Professional Documents
Culture Documents
Claim management
Under MBD-FIDIC
Contractual agreement
Initiation of dispute
Claim
Resolution Mechanism
Under MDB - FIDIC
Answer
It is evident that both internal and external aspects of business setting are present as the prime
contributors to cost overruns. The possible factors that cause for the project cost overrun can be
classified in to three main (broad categories) parts. These are:
1. Macro-Economic Factors
2. Management Factors
3. Business and Regulatory Environment
2.1 Macro-Economic Factors: The cost of construction is basically the cost of money, the
cost of material, the cost of labor and the cost of management. Some of the factors identified
under this category are:
Fluctuation in prices of raw materials,
According to clause 47.1 (price adjustment) of the PPA ICB Prices shall be adjusted for
fluctuations in the cost of inputs only if provided for in the Special Conditions of Contract.
If so provided, the amounts certified in each payment certificate, after deducting for
Advance Payment, shall be adjusted by applying the respective price adjustment factor to
the payment amounts due in each currency. A separate formula of the type indicated below
applies to each Contract currency:
Ln Mn En
pn= A+ b +c +d + etc .
Lo Mo Eo
Where:
pn is a price adjustment factor to be applied to the amount in each specific currency for
each payment certificate;
Ln, Mn, En, etc., are the current cost indices or reference prices of the cost elements in the
specific currency of origin at the date 28 days prior to the deadline for bid submission; and
Lo, Mo, Eo, etc., are the base cost indices or reference prices corresponding to the above
cost elements at the date 28 days prior to the last day of the period to which a particular
Interim Payment Certificate is related.
2.2.2 When parties enter into not finalized contract before work commences
2.2.3 Unable to define quality constraints and scope of work prior to tender;
2.2.4 Unclear condition of contracts
3. Payment (5%)
3.1 Please, discuss the importance of payment provisions in the construction contract from the
perspective of the Contractor; (1.50%)
Answer
The following are importance of Provision of Payment for contractor
It secures the right of the contractor to have payment for the work he has made and
completed as per the contract.
It control the cash flow of the contractor
Help the contractor to perform his day to day task without any problem
Purchase necessary resource for the construction of the project pay wages or salaries of
his worker without problem.
3.2 Comparison between interim and final payment
Identify & discuss, at least, two major differences between interim/progress payment & final
payment; (1.75%)
Answer
Difference
No Interim/progress payment Final payment
It is a payment made to the It is a payment made at the completion of a project.
contractor after completing Once the final payment is made the engineer has no
some amount of work as per power to amend any mistakes.
the agreement on weekly or Mistakes/disputes are solved through arbitration
monthly interval. process if the following are happened to the final
If mistakes or correction are payment.
made it can be corrected in Fraud
the next interim payment. Claim raised before the issue of the final
The contractor can request payment (this is possible until defect
interim payment as per SCC liability period only).
of the contract document with The contractor should submit his final payment
no time limit. certificate after 56 days of receiving the
performance certificate.
3.2 Discuss four major legal & contractual effects of the final payment; (1.75%)
Answer
Some of the legal and contractual effects of final payment are:
3. Once final payment is done the engineer has no power to incorporate any mistakes or
correction of contractor’s claim even if their claim is accepted.
4. Only the arbitration or the court can amend the final payment when
Frauds exist in the final payment.
Unjust ices enrichment
the contractor raised claim before the approval of the final payment
5. It shows the completion of the project
6. It is the event where obligation of parties end
4. Termination of a contract
a. Following termination valuation at the date of termination has been undertaken in the
presence of both the representatives of the employer & the contractor. This joint
document records the following:
the status of the executed works
the financial status of the project under all the monthly payment certificates
effected to the contractor
the value of construction material on site
Records the type, number, status of construction machinery, equipment & plant
of the contractor and valuate the entire said asset.
the value of temporary works including project site office
This helps for determining the rights, obligations and/or remedial rights of the
employer & the original contractor.
b. The contractor stops his/her work PPA. 59.5 (works) If the Contract is terminated, the
Contractor shall stop work immediately, make the Site safe and secure, and leave the
Site as soon as reasonably possible.
b) Assuming that the new contractor engaged by the employer has delayed the
completion of the project. Is the terminated contractor liable for such delay? If
yes, why? If not, why not? Discuss.
According to Clause 15.3 there should be valuation of the works done for financial and
physical status of the project. So if the work is delayed at that time the original
contractor is responsible otherwise he is not.
4. Sub-contracting (5%)
6.1 The Sub-contractor which has been selected & appointed by the Contractor, indeed with
the approval of the Employer, has gone bankrupt. The Main Contractor has been delayed
in the completion of the project. The Employer has deducted liquidated damages from the
Payment due to the Contractor. The Contractor has argued that for the bankruptcy of the
Sub-contractor the Main Contractor is not responsible. Why the Contractor is or is not
responsible for the delay caused by the selected Sub-contractor? (2.5%)
Answer
Even though the subcontractor (domestic) selected & appointed by the Contractor, indeed with
the approval of the Employer, the legal effect of the subcontract is that the Main Contractor shall
be responsible, to the Employer, for the acts, defaults & neglects of any subcontractor, his
agents, servants or workmen as fully as if they were the acts, defaults or neglects of the Main
Contractor, his agents, servants or workmen.
The approval of the said subcontractor by the Engineer is not a legal ground for the Main
Contractor to escape liability arising out of any acts, defaults or neglects of the Sub-contractor.
In principle, there are no privities of contract between the Employer & the Sub-contractor.
On the basis of the effect of the doctrine of the assignment, a direct legal relationship may be
created by way of assignment of rights of the Main Contractor, under the Main Contract, to the
Employer.
According to Article 3206(1) of the civil code “The approval given by the administrative
authorities to the sub-contract shall not affect the contractual bond between the administrative
authorities and .their contracting party.” And article 3206(2) “The original party shall remain
liable for the works done and supplies made by the sub-contractor as though they had been done
or made by him.”
So due to this the main contractor is responsible for the fault of the domestic subcontractor.
6.2 Would your opinion be different if the Sub-contractor were a nominated one? If yes, why
& if not, why not? (2.5%)
Answer
No because even if, the Sub-contractor were a nominated one since it has a consent of the
main contractor similar to the domestic for any fault of this subcontractor the main contractor
is responsible with the same reason as mentioned above in (a).
7.2 Please, thoroughly discuss the advantages & disadvantages of force account project
delivery system vis-à-vis the contract method project delivery system? (2.5%)
Answer
Advantage and disadvantage of Force account vis-à-vis the contract method project delivery
system
No Advantage Disadvantage
1 Mistakes are minimized in the Susceptible for making mistake as it
execution of the document. is performed by one party.
The construction of the project is The construction period is limited
faster. kept as there no completion.
When the all contractors give more Quality is not that much
price than expected. High work load.
If a project exist in difficult area
for instance area with war, disease
for normal contractors
Contract Termination
General Course Knowledge Examination Questions
1. Termination of a Construction Contract
Assuming that a construction contract, under MDB-FIDIC conditions of contract has been duly
terminated, by the employer, due to the default of the contractor
a) What are the critical steps to be taken in terms of contract administration immediately after such
termination and why? Discuss.
b) Assuming that the new contractor engaged by the employer has delayed the completion of the project.
Is the terminated contractor liable for such delay? If yes, why? If not, why not? Discuss.
c) Would your position be different, under question b, if the conditions of contract were that of PPA
(2006)? If yes, why? If not, why not?
Support your arguments by citing the relevant clauses from the respective conditions of contract;
8. Project Delivery System & Value Engineering
Under the design-bid-build project delivery system, the contractor is allowed to make
proposals (say for the improvement of bridge design, through value engineering).
Assuming that a contractor has made a proposal & such proposal has been approved
by the Engineer. Would the contractor become liable for design related problems say for
the collapse of such bridge due to fault design if the proposal were related to some
design works & as such designed by the contractor?
8.1 Define & distinguish DBB & DB project delivery systems; Page limit: not less
than one full page;
According to 13.2 value engineering and clause 4.1 the contractor can have a proposal.
“the Contractor may, at any time, submit to the Engineer a written proposal which (in the
Contractor’s opinion) will, if adopted, (i) accelerate completion, (ii) reduce the cost to the
Employer of executing, maintaining or operating the Works, (iii) improve the efficiency or
value to the Employer of the completed Works, or (iv) otherwise be of benefit to the
Employer,
Clause 4.1 “The Contractor shall design (to the extent specified in the Contract),
execute and complete the Works in accordance with the Contract and with the
Engineer’s instructions, and shall remedy any defects in the Works.”
so the project delivery system is not changed because,
8.3 Is such contractor liable for such design failure, then? If yes, why? If not, why
not? Please, discuss your reasons based on MDB-FIDIC or any other applicable
conditions of contract; Page limit: one full page;
According to clause 4.1 (c) “the Contractor shall be responsible for this part and it shall,
when the Works are completed, be fit for such purposes for which the part is intended
as are specified in the Contract; and “
Not requesting advice from or consultation with the Member regarding the Contract,
otherwise than in the normal course of the DB’s activities under the Contract & the DBA
Undertaking that the Member not to be appointed as an arbitrator in any arbitration under
the Contract
Undertaking that the Member not to be called as a witness to give evidence before the
arbitration proceeding
Undertaking that the Member not to be liable for any claims for anything done or omitted in
the discharge or purported discharge of the Member’s function
Indemnifying & holding the Member harmless against & from which the Member is
relieved from liability under the DBA
Providing appropriate security for a sum equivalent to the reasonable expenses to be
incurred by the Member(s)
Effecting payment to the Member(s) as per the DBA
Adjustment of Retainer Fee or Daily Fee after 24 calendar months, by agreement
9. Delay and Disruption Claims
9.1 What do you understand by delay & disruption claims? Is there any difference between the
two types of claims? If yes, why? If not, why not? Define the concepts and discuss them in
detail. (5%)
Answer
Delay can be defined as a period during which a contractor cannot employ his resources at
normal intended output, having regard to the nature and amount of work which is available under
the agreed program of working or under any rearrangement of that program.
“Construction period is the time gap between the commencement date and the completion date”
Some of the effects of delay are:
Time overrun, Arbitration,
Cost overrun, Total abandonment
Dispute, Litigation
Disruption may be defined as the effect of an event or a number of events on the efficiency of
execution of the works, irrespective of whether or not there had been a delay to a critical activity.
It can be defined as an interruption to the planned work sequence of flow of work (Bramble and
Callahan, 2005), or as events that impede the contractor from completing the work as planned
Continuous, extensive & cumulative disruption, however, may end in critical delay &
prolongation of the time for completion. Inefficiency, loss of productivity of labour &
uneconomic use of equipment comes under the heading of disruption when they are caused by an
event which is not the responsibility of the contractor.
A proper evaluation of a claim for disruption requires the following pre-requisites.
An identification & analysis of each of the operations claimed to have been disrupted. It
is not sufficient simply to state that the execution of the works has been disrupted.
The cause & the manner in which disruption has occurred should be established.
The figures for the anticipated output. The resources planned & the time required to
achieve the completion of the disrupted operations as calculated in the tender have to be
shown to be achievable.
The effect of any inefficiency on the part of the disrupted party in carrying out the works
should be properly calculated & its effect included in the calculations of disruption
suffered.
The number of hours actually logged in the time sheets for the disrupted operation has to
be shown to be accurate.
When records are available & are correct, then the cost of disruption can be simply calculated as
the number of hours actually worked less that originally anticipated in the tender, with the result
being multiplied by the cost of the particular resources disrupted per hour.
When acceleration of the progress of the works is required, the cost may include the expense of,
Working additional hour;
Providing additional labour;
Providing additional or different equipment;
Advancing the date of delivery of manufactured elements;
Disruptions are events that prevent the contractor completing the work as planned. Many
disruptions to complex projects are planned for at the bid stage because they may be expected to
unfold during the project. For example, some level of rework is usually expected, even when
everything goes well, because there will always be ‘normal’ errors and mistakes made by both
the contractor and employer.
Disruption claims are sometimes included with delay claims but are fundamentally different.
Disruption may not result in delay. Contractors claim that they could not achieve their planned
output because of the Employer’s actions and hence that the damages or extra costs are payable.
Disruption (loss of productivity) results in a delay to the work being carried out and not
necessarily to completion of the Works. The work produced is not changed, it simply takes
longer to complete.
A disruption claim is a claim for alleged disruption or loss of productivity resulting from the acts
or omissions of the Principal or the Principal’s agents. Disruption claims are sometimes included
with delay claims but are fundamentally different. Disruption may not result in delay.
Contractors claim that they could not achieve their planned output because of the Principal’s
actions and hence that the damages or extra costs are payable.
A ‘real’ delay may be defined as a period during which a contractor cannot employ his
resources at normal intended output, having regard to the nature and amount of work
which is available under the agreed program of working or under any rearrangement of
that program. “Construction period is the time gap between the commencement date
and the completion date”. If any project is completed beyond the completion (contract)
period it is delayed.
Liability of contract parties towards delay
The categories of responsibilities are:
Owner (agent) responsible: contractor will be granted time extension and
additional cost, where warranted.
Contractor (subcontractor) responsible: contractor will not be granted time or
costs and may have to pay damages/penalties.
Neither party (e.g. act of God) responsible: contractor will receive additional
time to complete the project but no costs will be granted and no damages /
penalties assessed.
Both parties responsible: contractor will receive additional time to complete the
project but no costs will be granted and no damages/penalties assessed.
Disruption claim
Disruption in the construction industry can be defined as an interruption to the planned
work sequence of flow of work (Bramble and Callahan, 2005), or as events that impede
the contractor from completing the work as planned.
Disruptions are events that prevent the contractor completing the work as planned.
Many disruptions to complex projects are planned for at the bid stage because they may
be expected to unfold during the project. For example, some level of rework is usually
expected, even when everything goes well, because there will always be ‘normal’ errors
and mistakes made by both the contractor and employer.
A disruption claim is a claim for alleged disruption or loss of productivity resulting from
the acts or omissions of the Principal or the Principal’s agents. Disruption claims are
sometimes included with delay claims but are fundamentally different. Disruption may
not result in delay. Contractors claim that they could not achieve their planned output
because of the Principal’s actions and hence that the damages or extra costs are
payable. Contractors claim that they could not achieve their planned output because of
the Employer’s actions and hence that the damages or extra costs are payable.
10.2 Discuss the at least 3 difference between delay & disruption claim
Difference
Delay claim Disruption claim
Disruption (loss of productivity) results in a
delay to the work being carried out and not
necessarily to completion of the Works.
The work produced is not changed, it
simply takes longer to complete.
It will have both contractor and employer Disruption may not result in delay.
Some papers have defined a construction defect as that which makes a project
dangerous, unsafe or causes real damage to the consumer. In general terms, defects or
defective works is where the standard and quality of workmanship and materials as
specified in the contract is deficient. Defects can be Patent Defects or Latent Defects.
10.3 Comparison between MDB-FIDIC and PPA Conditions of Contract Related to Delay.
Under this section of this study comparison shall be made between MDB-FIDIC and
PPA Conditions of Contract related to delay claims. The comparison shall be limited to
those clauses which have relevance to delay and associated delay claims.
9.2 Would your opinion be different, if the Sub-contractor were a nominated sub-contractor?
Why/why not? Please, discuss in detail. Please, support your discussion by citing relevant
clauses and/or articles from the relevant conditions of contract & the applicable law,
respectively.(2.5%)
Answer No, because similar to the above reason Even though, the NSC has been selected or
appointed or approved by the Employer/Engineer, there shall be no privity of contract between
the Employer/Engineer & the NSC.
The Main Contractor shall become liable towards the Employer for the acts, defaults or breach
of the NSC
9.3 The Sub-contractor which has been selected & appointed by the Contractor, indeed with the
approval of the Employer, has gone bankrupt. The Main Contractor has been delayed in the
completion of the project. The Employer has deducted liquidated damages from the Payment
due to the Contractor. The Contractor has argued that for the bankruptcy of the Sub-
contractor the Main Contractor is not responsible. Why the Contractor is or is not responsible
for the delay caused by the selected Sub-contractor? (2.5%)
According to Art.3206 (3) of Civil Code the contractor is not responsible for the delay cause by the sub
contactors this is due to the approval of the sub-contractor by the administrative authorities (employer)
shall however imply the exoneration of the contractant (contractor) from the penalties for delay, where
such delay is attributable to the sub-contractor.
The enforcement of liquidated damages clause against the Sub-contractor by the Main Contractor might
be challenged in case of Administrative Contracts (Public Works) on the ground of Article 3206 (3) of the
Civil Code-Sub-contract.
9.4 Would your opinion be different if the Sub-contractor were a nominated one? If yes, why & if
not, why not? (2.5%)
Answer
Cost has its proven importance as the prime factor for project success. Most of the significant
factors affecting project costs are qualitative such as client priority on construction time;
contractor’s planning capability, procurement methods and market conditions including the level
of construction activity (Elchaig et al, 2005). A project otherwise completed may not be regarded
as a successful endeavor until and unless it satisfies the cost limitations applied to it. In spite of
its proven importance it is not uncommon to see a construction project failing to achieve its goal
within the specified cost.
Answer
According to Clause of 6.1 (Health and safety) under the MDB FIDIC, and clause 19.1 of PPA,
The Contractor shall be responsible for the safety of all activities on the Site. And clause 4.9
(quality assurance) of the MDB, the contractor shall institute a quality assurance system to
demonstrate compliance with the requirement of the contract. Clause 8.2 (Time for completion),
the contractor shall complete the whole work and each section ( if any), within the time for
completion for the works or section (as the case may be).
3. Role of the Engineer (6%)
a) Discuss the different roles of the engineer as contract administrator & project supervisor only during
the execution phase of a construction project. You are expected to mention & discuss three functions
under each type of role;
b) Discuss also the possible five negative effects in contract administration and/or project supervision
during the execution phase of a construction project in the absence of such Engineer.
You may apply MDB-FIDC or PPA conditions of contract for your analysis; Instruction:
5. Role of engineer
Construction Supervision
With respect to Construction supervision, once work starts on the project, to supervise
or to inspect the work carried out by the contractor in order to ensure conformity with the
design requirements.
Contract administrator
Especially the role of the consultant as contract administrator divided in to the following
distinct role.
a. Agent Role
The agent role is further divided in to power & function.
Power
The following are some of important powers of the consultant.
Power to make contracts, if authorized by the client;
Power to instruct variations, if authorized;
Power to order suspension of the performance of the works, if authorized;
Power to delegate its functions to assistants, if allowed; (This is true in case of ,
Resident Engineer, Engineer’s Representative, Clerk of Works, Independent
Inspectors, Quantity Surveyors).
Function
The following are some of important functions of the consultant.
Advising the employer;
On costs of the project;
on appointment of particular contractors;
on appointment of subcontractors;
on rights & obligations of the employer under the construction contract, ( for
example, in relation to taking insurance by the employer),
on informing the breach of contracts by others(consultants, contractors); Issuing
instructions to the contractor under the construction contract in writing;
Providing information to the contractor;
Contract documents;
contract drawings;
unprimed bill of quantities and any other amendment thereof(BOQ);
accurately dimensioned drawings(for the purpose of setting out);
Inspecting & monitoring of the construction works;
all the works to be executed under the construction contract,
to carry out tests of any materials,
to detect bad workmanship & defect;
Performing quantity surveying functions;
Certainly through a qualified quantity surveyor;
Professional or independent Role;
Consultative role;
b. Professional Role
The independent role of the consultant may be expressed in the following professional
functions.
Certification function;
Other decision-making functions;
Certification Function
The consultant may certify & issue the following certificates under the terms of
the construction contract.
Interim Payment Certificates;
Final Payment Certificate;
Event Recording Certificates;
Certificate of non-completion; in case of delay for the purpose of triggering the
machinery of liquidated damages;
Certificate of practical/substantial Completion certificate;
Certificate of Completion of making good defects;( or Defects Liability Certificate)
c. Consultative Role
Undertaking Consultation both with the employer & the contractor, under the relevant
construction contract, before making any determination; this role is a new one
introduced through the New FIDIC Red Book. See also Clause 3.5 cum other clauses of
same of the MDB Version of FIDIC;
Decision Making Function
This days may be controversial;
Is taking determination, for example as per Clause 3.5 of FIDIC & MDB
Conditions of Contract by the Engineer a decision?
c. What would be your professional opinion whether or not the contract time being calendar
days or working days? Does it have any legal or contractual effect if the contract time were
either calendar days or working days? Why? Discuss & support your position by doing
some calculations. (5%)
Answer
My professional opinion is it is better to make agreement with Calder days for better
management than working days. Yes
Contractual effect
Liquidated damage
Legal effect
Effect of contract and or legal effect 1731
d. Assuming that the collapse of the two bridges were caused due to poor design, is there any
liability of the engineer towards the employer (i.e. the Client) under their agreement? If
yes, why? If not, why not? Assume that their agreement was based on the PPA
Consultancy Services Agreement ICB 2006. (2.5%)
Answer Yes, because the liability of the consultant shall be seen in light of the:
Type of professional services they contractually undertake to provide;
The specific contractual arrangement made between the client & the consultant; and.
The interpretation of the applicable law;
e. Assuming that the collapse of the two bridges were caused due to poor workmanship, is
there any liability of the engineer towards the employer (i.e. the Client) under their
agreement due to lack of supervision? If yes, why? If not, why not? Assume that their
agreement was based on the PPA Consultancy Services Agreement ICB 2006. (2.5%)
Answer
PPA 17.1
the contractor has also argued that the method for the calculation of the reductionof the
capacity of the plant has never been agreed;
the contractor has also further argued that loss of water sales has never been agreed
between the contractor & the employer; therefore, the construction company shallnot be held li
able for the situations not provided in the contract;
You are a well-known Construction Management & Claims Specialist in the country. Both
the employer & the contractor have come to your office to solicit your professional adviceto res
olve their disputes.
Examination Questions
a) What are the disputes, if any, between the employer & the contractor? Identify &
discuss their merit;
b) What is your professional opinion on & justifications for the validity of the
contractor’s argument in relation to the maximum extent of the liquidated
damages? Discuss;
c) What are the essential points that you should consider regarding the claims
pertaining to reduction of the contract price?
Please, refer MDB Clause 9.4 (Failureto Pass Tests on Completion) Discuss;
d) What is the extent of the reduction of the contract price in your professional
approach & method? Why? Discuss. Please, refer the same Clause 9.4 (Failure toPass
Tests on Completion);
e) Is the contractor correct in denying any liability pertaining to loss of water sales? If
yes, why? If not, why not? Discuss.
Please, consider legal liability of the contractor,if any?
f) What kind of dispute resolution mechanism do you suggest for the parties to settle
their disputes, if any, and why? Discuss;
Instructions: You may refer to MDBFIDIC (2006) or PPA (2006) conditions of contract tosuppo
rt your position or argument or analysis;
Short answers like “yes” or “no” have no value unless supported by acceptable reasons &appr
opriate contract clauses and/or the applicable law provisions;
Answer
a. What are the disputes, if any, between the employer & the contractor? Explain. (5%)
Answer
The following are the dispute between the employer and the contractor
Liquidated damage ( Sectional or total of the project)
Method of calculation for the reduction of the plant capacity from the agreed contract.
Loss of water sale as it is not described in the contract document.
b. What are the essential points that you should consider regarding the claims of the
employer pertaining to liquidated damages? (2.5%)
Answer
The essential points are:
The sectional completion date up on which they agreed. MDB-FIDIC clause 8.2 in relation
with clause 8.7
The agreed liquidated damage on the daily payment of liquidated damage for the section.
The duration of delay of the section.
Notice of the claim by the employer should be submitted to contractor within 28 days
according to MDB- FIDIC clause 2.5.
The important clause on which the claim is based.
c. What is your professional opinion on & justifications for the validity of the
contractor.’ argument in relation to the maximum extent of the liquidated damages?
(2.5%)
Answer
My professional opinion is according to MDB-FIDIC clause 8.7 (delay Damage) and clause 8.2
the contractor is liable for delay to pay a liquidated damage for the employer. In parallel with this
in this case study as per the agreement of the employer and the contractor the contractor is only
liable for the section that he delayed. Therefore, the contractor is liable only for the plant work
which is delayed for 300 days to pay maximum liquidated damages.
d. What are the essential points that you should consider regarding the claims pertaining to
reduction of the contract price? Please, refer to Clause 9.4 (Failure to Pass Tests on
Completion) of the MDB Conditions of Contract. (2.5%)
Answer
The essential points that we should considered are:
Contractor’s obligation under the contract
Can the employer reduce the contract price.
The reduction value of the contract price shall be appropriate to cover the reduced
value to the Employer as a result of this failure.
Weather the Method of calculation in the contract data is indicated or not
e. What would be the extent of the reduction of the contract price in your professional
approach & method? Why? Please, refer to Clause 9.4 (Failure to Pass Tests on
Completion) of the MDB Conditions of Contract.
Answer: In my professional approach and method the reduction of the contract price should be
done in two cases:
Case 1 If the method of calculation for reduction of price is indicated in the contract document
the contract price should be reduce
For reductions in capacity of the plant
Cost of planning designing, construction and supervision of 100,000CM/d. or cost for
remedying the defect occurred in the plant
Case 2 If the method of calculation is not indicated on the contract document the contractor and
the employer require the reduction of the price to be agreed by both Parties (in full satisfaction
of this failure only) and paid before this Taking-Over Certificate is issued, according to MDB –
FIDIC clause 9.4.
f. Is the contractor correct in denying any liability pertaining to loss of water sales? If yes,
why? If not, why not? (5%)
Answer
Yes, because according to MDB-FIDIC clause 17.6 “Neither Party shall be liable to the other
Party for loss of use of any Works, loss of profit, loss of any contract or for any indirect or
consequential loss or damage which may be suffered by the other Party in connection with the
Contract, other than as specifically provided in Sub-Clause 8.7 [ Delay Damages ]; Sub-Clause
11.2 [ Cost of Remedying Defects ]; Sub-Clause 15.4 [ Payment after Termination ]; Sub-Clause
16.4 [ Payment on Termination ]; Sub-Clause 17.1 [ Indemnities]; Sub-Clause 17.4 (b)
[consequences of Employer’s Risks ] and Sub-Clause 17.5 [ Intellectual and Industrial Property
Rights ]”. Therefore, loss of water sale is consequential loss of use of the plant and the contractor
is correct in denying the liability towards this situation.