per patient treated.
How much would have to be budgeted by the clinic to decrease the average size of the
queue from 1(1/3) patients to ½ patient?
7. Goods trucks arrive randomly at a stockyard with a mean of 8 trucks / hour. A crew of
four operations can unload a truck in 6 minutes. Trucks containing in queue to be
unloaded are paid a waiting charge at the rate of Rs.60 per hour. Operations are paid a
wage rate of Rs. 20 per hour. It is possible to augment the crew strength to 2 or 3(of four
operatives per crew) when the unloading time will be 4 minutes or 3 minutes
respectively per truck. Find the optimal crew size.
THEORY OF GAMES
Games with saddle point-(minimax and maximin principles)
1. For the game with payoff matrix, determine the optimal strategies for players A and B.
also determine the value of the game. Is this game (1) fair? (2) Strictly determinable?
Player A/ Player B B B
B 1 2 3
A1 -1 2 -2
A2 6 4 -6
2. A company management and the labor union are negotiating a new three year
settlement.Each of these has 4 strategies
I: Hard and aggressive bargaining.
II: Reasoning and logical approach.
III: Legalistic strategy.
IV: Conciliatory approach.
The costs to the company are given for every pair of strategy choice.
Company
strategies
Union
I II III IV
strategies
I 20 15 12 35
II 25 14 8 10
III 40 2 10 5
IV -5 4 11 0
What strategy will the two sides adopt? Also determine value of the game.
3. For what value of the game with following pay off matrix is strictly determinable?
PLAYER B
B B B
1 2 3
A
6 2
PLAYER 1
A A
-1 -7
2
A
-2 4
3
6. In a game of matching coins with two players, suppose A wins one unit of value when
there are two heads, wins nothing when there are two tails and losses half unit of value
when there is one head and one tail. Determine the payoff matrix, the best strategies for
each player and the value of the game to A.
SIMULATION
1. Using random numbers to simulate a sample, find the probability that a packet of 6
products does not contain any defective product, when the production line produces 10
percent defective products. Compare the answer with the expected probability.
2. A bakery keeps stock of popular brand of cake. Previous experience shows the daily
demand pattern for the item with associated probability, as given below
Daily demand
0 10 20 30 40 50
{no}
0.0 0.2 0.1 0.5 0.1 0.0
Probability
1 0 5 0 2 2
Use the following sequence of random numbers to simulate the demand for next ten
days.
Random numbers: 25, 39, 65, 76, 12, 05, 73, 89, 19, 49
Also estimate the daily average demand for the cakes on the basis of the simulated data.
3. A company manufactures around 200 mopeds. Depending upon The availability of raw
materials and other conditions, the daily production has been varying from 196 mopeds
to 204 mopeds whose probability distribution is given below
Production Per
196 197 198 199 200 201 202 203 204
Day
0.0 0.0 0.1 0.1 0.2 0.1 0.1 0.0 0.0
Probability
5 9 2 4 0 5 1 8 6
The finished mopeds are transported in a specially designed three storied lorry that can
accommodate only 200 mopeds. Using the following 15 random numbers: 82, 89, 78, 24,
53, 61, 18, 45, 23, 50, 77, 27, 54 and 10, Simulate the mopeds waiting in the factory?
(a) What will be the average no. of mopeds waiting in the factory?
(b) What will be the no, of empty spaces in this lorry?
QUEUING PROBLEMS
4. A dentist schedules all his patients for 30 minutes appointments. Some of the patients
take more 30 minutes and some less depending on the type of dental work to be done.
The following summary shows the various categories of work, their probabilities and
time actually needed to complete the work
Category of Time required Prob. Of
service {min} category
Filling 45 0.40
Crown 60 0.15
Cleaning 15 0.15
Extraction 45 0.10
checkup 15 0.20
Simulate the dentist’s clinic for 4 hours and determine the average waiting time for the
patients as well as the idleness of the doctor. Assume that all the patients show up at
the clinic at exactly their scheduled arrival time starting at 2:00 A. M. use the following
random numbers for handling the above problem: 40, 82, 11, 34, 25, 66, 17, and 79.
5. The management of ABC Co. is considering the question of marketing a new product.
The FC required in the project is rs.4000. Three factors are uncertain SP, VC and sales
volume. The product has life of only one year. The management has data on these three
factors
SP Prob VC Prob Sales volume Prob
[Rs] . [Rs] . [Units] .
3 0.2 1 0.3 2000 0.3
4 0.5 2 0.6 3000 0.3
5 0.3 3 0.1 5000 0.4
Considering the following sequence of 30 random numbers: 81, 32, 60, 04, 46, 31, 67,
25, 24, 10, 40, 02, 39, 68, 08, 59, 66, 90, 12, 64, 79, 31, 86, 68, 82, 89, 25, 11, 98, 16
Using the sequence [first 3 random numbers for the first trail etc simulate the average
profit for the above project on the basis of 10 trails.