Professional Documents
Culture Documents
In this instalment of this series, Entrusty Group will provide the answer to another frequently
asked question above.
W
e often hear cash flow used in the Malaysian construction forms of construction contract
is the lifeblood of the industry before we move on to the relating to such certificates.
construction industry. Yet, common law termination.
late payment is an endemic feature ● Determination of Employment
and a root cause of many problems Standard Forms of Construction by Contractor
and disputes in the construction Contract The majority of standard forms
industry in Malaysia. of construction contract, except
● Certificates relating to JKR forms of contrac t i.e. JKR
In the previous issue of Master payment 203A and JKR DB/T, allow the
Builders Journal, we have explained Most of the standard forms of Contractor to determine his own
the difference between determination construction contract in Malaysia employment upon the Employer
of employment and termination require the Employer to pay the failing or neglec ting to make
of contract, together with their Contractor within the stipulated payment on the amount due in
respective implications. In this period upon receipt of the amount the certificate. Table 2 indicates
article, we will look into the situation due as stated in the certificate issued the relevant contract clauses for
where the innocent party, usually by the Architect/Engineer/SO/PD. the determination of employment
the Contractor, who contemplates There are generally three main types by the Contractor for payment
whether to elect to determine its of certificate relating to payment that default.
own employment or to terminate entitle the Contractor to payment
the contract when the guilty party, by the Employer, namely Interim ● Suspension of Works and
usually the Employer, fails to honour Certificate, Penultimate Certificate Interest Charge
the Contractor’s payment within the and Final Certificate. Table 1 shows Most standard forms of construction
stipulated period in the contract. the relevant clauses in the standard contract provision on Employer’s
92
Table 2 - Determination of employment by the Contractor under the over a time, makes either partial
relevant contract clauses of the standard forms of construction contract in payment or late payment or both;
Malaysia (4) U n l a w f u l o r w r o n g f u l
Employer’s defaults Relevant Contract Clauses deduction of payment – When the
Employer unlawfully or wrongfully
PAM PAM JKR JKR IEM CIDB
deducts any amount due in the
2000
2006 1998 203A DB/T 1989 certificate; and
Failure to pay 26.1 26.1 (i) - - 52 (a) 45.1 (5) I m p ro p e rl y w i t h h o l d i n g
(a) (i) (a) (i) payment due – When the Employer
improperly, usually not in accordance
with the Contract withholds any
Table 3 - Relevant provisions for suspension of works and interest charge payment due to the Contractor;
due to the Employer’s default in payment in the standard forms of
construction contract in Malaysia Any of the above scenarios committed
Brief Description Relevant Contract Clauses by the Employer can be considered
as breach of contract for failure to
PAM PAM JKR JKR IEM CIDB pay accordingly but not all of them
2000
2006 1998 203A DB/T 1989 amount to repudiatory breach. So,
Suspension of works 30.7 - - - - 42.10 on what circumstances does the
Employer commit repudiatory breach
Interest charge 30.17 - - - - 42.9 which can result in the Contractor
(b)
having to rescind the contract i.e.
to terminate?
default in payment, stipulate that contract was formed or by the
the Contractor can either continue actions of one or both parties. Keating on Building Contracts (6 th
with his work or determine his In order for a contrac t to be edition 1995, p 156) explained
own employment upon default terminated, one party must be in that when one party breaches the
in payment by the Employer. In repudiatory breach that goes to the contract, the other party can elect
addition, PAM 2006 and CIDB 2000 root of the contract and the innocent to put an end to it by these two
allow the Contractor to suspend the party accepts such repudiation by circumstances:-
works and/or claim interest for the rescinding the contract thereby
unpaid amount. Table 3 indicates excusing the latter from further (1) where the contracting parties
the relevant contract clauses for the performance. Repudiation entitles have agreed, whether by express
suspension of works and interest the innocent party to damages as words or implication of law that
charge for such default. provided and illustrated in Section any breach of the contractual term
40 of the Contracts Act 1950. in question shall entitle the other
Common Law Termination party to elect to put an end to all
Late payment: Is it a remaining primary obligations of both
In the previous article, we have ground for determination or parties, i.e. where there is a breach
explained the word ’determination’, termination? of condition;
in the context of construction
contract, is about bringing to an Now back to the question whether (2) where the event resulting from
end the Contractor’s employment late payment is a ground for the breach of contract has the effect
under a particular contract whereby determination or termination. In order of depriving the other par ty of
the Contractor’s obligation and to answer that, let us consider five substantially the whole benefit which
responsibility to carry out the works scenarios usually faced by Contractor was the intention of the parties that
under the contract is terminated pertinent to payment upon issuance he should obtain from the contract,
and not the contract. Therefore, the of Interim Certificate, namely:- i.e. where there is a fundamental
Contractor’s rights and remedies (1) Par tial payment – When breach.
under the contract and at common the Employer makes only partial
law are preserved. payment/s on the amount due in Breach of condition
the certificate;
The termination of contract at (2) Late payment – When the Most construction contracts provision
common law occurs when a valid and Employer makes payment after the on payment requires the Employer
enforceable contract is brought to an stipulated period for honouring to pay the Contractor the amount
end either by becoming impossible payment; due on the certificate within a
to perform due to unforeseeable (3) Persistent irregular payment stipulated period. Any breach
circumstances at the time the – When the Employer persistently of such provision is a breach of
93
condition by the Employer which fulfil his contractual obligations, late payment is a ground for
entitles the Contractor to exercise thereby substantially depriving the determination or termination or
his rights and remedies as spelt out Contractor the benefit/s intended otherwise.
in the relevant contract provision by the contract. The Contractor may
i.e. determination of employment then rescind the contract and sue (1) Yap Mok Hin v United Malay
by the Contractor. In PAM 2006 for damages. States Sugar Industries Ltd [1996] 2
and CIDB 2000, the Contractor can MLJ 286
suspend the works and/or claim In case of late payment where In this case, the court held that a
interest for the unpaid amount if he the contract does not provide for mere non-payment of a progress
elects not to determinate his own determination, the explicit wordings p ay m e n t d o e s n o t c o n s t i t u t e
employment. contained in the terms and conditions repudiation and it was the contractor
of the contract concerning payment who repudiated the contract by
In the case of late payment, if it and its remedy will be pertinent, abandoning the work.
is a merely late payment in one particularly whether the time for
payment certificate, although it payment is of essence or not. For (2) Ban Hong Joo Mines Ltd v Chen
is a breach of condition by the an example, where the term of the & Yap Ltd [1969] 2 MLJ 83
Employer, the Contractor normally contract stipulates that the Employer In this case, the court referred to
will not elect to take such drastic is obliged to pay the Contractor for English case, Freeth v Burr (1873-
action to determinate his own the amount of work done or where 74), 9 CP 208 in which the learned
employment due to commercial there is intention of both parties to judge, Keating, J said ’It is not a
interest and the serious contractual obtain the benefit/s for the work mere refusal or omission of one of the
and legal implications. However, if completed within a certain period, contracting parties to do something
the late payment is persistent or the failure to pay by the Employer is a which he ought to do that will justify
Employer has no intention to pay fundamental breach which entitles the other in repudiating the contract;
accordingly or at all, the Contractor the Contrac tor to rescind the but there must be an absolute refusal
may be forced to take such drastic contract. to perform his part of the contract.
action. Where there is a dispute Non-payment is an element.’
or difference on this matter, then In some cases, a failure to pay in
the aggrieved party can refer to one payment due, out of many, The court held that the Employer
mediation or arbitration, as provided or simply late by a few days, may was in breach of his obligation by
under most forms of construction not be sufficient for the Contractor deliberately refusing to pay what was
contract. to rescind the contract unless the already due by way of fortnightly
Contractor can prove that he has payments which was an important
However, in JKR forms of contract i.e. substantially completed the work element for the Contractor to treat
JKR 203A and JKR DB/T, the Contractor and has suffered substantial losses the contract as at an end.
is not allowed to determine his own as consequence of the breach or if
employment or suspend the works it had occurred towards the end of (3) Pembenaan Leow Tuck Chui &
or claim interest for the unpaid the contract. Sons Sdn Bhd v Dr Leela’s Medical
amount. The Contractor’s rights and Centre Sdn Bhd [1995] 2 MLJ 57
remedies for this breach under the Fundamental breach can also occur In this case, the Contractor was
contract would be to refer to the even though the contract provides entitled to obtain full payment
SO/PD for his decision and if it is for a contractual determination due in the Penultimate Certificate
still unresolved, then the Contractor clause. For example, when the pending the disputes resolution.
may end up having to refer to Employer persistently fails or refuses The Employer rights to set-off under
arbitration for redress and resolution. to fulfil his contractual obligations the PAM 1969 also came before the
Alternatively, the Contractor may despite the Contractor’s repeated Federal Court for decision.
pursue to seek redress by bringing demands. Then the Contractor can
the matter to the court without either bring this matter to the court The court held that under Clause
rescinding the contract and go for without rescinding the contract and 30(1), the Contrac tor shall be
summary judgement under Order 14 go for summary judgement under entitled to payment for the sum
or to rescind the contract and sue Order 14 or rescind the contract and certified upon the expiration of 21
for damages. sue for damages. days of the period for honouring
interim certificate from the date
Fundamental breach Case Law of presentation to the Employer.
The seriousness of the requirement
Fundamental breach occurs when The following cour t cases will in the contract for honouring an
the Employer has committed shed some light on this question interim certificate was emphasised
repudiatory breach by refusing to as to under what circumstances by Clause 26.1(1)(a) which allowed
94
Late payment certainly constitutes For further details, please visit website: www.entrusty.com. or contact
a breach of contract and whether HT Ong at 22-1& 2 Jalan 2/109E, Desa Business Park, Taman Desa, 58100
it is a ground for determination or Kuala Lumpur, Malaysia. Tel: 6(03)-7982 2123 Fax: 6(03)-7982 3122 Email:
termination is very much dependent enquiry@entrusty.com.my.
on the contract provisions and the
intention/action of the contracting Entrusty Group provides 30 minutes of free consultancy (with prior
parties. In common law termination, appointment) to MBAM members on their contractual questions. The Group
a mere late payment may not be also provides both in-house and public seminars/workshops in its various
sufficient for the Contractor to rescind areas of expertise.
95