Professional Documents
Culture Documents
Serbia Railways Asset Management Plan Using Life Cycle Costs
Serbia Railways Asset Management Plan Using Life Cycle Costs
May 9, 2020
Transport
.
Public Disclosure Authorized
Public Disclosure Authorized
This work is a product of the staff of The World Bank. The findings, interpretations, and conclusions expressed in this work do not necessarily reflect
the views of the Executive Directors of The World Bank or the governments they represent. The World Bank does not guarantee the accuracy of the
data included in this work. The boundaries, colors, denominations, and other information shown on any map in this work do not imply any judgment
on the part of The World Bank concerning the legal status of any territory or the endorsement or acceptance of such boundaries.
The material in this work is subject to copyright. Because The World Bank encourages dissemination of its knowledge, this work may be reproduced,
in whole or in part, for noncommercial purposes as long as full attribution to this work is given.
Attribution—Please cite the work as follows: “World Bank. 2020. Serbia Railways Asset Management Plan Using Life-Cycle Costs. © World Bank.”
All queries on rights and licenses, including subsidiary rights, should be addressed to World Bank Publications, The World Bank Group, 1818 H
Street NW, Washington, DC 20433, USA; fax: 202-522-2625; e-mail: pubrights@worldbank.org.
LIST OF FIGURES
LIST OF TABLES
This study has been funded by a generous grant from the Mobility and Logistics MDTF.
The report was prepared by a World Bank team led by Victor Aragones, Senior Transport
Specialist, Task Team Leader; Rodrigo Archondo, Senior Engineer; Svetlana Vukanovic, Senior
Transport Specialist; and Helena Goetsch, Junior Professional Officer. Desanka Stanic (Program
Assistant), Andoriah Indah Purwaningtyas (Program Assistant), and Graciela Tejeda (Program
Assistant) provided support to the team throughout the study.
The report benefited from the comments of peer reviewers Simon Ellis (Program Lead) and
Wenyu Jia (Senior Urban Transport Specialist). The team is grateful for the guidance provided by
Stephen Ndegwa (Country Manager), Karla Gonzalez Carvajal (Practice Manager for Europe), Juan
Gaviria (Former Practice Manager), and Baher El-Hifnawy (Former Lead Economist). The World
Bank would like to recognize Peter Veit, Branko Bajatovic, and Stefan Marschnig for their
dedication and effort during the implementation of the life-cycle costs method and its
documentation outlined in this report.
The World Bank team would like to formally thank the Ministry of Construction, Transport, and
Infrastructure (MCTI), Infrastruktura Železnice Srbije (IZS), Srbija Voz, and Srbija Cargo for
fruitful discussions, consultations, ideas, and access to data and information.
Understanding the life-cycle cost (LCC) of rail infrastructure is key to managing assets in an
efficient manner. Similar to financial sustainability, efforts toward infrastructure sustainability must
account for the full costs of constructing, operating, maintaining, and renewing infrastructure.
Knowing these costs enables infrastructure managers to choose how to optimize investments
under existing conditions.
The introduction of the LCC model, through the World Bank technical assistance (TA) described
in this report, created the capacity within Serbian Railways Infrastructure (Infrastruktura Železnice
Srbije, IZS) to account for the costs of rail tracks through their life cycle. Importantly, the model
was adjusted to local conditions by IZS staff, who now will be able to continue using this tool to
augment the organization’s capacity in rail asset management (RAM).
In general, RAM is a practice of systematically managing rail assets through their life cycle. This
approach to managing rail assets provides more value for the money being invested, whether in
capital or operations and maintenance. By managing assets’ performance, risks, and costs,
practitioners can ensure a greater degree of safety in a more cost-effective manner. This translates
into higher levels of service for rail customers.
Ideally, RAM encompasses all components of a rail system, such as tracks, structures, equipment,
signaling, and others. In the process, analysts try to identify the most cost-effective way of
constructing, maintaining, and renewing infrastructure over its entire life cycle. For example, when
looking at track, analysts will gather information about the type of ballast (limestone or granite),
crossties (wooden or concrete), rails (49E1-R260-CWR or 49E1-R260-jointed), and welding
(alumino-thermic or flash butt). An infrastructure manager will be able to estimate the track
needed, based on the expected service life and under specific operating conditions, when different
components are used. The same logic applies to maintenance practices. A global wealth of
knowledge about rail maintenance can be utilized to determine the frequency of maintenance
activities needed to ensure customers receive a particular level of service. Some maintenance
activities, such as grinding or tamping, can enhance safety and maintain service life if performed
with the ideal frequency.
RAM also enables technical staff and decision-makers to learn about the consequences of deferring
maintenance, including shortened service life. Beyond the loss of service life, a RAM system will
estimate full costs not only to the infrastructure manager, but also to society as a whole (including
rail customers and the general public).
The LCC model offers a simple and low-cost way to estimate the life cycles of track infrastructure
and its associated costs. This is important, as its concepts and principles constitute the foundation
for the establishment of more advanced RAM systems. The TA that is the subject of this report
introduced this capacity in IZS, which paves the way for further advances in RAM that, ideally, will
move beyond track infrastructure (i.e., the focus of this TA) to cover all rail system components.
The introduction of RAM in Serbia is important at this time. Even as the sector is being revitalized,
existing railway assets have fallen into a state of disrepair due to inadequate maintenance over the
past 30 years. The absence of RAM allowed scarce maintenance budgets to be misallocated and
used in a nonstrategic manner to address only immediate emergency needs. This created a vicious
Main Recommendations
During the preparation of the TA, IZS and the World Bank team decided that the implementation
of the LCC model is best followed by three groups of actions in support of full RAM
implementation. The actions relate to cost estimation, cost coding, and the augmentation of
management reporting. IZS is currently identifying the most efficient ways to implement each
action.
A RAM system goes beyond having an LCC model. It is important for IZS to continue its efforts
on this front by creating a system that will generate the data needed for more context-specific
analysis, continue to improve the LCC model, integrate the LCC model with costs accounting
(estimating and coding), and utilize the LCC’s model output to generate the proper RAM
• Equip IZS to analyze its own efficiency in the delivery of service life, and in cost recovery. This TA has
created the capacity within IZS to analyze service life and cost recovery, but more can be
done to ensure that the knowledge in the working group is institutionalized and becomes
part of the organization.
• Prepare output-driven maintenance plans. It is key for the LCC method, database, and software to
be used to generate output-driven maintenance plans. Such plans can then be used in
budget deliberations with the Government of Serbia to determine the best way forward in
securing a sustainable level of service across the network.
• Identify the costs of individual maintenance efforts. Current cost accounting does not have the
capability to identify where maintenance funds are being spent in the network. This would
enable mapping of the maintenance investment in the rail network and more accurate data
for use in the LCC method. This in turn would provide better information regarding the
remaining service life in the network and areas of the rail system that require attention.
Furthermore, this would enable decision-makers to know if resources are being spent in the
segments of the network that have higher levels of traffic.
• Strengthen the integration of RAM tools with the decision-making process. This is to ensure that
outputs and documents being produced by the LCC model and the other components of
the emerging RAM system are used in the planning process for the maintenance and
renewal of infrastructure. Furthermore, the outputs of the RAM system should also be
integrated in overall management decisions within IZS and in its dealings with MCTI,
Serbia Cargo, and Serbia Voz.
The proposed implementation plan is structured around four specific groups of tasks:
1) Appoint and empower the IZS working group to manage the implementation scope;
2) Implement a robust cost estimating approach;
3) Enhance cost coding to enable maintenance project identifications;
4) Augment management reporting.
• The set of standard elements to be used in the Standard Elements (StE) approach needs to
be enlarged so long as standard elements cover 80 to 90 percent of the network.
• Speed restrictions must be monetized, using an approach that is feasible given the existing
data.
If these challenges are addressed, the use of StE approach can then support:
• The identification of components to be used for different parts and lines in the network.
• The development of a track asset management database system that integrates the LLC
model, IRT, and GIS.
The IZS working group, which started its work in mid-2018, is by now composed of informed and
experienced members who have already delivered first results. This group is well positioned to
oversee the implementation of the next steps with proper support from the leadership of the
company and decision-makers in the Government of Serbia.
Furthermore, the LCC method should be used extensively in the upcoming years as the Serbian
railway system sees a significant increase in investment in the rehabilitation of its rail lines. This will
provide an easy-to-use tool in determining investment options and estimating the LCC of new
infrastructure, avoiding potential mistakes that could affect the performance and sustainability of
the railway sector in the long term.
The objective of the World Bank’s technical assistance (TA) in the asset management planning of
Serbia’s railways, using the life-cycle cost (LCC) method, is to improve the condition of key track
infrastructure in the country. The appropriate use of the LCC model would enable Serbian
Railways Infrastructure (Infrastruktura Železnice Srbije, IZS) to optimize the use of the scarce
financial resources available for maintaining track infrastructure. The LCC model offers a simple
and inexpensive way to estimate the longevity and condition of track infrastructure and the costs
associated with its renewal and maintenance. This is important, as the model’s concepts and
principles form the foundation for the establishment of a more advanced rail asset management
(RAM) system. This TA introduces this capacity in IZS, with a focus on track infrastructure, and
thus paves the way for further advances in RAM, which ideally will cover all rail system
components (structures, signaling, rolling stock, and others).
This is important for Serbia at the moment; many railway assets have fallen into a state of disrepair
due to inappropriate maintenance, and are in suboptimal condition. The limited funds available for
maintenance are often allocated in a nonstrategic manner to address emergency needs. This creates
a vicious cycle in which assets deteriorate to the point where they have to be rehabilitated.
Meanwhile, overall costs could have been reduced through timely maintenance.
This TA followed a World Bank policy note, prepared in 2015, that recommended
commercialization and efficiency improvements in Serbia’s railways. The implementation of the
LCC method complements these recommendations by providing specific guidance on improving
the cost-effectiveness of Serbia’s rail infrastructure.
Another important event in Serbia’s rail sector was the reform of Serbian Railways, supported by
the World Bank through two development policy operations (DPOs). Serbian Railways, once a
vertically integrated company, was unbundled into three separate businesses, that today handle
infrastructure (IZS), passenger transport (Serbia Voz), and cargo transport (Serbia Cargo).1 This
new structure generated the need for a variety of services and transactions to be performed
between the three rail businesses. For example, IZS transitioned from being a department of
Serbian Railways to being a corporate entity of its own. It is now tasked with maintaining and
developing railway infrastructure and providing traffic dispatching and coordination services.
Contrary to the previous practice, access to railway infrastructure is no longer “free” for operators
but involves a fee. Related to this change, IZS’s scope of responsibility now includes decision-
making on a variety of issues, including revenue, expenditure, and costs. These financial outcomes
have to be reflected in IZS’s own profit and loss statement, among other financial statements.
These changes imply that the infrastructure manager is now directly responsible for ensuring that
the network can provide the level of service needed at the agreed access fee.
A key feature of the new railway setup is the permanent interface between the operators and the
infrastructure manager. The infrastructure manager allocates a path, which is purchased by the
operator. Thus, the infrastructure manager has an underlying obligation to provide service to the
Rail Asset Management and Its Importance for a Sustainable and Safe
Railway
In general, rail asset management (RAM) is a practice of systematically managing assets through
their life cycle—that is, procuring, operating, inspecting, maintaining, rehabilitating, and replacing
them.2 This approach to managing rail assets provides greater value for the money spent over an
asset’s lifetime by managing performance, risks, and costs. In other words, when properly
managed, rail assets can support the functioning of a safe, cost-effective, and reliable rail
transportation system on a life-cycle basis.
A RAM system comprises all the methods, procedures, and tools used to optimize costs,
performance, and risks across all rail infrastructure and rolling stock. This means that track,
structures, and equipment—among the other components of a rail system—must be considered in
the RAM context. Furthermore, a complete RAM system will take into account the full costs
related to each stage in an asset’s life cycle, and consider how each decision affects the service life
of the asset and its cost. This supports their optimization—that is, the most cost-effective way of
constructing, maintaining, and renewing infrastructure over their life cycle. The detailed data
supporting a RAM system will also enable technical staff and decision-makers to learn about the
consequences of each possible decision. In the process of looking at these, analysts must not only
take into account the costs to the infrastructure manager but also to society as a whole (including
rail customers and the general public).
In sum, RAM allows an infrastructure manager to find the right balance of initial investment and
maintenance, of a preferred level of service and an expected service life. These factors are not fixed
but depend on the operations and characteristics of a railway system. As such, technical staff and
management must be able to use RAM tools in a contextual manner to make the appropriate
decisions.
As noted in the introduction to this report, Serbia’s rail sector has started a process of reform and
been reorganized into vertically separated companies. The implementation of a RAM system in
Serbia is needed at this critical juncture. The railway system is expected to see a significant level of
investment in the coming years, and needs to prepare so it can manage its assets. Careful planning
will ensure that this investment provides the expected level of service for the expected number of
years at the expected cost. Otherwise, the risk is to lose the initial investment through improper
maintenance, prompting a gradual deterioration in the level of service and eventually resulting in a
lost opportunity to use new infrastructure to attract passengers and freight to the railway system.
Reflecting the importance of institutional attributes, this section reviews the current organizational
setup of IZS and its obligations as an infrastructure manager.
2Federal Transit Administration, “Final Rule Transit Asset Management,” Federal Register Vol. 81, No. 143, July 26,
2016, https://www.govinfo.gov/content/pkg/FR-2016-07-26/pdf/2016-16883.pdf.
3Carr, Gary A., Ali Tajaddini, and Boris Nejikovsky, “Autonomous Track Inspection Systems—Today and
Tomorrow,” AREMA Annual Conference and Exposition Proceedings, Chicago, IL, September 20–23, 2009.
4 Ibid
5 As a public utility in Serbia, IZS is required to follow a government-prescribed format for its business plan.
Collectively, the four initiatives provide a strong platform for IZS to strengthen delivery of the
scope of its infrastructure contract9 with the MCTI through (i) delivery of its business plan and
network statement (“institutional obligations”) and (ii) improved efficiency of service life provision
for its assets and cost recovery of its operations (“managerial obligations”). When completed, the
four initiatives will further improve IZS’s ability to deliver its obligations.
Table 1. Mapping of Ongoing Initiatives and IZS Obligations
Obligation
Institutional Managerial Managerial Institutional
Network Efficient service Cost recovery of
Initiative Maintenance Plan
Statement life provision operations
Asset Register
Integrated
Trafic Data
Railway
Cost Data
Database
Revenue Data
Introduction of Standard Elements
Introduction of SAP
Introduction of "Timesheet"
Primary relevance in addressing the obligation
Secondary relevance in addressing the obligation
• Asset register. This element of the database is structured to include details required for annex
6 of the network statement, allowing IZS to produce annex 6 as an immediate deliverable
9 Three key elements of IZS’s scope under the contract include (i) infrastructure maintenance and network upgrades;
(ii) traffic management, security, and safety of infrastructure; and (iii) project preparation in support of network
development.
10 On December 2018, the database was transferred to IZS for further development.
Regional Lines
SRIM SRIM
Data source: Data source:
SRIM Data source:SRIM Data source: Data source: Data source:
SRIM Block 2: Traffic SRIMdata SRIM SRIM SRIM SRIM
(UIC categories of data)
Passenger trains Passenger trains Freight trains (last Freight trains
(last 5 years) (current year) 5 years) (current year)
Data source: Data source: Data source: Data source:
Main Lines
Data source: Data source: Data source: Data source: Data source:
Annex 6 SRIM Diagnostic SRIM SRIM
(Network Data source: Data source:
train readings Data source: Data source:
Local Lines
Data source: Data source: Data source: Data source: Data source:
Local Lines
Note: SEETO = South East Europe Transport Observatory; SRIM = Serbia Railways Infrastructure Manager; TBD =
to be decided.
11 As of December 2018.
12 For simplicity, the traffic load information may be recorded, stored, and updated elsewhere from the database.
• The structure of the asset register enables production of annex 6 of the network statement
as an immediate deliverable. The asset register also acts as a data repository for an analysis
of service life and the development of maintenance plans.
• The components devoted to data on traffic, costs, and revenue are direct inputs for the
maintenance plan, and also an analysis of service life and the cost recovery of IZS
operations.
4 2
Completion
and Budgeting
Reporting
3
Execution
and Cost
Monitoring
Observations made for each step in the maintenance value chain are presented in terms of where
the step fits in the overall picture, what entity is responsible for it, and how it interfaces with
ongoing initiatives.
It is important to note that the current IZS method for planning maintenance is based on track
conditions. Thus, it is more reactive than systematic. In many other rail systems around the world,
maintenance is prioritized and planned with a longer-term horizon based on the life years of the
track and the volume of traffic that moves over it.
Definition of Scope
On an annual basis, the Infrastructure Maintenance Department (Center for Infrastructure Works
Supervision) assesses the conditions of all assets in the network and determines the scope of
necessary works based on the conditions observed in the field. Considering the level of resources
required, a decision is made whether the work can be undertaken using in-house resources under
the maintenance budget category (and thus becoming an operating expenditure, OPEX) or needs
to be externally funded and be treated as an investment project (such as a renewal or upgrade
requiring capital expenditure, CAPEX).
Following site reports from the infrastructure supervision teams, IZS’s civil works and electrical
works teams propose the scope required to bring the asset quality in line with the original
specification. This is executed in a bottom-up fashion and shown per individual line. As a result,
the proposed maintenance scope is broken down by functional input and is driven by affordability
rather than the expected traffic on the line. Given the significant maintenance backlog, the majority
of estimated work is reactive and considered an “urgent intervention.”
• Organizational unit;
• Line (main, regional, local, other); and
• Ledger account and subaccount for the relevant asset (structure, level crossing, item of
plant, other).
Discussions with IZS’s experts have shown that a standard estimating approach in IZS takes
account of materials and related costs but typically excludes a number of direct cost items,
including the costs of (i) in-house stock (when items such as sleepers and rails are taken from
reserves or from a different location), (ii) labor (which are included as such only in the business
plan14), (iii) fuel and lubricants, and (iv) the depreciation of the plant and equipment used in
specific activities. These costs are subsequently budgeted in aggregate in the business plan, and
shown to be part of human resources, depreciation, or other costs.
Once the total maintenance budget is developed and negotiated, it is allocated to the individual
lines as part of the annual maintenance plan.
The infrastructure maintenance departments in charge of civil works and electrical works take
ownership of the budgeting task. Once the budgets are developed, they become the responsibility
of the Department for Planning and Analysis.
The introduction of SAP and the cost recording application will significantly improve the
budgeting (costing) of the identified scope through the availability of accurate cost inputs across all
cost categories.
14Review of the 2018 Maintenance Plan and Business Plan highlighted that the maintenance budget for 2018 is
estimated at SRD 1,173 million. This figure, as per the Annual Maintenance Plan, excluded indirect costs. If this were,
indeed, the total 2018 direct maintenance costs, it would imply that infrastructure maintenance, being the core
corporate activity, accounts for only 9 percent of 2018’s corporate total cost (estimated at SRD 13,487 million). In
comparison, the labor cost component for 2018 is estimated at SRD 6,005 million (44.5 percent of total cost). Using a
similarly “skewed” reporting proforma, the first infrastructure contract estimated infrastructure maintenance at a cost
of SRD 1,400 million (by excluding similar cost categories as above) and traffic management at SRD 6,100 million.
Captured in the AS. Can be reported per type of works Captured and reported per invoice but not per
1 Material
(Civils/Electrical) but not per project/ location. project/location.
Captured in the AS. Can be reported per type of works Captured and reported per invoice but not per
2 Fuel and lubricants
(Civils/Electrical) but not per project/location. project/location.
The cost exists and should be budgeted for but is not The cost exists and should be budgeted for but is not
8 Cost of access (possessions)
tracked by the IZS AS tracked by the IZS AS
Note: AS = accounting system; IZS = Serbian Railways Infrastructure (Infrastruktura Železnice Srbije).
Most importantly, while the current cost coding enables some level of identification of the location
where the cost was incurred, there is no code available for the project number and information
about why the cost was incurred in the first place (e.g., to enable a greater traffic load and greater
access charging revenue or the achievement of some strategic state goals for a specific line or
region). In consequence, IZS (i) has no accurate means to determine the total cost of its individual
15Similarly, the current situation makes the budgeting of CAPEX works also difficult as IZS relies on tender prices for
the unit costs when budgeting for work that is to be completed by parties other than IZS. The tender prices used
therein do not reflect the completed work because they (i) are driven by the contractor’s aggressive pricing and
willingness to win work at a different point in time than the budgeted work is scheduled for; (ii) do not take account of
whether 100 percent of work has actually been completed for 100 percent of the funding; (iii) are unclear whether,
how, and if scarce resources and concurrent projects are taken into account in the unit cost calculation; and (iv) do not
reflect the “total outturn costs” since they do not account for variations in scope, legal settlements arising from claims,
and “below the line” costs that have not been budgeted for but have been incurred by IZS as a result of delivering the
works.
This chapter describes the application of the LCC method in support of effective rail asset
management. It begins by describing the principles underlying the methodology and the specific
points at which it can add value to an organization’s overall decision-making processes. This is
followed by an outline of the data required as inputs for the model, and the overall logic behind the
methodology.
System Adequacy
Rail is perhaps the most efficient land transport mode to move heavy commodities over long
distances. It is well known that railways excel when they are well maintained and are used to move
a large volume of freight over long distances. When used for passenger transport, railways may
excel in particular markets, such as for medium-distance travel in high-density urban and suburban
agglomerations. Thus, a rail system’s general assessment looks at the market (possible customers
in passenger and freight transportation) and production (number of trains operated). If both
variables are deemed adequate, then it becomes clear that assets need to be managed sustainably
and with a focus on long-term economic efficiency. System adequacy is thus based on the
determination of three main factors:
1. An adequate market—that is, if infrastructure capacity is appropriate, given market demand.
Capacity involves not only the actual amount of service but the quality as well. A railway
system should adjust capacity to meet changes in demand.
2. Adequate production, achieved once a predetermined number of trains and volume of
passengers and/or freight are transported on the system.
3. Adequate rail assets, based on predetermined standards for the size, quality, and amount of
each rail system component.
TU Graz, in collaboration with the Austrian Federal Railways (Österreichische Bundesbahnen,
ÖBB), set benchmarks for an adequate market for ÖBB. These benchmarks were used to assess
the passenger traffic and freight volumes of the Serbian rail network (tables 3 and 4).
Table 3. An Assessment of Passenger Traffic on Serbian Railways
Passenger Traffic
1 Average speed ≥ 60 km/h
(in competition with an overland road)
2 Degree of utilization of the infrastructure capacity ≥ 50%
(~ 40 trains per day)
3 Minimum utilization of rolling stock
40% of seats or 20% of seats and stance
4 Relation riding time: Holding time > 10 : 1
Potential passengers > 2,000 per day (60 min. isochrones) (about 50 passengers per
train)
Minimum demand
80 hop-ons/hop-offs per day for an additional station
(1 hop-on and 1 hop-off per train)
Note: km/h = kilometer per hour.
Once system adequacy at the level of the market, production, and assets is considered, rail lines can
be assessed at a technical level to determine the best maintenance or renewal strategy, and the
remaining service life of assets. At this point, data can determine whether maintenance or renewal
is the best course of action for a given line or track. The first step in determining how to assess this
life cycle is to determine the data that are available about the network.
Rail
Ballast
Crossties
Subsoil
Source: Photo from TU Graz with information from the World Bank, 2020.
Ballast is the material used to form the bed of the railroad track and to maintain crossties in place.
In order to meet its function, ballast needs to be permeable and granular, and is placed under and
around ties to fix the structure in place. Ballast must provide adequate drainage by allowing water
through easily. Some of the materials used as ballast are granite, basalt, limestone, dolomite, and
gravel.
Sleepers (or crossties) are wooden or concrete beams laid transversely under the rails of a railroad
track to support it. Crossties can be timber, concrete, composite, and even steel. The most popular
types are wooden and steel. The ties normally are assembled together with the rails through steel
plates, fasteners, or other devices.
Rails are the steel bars laid on the crossties. The many types of rails vary depending on weight, size,
and type of steel. Continuously welded rail (CWR) has a length of 438 meters and performs better
for heavier or faster train operations. The other type of rail is “bolted” or “jointed” track. These
tracks are joined with bolts. A better alternative is to weld the different segments of rails, called
welded rail.
Figures 8, 9, 10 and 11 show how different sections in the network provide the data necessary to
generate work cycles. Each section was constructed at different points in time (in this example
section I in 1985, section II in 1975, and section III in 1990). There is also record about when the
first slow order was put in each section. Data between construction and slow order is the input
data for the work cycle. In this example, section I provides data for years 0 to 19 in the working
cycle, section II provides data for years 20 to 43, and section III provides data for section I
provides data for years 10 to 33.
Note: See Appendix B for a clearer image. ML = main line; RL = regional line.
Note: See Appendix B for a clearer image. CWR = continuous welded rail; SKL = tension clamp fasteners.
Note: See Appendix B for a clearer image. CWR = continuous welded rail.
• Nova Pazova–Stara Pazova is a 6 kilometer (km) segment with a design speed of 120
km/hour(h). The line has no speed restrictions, and freight trains operate at a speed
limit of 80 km/h. This is a main line with two tracks. Results show that the two tracks
still have adequate service life left. However, one of the tracks has already lost some of
its service life that will not be possible to recover (Track A). In the best case, under
sufficient maintenance practices, Track A would end in 2023 (without speed
restrictions). Track B is still within its optimal service life, and under adequate
maintenance, its service life would end in 2043.
• Lapovo–Brzan stajaliste is a 4.6 km segment with a design speed of 120 km/h. The
segment is double tracked but the prescribed speed on the left track is 50 km/h and 70
km/h on the right track. This is a main line. In this case, the LCC method indicates that
the service life for both tracks has already been reached and costs will increase
continuously until tracks are renewed. The best time to re-lay the tracks would have
been 2014, so it is important to reinvest in the line in the near term.
• Adrani–Samalia is a 5.8 km segment with a design speed of 100 km/h. There are no
speed restrictions on the line. This is a regional line. Service life of this line has been
reached. However, its costs are flat and its service life can be extended but major
While the results of the case studies were interesting and insightful, more importantly, the lesson of
the first stage was that the LCC method can be successfully implemented in Serbia. This is because
enough data exist within IZS to use the LCC method, and data would become more readily
available once the IRD was completed. These two factors persuaded IZS to move forward with the
implementation of the LCC method over the entire Serbian rail network.
2,000–5,000
5,000–8,000
8,000–15,000
15,000–30,000
30,000–45,000
45,000–70,000
70,000<
Track geometry—radius. Serbian rail lines normally have a radius of less than 200 meters (m) to more
than 600 m. Under this parameter, the working group decided to remove alignment categories
between 1,000 m and 3,000 m and more than 3,000 m that are often observed in other European
railways.
Table 6. Rail Line Radius
Alignment
(R<200 m)
250 m ≤ R<400 m
400 m ≤ R<600 m
R>600 m
3,000–1,000 m
>3,000 m
Subsoil quality. This is the only parameter that is not measured but is more an observation by experts
that must try to fulfill a description. Good subsoil does not impact maintenance demand or service
life. Standing water means that subsoil has a problem with drainage. Soiling means that residue
needs to be removed from track structure in order to recover the state of repair. Soiling and
standing water mean that track structure is being affected by the presence of both soil and water.
Table 7. Subsoil Quality
Subsoil
Good
Water
Soil
Sleeper type. The Serbia case presents two main sleeper types: concrete and wood. This is similar to
the international experience.
Table 8. Sleeper Types
Sleeper Type
Concrete SKL
Wooden K
Wooden nails
Rail type. Table 9 includes three rail parameters: rail profile, steel grade, and welding type. This is the
rail type that is used to build the track and specifies the steel and other quality characteristics that
will determine the strength, quality, and durability of the rail. For Serbia, 49E1 and 60E1 rail
profiles were identified. As can be seen in table 9, both continuous welded rails (CWR) and jointed
rails are used in Serbia. In terms of steel grade, R260 is the main steel grade used in Serbia and no
other steel grades are included in the parameter set.
Table 9. Rail Types
Rail Profile Welding Type
49E1-R260-CWR Alumino-thermic
60E1-R260-CWR Flash-butt
49E1-R260-jointed
60E1-R260-jointed
(Xa-R200-jointed)
The remaining parameters are self-explanatory. In terms of ballast there are only two main ballast
types used in Serbia: limestone and eruptive. There are both single- and double-tracked lines in
Serbia.
Once these parameters and their viable values were identified, the working group came up with the
most likely combinations to be used in Serbia. This was based on their experience and knowledge
of the Serbian railways. These parameter sets are shown in table 10. The objective at this stage was
to cover as many kilometers as possible by finding the most common component combinations.
The 11 parameter sets in table 10 are likely to cover a large percentage share of the Serbia network
with the goal for the working group to cover 80–90 percent of the total railway network.
Note: CWR = continuous welded rail; K = k type fastening; m = meter; R = radius; SKL = tension clamp fasteners.
Once these 11 parameter sets were generated, the World Bank team and the IZS working group
agreed to move forward in designing 11 work cycles for the Serbian rail network. Work cycles are
the normal (expected) maintenance levels, renewal frequencies, and the life of the parameter sets in
a particular country (in this case, Serbia). Eleven work cycles were chosen that were likely to cover
a significant portion of the network and provide a good learning experience to the working group.
The work cycles were then to be discussed in a workshop in November 2018 with the World Bank
transport team.
In the interim, three IZS working group members visited the Austrian Federal Railways
(Österreichische Bundesbahnen, ÖBB) headquarters in November 5, 2018. The visit allowed IZS
staff to observe how ÖBB uses the LCC method in its day-to-day activities and establish a
professional link with ÖBB experts on life-cycle costs. The visit was coupled with attendance at the
World Bank’s Railway Conference in Vienna, which brings in international experts on rail asset
management.
Subsequent to the site visit to the ÖBB headquarters, the World Bank team, the MCTI, IZS, and
the railway operators held a two-day workshop to review the IZS Standard Elements proposal.
This workshop targeted the resolution of any pending questions and issues that required discussion
and advice. IZS gathered the original data on yearly maintenance executed in different sections
representative of the parameter sets. Based on these data and after removing temporary
(maintenance) and permanent (end-of-life) slow orders, the work cycles could be set up (e.g., figure
12). The work cycles were then subject to plausibility checks and cross-checking against
international experience.
Another important part of a standard element is maintenance and renewal activity. This information was incorporated into the table by adding
numeric information regarding each type of activity. The numbers for maintenance activities reflect the work performed in intervals of a kilometer of
track.
The standard elements represent the components of the track structure, the maintenance and rehabilitation work, and the life of the track. Once this
information is in place in a table, the economic information can be included to assess life-cycle costs of the infrastructure. In the Serbia case, this
process started by IZS providing cost maintenance and renewal costs for Serbia (see table 11).
Annuity = CF x NPV
• Speed restrictions are not economically efficient, neither for shifting maintenance costs nor
for prolonging service life;
The Integrated Railways Database (IRD) and the LCC method are now being used by IZS, and it is
clear that as a consequence of deferred maintenance across multiple years, and a limited
maintenance budget for the appropriate management of IZS infrastructure, a considerable backlog
of renewal work has developed over the past 20 years. On the other hand, IZS assets must be
maintained and renewed in order to sustain network serviceability and performance. The
infrastructure usage costs are largely dependent upon whether and how the balance is struck
between maintenance and renewal. Any trade-offs need to consider the key components (asset
condition, rate of degradation, life-cycle costs, resources, technology, and access and/or
performance regimes). Although the criteria for maintenance-renewals trade-offs varies across
different assets, two principles apply to all asset groups:
• Assets maintained to a higher standard require a greater level of maintenance but are likely
to require less frequent renewals;
• Reduction in the maintenance effort will generally cause assets to degrade more quickly—
both through natural deterioration and usage—leading to a more frequent requirement for
renewals.
• The database covers all assets and provides all asset-related information on any stretch of
the network.
• All traffic flows are tracked (no of trains, train-km, net-ton-km, gross ton-km, tons).
• The database includes an interface with the cost accounting system.
IZS established a dedicated working group to test implementation of the StE approach:
• The approach is now piloted within IZS with a view to assist with identifying the most
cost-efficient option for IZS to extend service life of its assets on particular line sections.
• The approach is applied on a number of characteristic stretches of the network and, once
applied across the network, is intended to serve as a direct input for the maintenance plan.
• The piloted decision-making approach embraces the focus on customer services as it takes
into account the impact of any maintenance and/or renewal works on the operators’
delivery of transport services to customers.
In addition to these findings, IZS also developed a computer software that consists of the
following modules:
1. Logical and physical model of the data, process, and functions (according to the requests
and needed parameters of LCC methodology).
2. Creation of the Microsoft SQL Server database (according to the requests and needed
parameters of LCC methodology) for 1,906 km of the railway network.
• Equip IZS to analyze its own efficiency in the delivery of service life and cost recovery. This technical
assistance has created the capacity within IZS to analyze service life and cost recovery, but
more can be done so the knowledge in the working group is institutionalized and becomes
part of the organization.
• Prepare output-driven maintenance plans. It is key for the LCC method, database, and related
software to be used to generate output-driven maintenance plans. Such plans can then be
used in budget deliberations with the Government of Serbia to determine the best way
forward to improve the service level of the network.
• Identify the cost of individual maintenance efforts. Current cost accounting does not have the
capability to identify where maintenance funds are being spent in the network. To rectify
this would enable the mapping of maintenance investments in the rail network and more
accurate data for use in the LCC method. This in turn would provide better information
regarding the remaining service life in the network and areas of the rail system that require
attention. Furthermore, this would enable decision-makers to know if resources are being
spent in those segment of the network that have higher volumes of traffic.
• Strengthen management reporting in support of line-by-line decision-making. This would increase
transparency and strengthen the dialogue between all stakeholders in the railway sector.
Detailed information about the management of assets would enable IZS to focus
negotiations and conversation about the state of rail infrastructure to the specific areas of
concern and to highlight where the focus should be directed.
• Strengthen integration of RAM tool with decision-making process. This is to ensure that outputs and
documents being produced by the LCC model and the other components of the emerging
RAM system are used in the planning process for maintenance and renewals of
infrastructure. Furthermore, the outputs of the RAM system should also be integrated in
overall management decisions within IZS and for IZS’ dealing with MCTI, Serbia Cargo,
and Serbia Voz.
For practicality, the proposed implementation plan is structured around four specific groups of
tasks:
In terms of improving the LCC method, IZS and the rail sector in general should establish a
through-going life-cycle management in which all decisions are taken focusing on a sustainable,
future-oriented railway system. Specific next steps for the LCC method are:
• The set of standard elements needs to be enlarged so long as standard elements cover 80 to
90 percent of the network.
• Track costs must be delivered and documented on a uniform basis.
• Speed restrictions must be monetized using an approach that is feasible given the existing
data.
If these challenges are addressed, the Standard Elements approach can support:
As the IZS working group started in mid-2018, it is now constituted by informed and experienced
members who have already delivered first results. As a result, this group is well positioned to play a
key role in implementing the next steps with proper support from the leadership of the company
and decision-makers in the Government of Serbia.
Furthermore, the LCC method should be used extensively in the upcoming years as the Serbian
railway systems sees a significant increase in investment to rehabilitate its rail lines. This will
provide an easy-to-use tool in determining investment options and estimating life-cycle costs for
new infrastructure, avoiding potential mistakes that could affect performance of the railway sector
in the long term or reduce its long-term sustainability.
Source: TU Graz.
Note: ML = main line; RL = regional line.
Source: TU Graz.
Note: CWR = continuous welded rail; m = meter; R = radius; SKL = tension clamp fasteners.
Source: TU Graz.
Note: CWR = continuous welded rail; m = meter; R = radius; SKL = tension clamp fasteners.