You are on page 1of 38

ABB Switzerland Ltd

High Voltage Products


Generator Circuit-
Breaker Systems
PTHG-V / Marta Lacorte
Business Development LAM
High Current Systems
All rights reserved. - 1 -
© Copyright 2004 ABB.

07/05/2007
Generator Circuit-Breaker? What are we talking about?

GCB

G G

Layout without Layout with


Generator Circuit-Breaker Generator Circuit-Breaker
© Copyright 2004 ABB
-2-
Advantages of Generator Circuit-Breakers

Simplified operation

Improved generator protection

Improved main and unit transformers protection

Increased power plant availability

Decreased costs (case dependent)


© Copyright 2004 ABB
-3-
Advantages of Generator Circuit-Breakers
Simplified Operation

GCB clear and logical plant arrangement

generator starting-up or shutting-down


only GCB operates
switching operations number reduction

power plant and the high-voltage grid operation


© Copyright 2004 ABB

responsibilities clearly defined


-4-
Advantages of Generator Circuit-Breakers
Generator, main and unit Transformers Improved
Protection

generator, main and unit transformers differential


protection zones maximum selectivity

Generator-fed short-circuit currents four cycles


interrupted
© Copyright 2004 ABB
-5-
Advantages of Generator Circuit-Breakers
Increased Power Plant Availability

simplified operation
clearly defined operational responsibilities
reduced operational errors
more reliable generator synchronisation
© Copyright 2004 ABB
-6-
Advantages of Generator Circuit-Breakers
Increased Power Plant Availability

rapid and selective clearing clearance of all types of


faults
avoid expensive secondary damage
avoid long down repair times
main or unit transformer tank bursting
generator damper winding thermal destruction
turbine-generator mechanical destruction
© Copyright 2004 ABB
-7-
Advantages of Generator Circuit-Breakers
Decreased costs (case dependent)
associated items of switchgear integration into GCB enclosure

simpler and more economic power plant layouts

simpler and more economic erection and commissioning

elimination of station transformer and associated high-voltage and medium-


voltage switchgear

increased power plant average availability

0.3…0.5 %

increased operating hours


© Copyright 2004 ABB

higher power plant operator profit


-8-
Requirements for Generator Circuit-Breakers
GCB requirements transmission and distribution CB
requirements

GCB high technical requirements

Rated current

Short-circuit currents (system-source and generator-


source)

Fault currents due to out-of-phase conditions

Fault currents asymmetry, delayed current zeros


© Copyright 2004 ABB

Recovery Voltages rate-of-rise


-9-
© Copyright 2004 ABB Standards IEC 62271-100 / 2001 (former IEC 56)

Generator circuit-breakers installed between generator and step-


up transformer are not within the scope of this standard
- 10 -
Standards
IEEE C37-013

1. Scope
This standard applies to all ac high-
voltage generator circuit breakers rated
on a symmetrical current basis that are
installed between the generator and the
transformer terminals. Pumped storage
installations are considered a special
application, and their requirements are
not completely covered by this standard.
NOTE — Since no other national or
international standard on generator
circuit breakers exists, this standard is
used worldwide.
© Copyright 2004 ABB
- 11 -
© Copyright 2004 ABB
- 12 -
ABB Generator Circuit Breakers worldwide

DB 1954-1993 HEC 3-6 1995-

DR 1969-1998 HGC 1998-

Our business card is nearly 5‘500


units installed and operating worldwide

Airblast GCB > 1900 units


SF6 GCB > 3450 units
HEK 1984-1999 HEC 7/8 2000-

HGI 1992- HECS 2003- HECPS 3/5S 2005-


ABB Switzerland Ltd, High Current Systems

Design and Manufacturing in


Zurich-Oerlikon, Switzerland
Approx. 100 Employees >70%
Deliveries in 2006: 352 GCB‘s
Market share world-wide: >70%

January 2007: received orders for almost 3600


GCB‘s in SF6 technology (since 1985)
Worldwide more than 3000 ABB GCB‘s (SF6) are
already in operation
© Copyright 2004 ABB
- 13 -
GCB PORTFOLIO 2006
Short Circuit Current [kA]
210kA

160kA

140kA
130kA
HECS-130 (HECPS-5S / HECS-130R)

100kA
HECS-100 (HECPS-3S / HECS-100R)
80kA
HECS- 80 HEC 7S HEC 7 HEC 8
63kA HGI 3
50kA
HGI 2
© Copyright 2004 ABB

6300A 8000A 10500A 13000A 18000A 23000A 24000A 28000A (57000A)

Rated Current [A]


- 14 -
© Copyright 2004 ABB Development of Generator Circuit-Breaker

GCB type: HECS (SF6)


- 15 -
Generator Circuit-Breaker System Type HECS

(1) Generator Circuit-Breaker


7
MO (2) Series Disconnector
9
3T (3) Capacitors
8

(4) Starting Disconnector for SFC


6T

5 2
(5) Manuell Short-Circuit Connection
1
(6) Earthing Switches
6G 10
4
(7) Current Transformers
3G
8
(8) Potential Transformers
(9) Surge Arrestor
7

(10) Motorized Short-Circuit Connection


© Copyright 2004 ABB

G
- 16 -
Generator Circuit-Breaker System Type HECS
View into one pole of Circuit-breaker type HECS-130L

Current transformer
Voltage transformer

Interrupting chamber
Series Disconnector
Surge arrester
© Copyright 2004 ABB
- 17 -
Interruption Chamber and Disconnector
Interrupting chamber
of the circuit-breaker type HECS-100L

Series Disconnector
View through the inspection windows
of HECS to assure that the disconnect
switch is in the open position.
© Copyright 2004 ABB
- 18 -
Earthing Switch - HECS
Earthing switch Semaphore and key
locking
© Copyright 2004 ABB

In CLOSED position
- 19 -
Hydro-Mechanical Spring Drive – HMB 4.5

Schematic diagram of the hydraulic View of a hydraulic spring


spring operating mechanism operating mechanism
© Copyright 2004 ABB
- 20 -
Current Transformer / Voltage Transformer

Current transformer Voltage transformer

According to According to
© Copyright 2004 ABB

IEC 60044-1 IEC 60044-2


or IEEE C57.13 or IEEE C57.13
- 21 -
ABB GCB advantages

Dimensions GCB ABB smaller in width and smaller length


less transportation cots and more flexibility for installation

transport units GCB totally mounted in the factory, the three phases and the control
cubicle mounted in the structure. Shorter commissioning time, less
assembling on site, less assembling mistake,higher availability

mechanic-hydraulic drive thousands of units installed in the world, approved


equipment, without failures

maintenance 20 years or 20’000 mechanical operations, until reach one of these limits only
supervision services are necessary, without take the GCB out of service

arc extinction method self blast extinction, assuring performance in the currents
interruption of high amplitude as well as of small current

type tests performed according to GCB standard IEEE C37.013 and in independent
© Copyright 2004 ABB

laboratory – KEMA
out-of-phase type test performed with 180°of phases disagreement
- 22 -
0
GCBType
GCB Type"D":
"D":
19
SouthAmerica
South America
8

0
50

DR 36 sc 1750 San Agaton 2

Planta Centro
DR 36 t 0500 1 18
Unidad 5

Planta Centro
DR 36 t 0500 1
Unidad 4

43 10
Planta Centro 0
DR 36 t 0500 2
Unidad 1 + 2

Planta Centro
DR 36 t 0500 1
Unidad 3
South America 148
DRT24.125 Macagua 2 4
World 1928
© Copyright 2004 ABB

DRT24.125 Macagua 2 2

DRT24.125 Macagua 2 4
- 23 -

DRT24.125 Macagua 2 2
GCBSF6
GCB SF6Type
Type
"H":
"H":
11 SouthAmerica
South America
15

12

8
27

HECS-100M Pedro Camejo 2


0
HEK 4 Macagua 2 5

HEK 4 Macagua 2 4

HEK 4 Macagua 2 4
13 3
5
© Copyright 2004 ABB

South America 103


World 3203
- 24 -
© Copyright 2004 ABB Replacement Northfield Mountain / USA

Northfield Mountain - After


Northfield Mountain. - Before
- 25 -
© Copyright 2004 ABB Replacement Benmore HPP / New Zealand
- 26 -
© Copyright 2004 ABB
- 27 -
Retrofit TPP Berezovskaja / Belorussia Estonia
© Copyright 2004 ABB
- 28 -
Retrofit TPP Berezovskaja / Belorussia Estonia
© Copyright 2004 ABB
- 29 -
TPP Kuala Langat (250MW) / Malaysia
© Copyright 2004 ABB
- 30 -
elimination of station transformer and high-voltage bay

GCB

G G

Layout without Layout with


© Copyright 2004 ABB

Generator Circuit-Breaker Generator Circuit-Breaker


- 31 -
Arc resistance effect in GCB
6

Arc resistance
r e s is tê n c ia
d o a rc o
4

2
Ta = Xd”/{2Πƒ(Ra)}

Ta = Xd”/{2Πƒ(Ra + Radd)}
0
0 0 .0 5 0 .1 0 .1 5 0 .2
© Copyright 2004 ABB

-1
- 32 -
Interruption of Generator-Fed Fault Currents
Without Generator Circuit-Breaker (Unit Connection)
© Copyright 2004 ABB
- 33 -
Interruption of Generator-Fed Fault Currents
With Generator Circuit-Breaker
© Copyright 2004 ABB
- 34 -
Simplified Operational Procedures
Layout without generator Layout with generator circuit-breaker
circuit-breaker
Unit start-up: Unit start-up:
1) Run-up unit on station transformer (start- 1) Run-up unit on unit transformer and
up supply) and synchronise generator synchronise generator with high-voltage
with high-voltage grid by means of high- grid by means of generator circuit-
voltage circuit-breaker breaker
2) Parallel unit auxiliaries supplies
3) Separate unit auxiliaries from station Unit routine shut-down:
transformer (start-up supply) 1) Trip generator circuit-breaker and shut-
down unit on unit transformer
Unit routine shut-down:
1) Parallel unit auxiliaries supplies Unit emergency shut-down:
2) Separate unit auxiliaries from unit 1) Trip generator circuit-breaker and shut-
transformer down unit on unit transformer
3) Trip high-voltage circuit-breaker and shut-
down unit on station transformer
Unit emergency shut-down:
1) Trip high-voltage circuit-breaker, unit
© Copyright 2004 ABB

auxiliaries are isolated


2) Automatic transfer of unit auxiliaries from
unit transformer to station transformer
(approx. 4…5 cycles)
3) Shut-down unit on station transformer
- 35 -
Equipment Failures
Main Transformer Failures

Sequence of events:
t = 0 ms: earth fault at
HV-side of transformer
t = 45 ms: 2-phase
short-circuit
t = 95 ms: 3-phase
short-circuit
t 150 ms: explosion
of transformer
© Copyright 2004 ABB
- 36 -
Equipment Failures
Short-Time Unbalanced Load Conditions
© Copyright 2004 ABB
- 37 -
Short Circuit Characteristic

G
system-source short-circuit
asymmetry 74%
voltage rate of rise TRV 6 kV/ms

generator-source short-circuit currents


asymmetry 130%
© Copyright 2004 ABB

voltage rate of rise TRT 2.2 kV/ms


- 38 -

You might also like