PURPOSE
To educate and ensure competency of personnel in the organization results in world class work
environment.
SCOPE
It is applicable for all the employees working in “APEX ENGINEERS”.
RESPONSIBILITY
The overall responsibility of implementation of this procedure under Plant Head
PROCEDURE
Page 01 of 04
APEX ENGINEERS EDUCATION DOC. NO.: AQSP-29
REV NO : 01
AND TRAINING REV DATE:10.06.2021
FOR INSPECTOR
A. Induction & Department Training shall be
given to Inspector–3Days.
Topics as per minimum requirement level as
defined in QF-204 skill evaluation criteria will
be taught during induction training.
3 Plant Head QF-204, QF-205B
B. Skill evaluation will be done on the next
working day of induction completion.
FOR STAFF
4 Induction period will be 1 days Plant Head QF-206
PREPARED BY :- APPROVED BY :-
Page 04 of 04
EDUCATION AND
APEX ENGINEERS TRAINING
DOC. NO.: AQSP-29
REV NO : 01
REV DATE:10.06.2021
g) OPERATOR OBSERVANCE
Production Engineer/ Supervisor will make Production
1 operator Observance Plan for all operators at a Engineer/ QF-21
Frequency of 3 months. Supervisor
2 Operator Observance Test will be done by the Production
Production Engineer/ Supervisor through Engineer/ QF-18
PREPARED BY :- APPROVED BY :-
Page 03 of 04
APEX ENGINEERS EDUCATION DOC. NO.: AQSP-29
REV NO : 01
AND TRAINING REV DATE:10.06.2021
h) POISON TEST
Poison`s test plan shall be made for all the
1 QA Head
visual inspectors on monthly basis. QF-189
Poison test shall be done through Poison test
2 QA Head
sheet QF-190
Passing Criterion for Poison Test is 100 %
3 QA Head
QF-190
If any abnormality is found during observation
then re training will be provided to the
4 concerned inspector within 3 days and poison QA Head QF-190
test will be conducted again
PREPARED BY :- APPROVED BY :-