Professional Documents
Culture Documents
07/05/2007
Generator Circuit-Breaker? What are we talking about?
GCB
G G
Simplified operation
simplified operation
clearly defined operational responsibilities
reduced operational errors
more reliable generator synchronisation
© Copyright 2004 ABB
-6-
Advantages of Generator Circuit-Breakers
Increased Power Plant Availability
0.3…0.5 %
Rated current
1. Scope
This standard applies to all ac high-
voltage generator circuit breakers rated
on a symmetrical current basis that are
installed between the generator and the
transformer terminals. Pumped storage
installations are considered a special
application, and their requirements are
not completely covered by this standard.
NOTE — Since no other national or
international standard on generator
circuit breakers exists, this standard is
used worldwide.
© Copyright 2004 ABB
- 11 -
© Copyright 2004 ABB
- 12 -
ABB Generator Circuit Breakers worldwide
160kA
140kA
130kA
HECS-130 (HECPS-5S / HECS-130R)
100kA
HECS-100 (HECPS-3S / HECS-100R)
80kA
HECS- 80 HEC 7S HEC 7 HEC 8
63kA HGI 3
50kA
HGI 2
© Copyright 2004 ABB
5 2
(5) Manuell Short-Circuit Connection
1
(6) Earthing Switches
6G 10
4
(7) Current Transformers
3G
8
(8) Potential Transformers
(9) Surge Arrestor
7
G
- 16 -
Generator Circuit-Breaker System Type HECS
View into one pole of Circuit-breaker type HECS-130L
Current transformer
Voltage transformer
Interrupting chamber
Series Disconnector
Surge arrester
© Copyright 2004 ABB
- 17 -
Interruption Chamber and Disconnector
Interrupting chamber
of the circuit-breaker type HECS-100L
Series Disconnector
View through the inspection windows
of HECS to assure that the disconnect
switch is in the open position.
© Copyright 2004 ABB
- 18 -
Earthing Switch - HECS
Earthing switch Semaphore and key
locking
© Copyright 2004 ABB
In CLOSED position
- 19 -
Hydro-Mechanical Spring Drive – HMB 4.5
According to According to
© Copyright 2004 ABB
transport units GCB totally mounted in the factory, the three phases and the control
cubicle mounted in the structure. Shorter commissioning time, less
assembling on site, less assembling mistake,higher availability
maintenance 20 years or 20’000 mechanical operations, until reach one of these limits only
supervision services are necessary, without take the GCB out of service
arc extinction method self blast extinction, assuring performance in the currents
interruption of high amplitude as well as of small current
type tests performed according to GCB standard IEEE C37.013 and in independent
© Copyright 2004 ABB
laboratory – KEMA
out-of-phase type test performed with 180°of phases disagreement
- 22 -
0
GCBType
GCB Type"D":
"D":
19
SouthAmerica
South America
8
0
50
Planta Centro
DR 36 t 0500 1 18
Unidad 5
Planta Centro
DR 36 t 0500 1
Unidad 4
43 10
Planta Centro 0
DR 36 t 0500 2
Unidad 1 + 2
Planta Centro
DR 36 t 0500 1
Unidad 3
South America 148
DRT24.125 Macagua 2 4
World 1928
© Copyright 2004 ABB
DRT24.125 Macagua 2 2
DRT24.125 Macagua 2 4
- 23 -
DRT24.125 Macagua 2 2
GCBSF6
GCB SF6Type
Type
"H":
"H":
11 SouthAmerica
South America
15
12
8
27
HEK 4 Macagua 2 4
HEK 4 Macagua 2 4
13 3
5
© Copyright 2004 ABB
GCB
G G
Arc resistance
r e s is tê n c ia
d o a rc o
4
2
Ta = Xd”/{2Πƒ(Ra)}
Ta = Xd”/{2Πƒ(Ra + Radd)}
0
0 0 .0 5 0 .1 0 .1 5 0 .2
© Copyright 2004 ABB
-1
- 32 -
Interruption of Generator-Fed Fault Currents
Without Generator Circuit-Breaker (Unit Connection)
© Copyright 2004 ABB
- 33 -
Interruption of Generator-Fed Fault Currents
With Generator Circuit-Breaker
© Copyright 2004 ABB
- 34 -
Simplified Operational Procedures
Layout without generator Layout with generator circuit-breaker
circuit-breaker
Unit start-up: Unit start-up:
1) Run-up unit on station transformer (start- 1) Run-up unit on unit transformer and
up supply) and synchronise generator synchronise generator with high-voltage
with high-voltage grid by means of high- grid by means of generator circuit-
voltage circuit-breaker breaker
2) Parallel unit auxiliaries supplies
3) Separate unit auxiliaries from station Unit routine shut-down:
transformer (start-up supply) 1) Trip generator circuit-breaker and shut-
down unit on unit transformer
Unit routine shut-down:
1) Parallel unit auxiliaries supplies Unit emergency shut-down:
2) Separate unit auxiliaries from unit 1) Trip generator circuit-breaker and shut-
transformer down unit on unit transformer
3) Trip high-voltage circuit-breaker and shut-
down unit on station transformer
Unit emergency shut-down:
1) Trip high-voltage circuit-breaker, unit
© Copyright 2004 ABB
Sequence of events:
t = 0 ms: earth fault at
HV-side of transformer
t = 45 ms: 2-phase
short-circuit
t = 95 ms: 3-phase
short-circuit
t 150 ms: explosion
of transformer
© Copyright 2004 ABB
- 36 -
Equipment Failures
Short-Time Unbalanced Load Conditions
© Copyright 2004 ABB
- 37 -
Short Circuit Characteristic
G
system-source short-circuit
asymmetry 74%
voltage rate of rise TRV 6 kV/ms