You are on page 1of 2

M1 ($) G1 ($) S1 ($) MO1 ($) M2 ($) G2 ($) S2 ($) M02 ($) i (%) N (yıl) DM BCA

120000 8000 30000 1000 60000 2000 5000 5000 1,0 10 PRESENT B/C

First Company
All Benefits
Present or uniform value for G1 value = B1 B1= 75.770,44 (12p)
B1+B2= 102.929,04 (2p)
Present or uniform value for S1 value =B2 B2= 27.158,61 (7p)

All Costs
Present or uniform value for M1 value = C1 C1= 120.000,00 (3p)
C1+C2= 129.471,30 (2p)
Present or uniform value for MO1 value = C2 C2= 9.471,30 (12p) (10p)
ΣB/ΣC or ΣB-ΣC= 0,79
Second Company
All Benefits
Present or uniform value for G1 value = B1 B1= 18.942,61 (12p)
B1+B2= 23.469,04 (2p)
Present or uniform value for S1 value =B2 B2= 4.526,43 (7p)

All Costs
Present or uniform value for M1 value = C1 C1= 60.000,00 (3p)
C1+C2= 107.356,52 (2p)
Present or uniform value for MO1 value = C2 C2= 47.356,52 (12p) (10p)
ΣB/ΣC or ΣB-ΣC= 0,22
1 2
Which company do you prefer? ( Put the right answer "+" sign )
+
(4p)
75.770,44 12
102.929,04 2
27.158,61 7
0,79 10

120.000,00 3
129.471,30 2
9.471,30 12

4 100
18.942,61 12
23.469,04 2
4.526,43 7
0,22 10

60.000,00 3
107.356,52 2
47.356,52 12