OFFICE MS PROJECT

ID Task Task Name Duration Start Finish Predecessors Resource Names Weight factor % Plan % Actual WBS
Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022
Mode % (Text2) Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
1 Office Building 197 days Tue 07/01/20 Mon 14/12/20 0 0 0 RS*
2 Foundation 67 days Tue 07/01/20 Thu 30/04/20 0 0 0 RS*.1
3 Begin Construction 0 days Tue 07/01/20 Tue 07/01/20 0 0 0 RS*.1.1 07/01
4 Site Preparation 20 days Tue 07/01/20 Fri 07/02/20 3SS Excavator;Pipe[100 M1];Fence[10 M2] 0 0 0 RS*.1.2 Excavator;Pipe[100 M1];Fence[10 M2]
5 Excavation 10 days Tue 04/02/20 Wed 19/02/20 4 Excavator 0 0 0 RS*.1.3 Excavator
6 Install Underground Water Line 10 days Tue 18/02/20 Wed 04/03/20 5 Plumber 0 0 0 RS*.1.4 Plumber

7 Install Underground Electrical 10 days Tue 18/02/20 Wed 04/03/20 5 Electrician;Painting Vendor 0 0 0 RS*.1.5 Electrician;Painting Vendor
Conduit
8 Form/Pour Concrete Footings 10 days Tue 03/03/20 Wed 18/03/20 6;7 Iron Worker;Laborer 0 0 0 RS*.1.6 Iron Worker;Laborer

9 Form/Pour Concrete Walls 10 days Tue 17/03/20 Wed 01/04/20 8 Iron Worker;Laborer 0 0 0 RS*.1.7 Iron Worker;Laborer
10 Form/Pour Concrete Slab 5 days Tue 31/03/20 Mon 06/04/20 9 Iron Worker;Laborer 0 0 0 RS*.1.8 Iron Worker;Laborer
11 Backfill and Compact Fills 2 days Tue 07/04/20 Wed 08/04/20 10 Excavator;Laborer;Bakhoe[1] 0 0 0 RS*.1.9 Excavator;Laborer;Bakhoe[1]
12 Structure 69 days Thu 09/04/20 Thu 06/08/20 0 0 0 RS*.2
13 Erect Structural Frame 20 days Thu 09/04/20 Wed 13/05/20 11 Hydrolic Crane[1];Iron Worker;Johan Wales 0 0 0 RS*.2.1 Hydrolic Crane[1];Iron Worker;Johan Wales

14 Floor Decking 14 days Thu 07/05/20 Fri 29/05/20 13 Hydrolic Crane[1];Iron Worker;Johan Wales 0 0 0 RS*.2.2 Hydrolic Crane[1];Iron Worker;Johan Wales

15 Form/Pour Basement Slab and 25 days Wed 27/05/20 Wed 08/07/20 14 Iron Worker;Laborer 0 0 0 RS*.2.3 Iron Worker;Laborer
Floors
16 Erect Stairwall and Elevator 10 days Wed 01/07/20 Thu 16/07/20 15 Carpenter;Iron Worker;Laborer 0 0 0 RS*.2.4 Carpenter;Iron Worker;Laborer
Walls
17 Install Interior Wall Frame 15 days Wed 27/05/20 Fri 19/06/20 15SS Carpenter 0 0 0 RS*.2.5 Carpenter
18 M/E System 50 days Tue 07/01/20 Wed 01/04/20 0 0 0 RS*.3
19 Plumbing & Electrical 45 days Wed 27/05/20 Wed 12/08/20 0 0 0 RS*.3.1
20 Set Mechanical and 15 days Wed 27/05/20 Fri 19/06/20 15SS Nicholas Doe;Plumber;Electrician 0 0 0 RS*.3.1.1 Nicholas Doe;Plumber;Electrician
Electrical Equipment
21 Rough-in 15 days Wed 17/06/20 Fri 10/07/20 17;20 Electrician;Plumber 0 0 0 RS*.3.1.2 Electrician;Plumber
Plumbing/Electrical/Mechanical
22 Install Wiring and Cable 15 days Wed 08/07/20 Fri 31/07/20 21 Electrician 0 0 0 RS*.3.1.3 Electrician
23 Elevator 15 days Wed 15/07/20 Fri 07/08/20 0 0 0 RS*.3.2
24 Install Elevator Rails and 10 days Wed 15/07/20 Thu 30/07/20 16 Elevator Vendor 0 0 0 RS*.3.2.1 Elevator Vendor
Equipment
25 Install Elevator Cabinet and 5 days Wed 29/07/20 Tue 04/08/20 22;24 Elevator Vendor 0 0 0 RS*.3.2.2 Elevator Vendor
Finishes
26 Exterior 38 days Tue 07/01/20 Wed 11/03/20 0 0 0 RS*.4
27 Brick Exterior Walls 28 days Wed 17/06/20 Mon 03/08/20 17 Carpenter;Mason 0 0 0 RS*.4.1 Carpenter;Mason
28 Install Exterior Doors and 10 days Wed 17/06/20 Thu 02/07/20 27SS Carpenter 0 0 0 RS*.4.2 Carpenter
Windows
29 Insulation and Built-up Roofing 10 days Mon 27/07/20 Wed 12/08/20 27;28 Laborer;Rooler 0 0 0 RS*.4.3 Laborer;Rooler

30 Interior 38 days Tue 07/01/20 Wed 11/03/20 0 0 0 RS*.5


31 Walls 35 days Tue 07/01/20 Thu 05/03/20 0 0 0 RS*.5.1
32 Drywall in Office 15 days Mon 10/08/20 Thu 03/09/20 25;29 Carpenter 0 0 0 RS*.5.1.1 Carpenter
33 Paint Building Interior 20 days Mon 31/08/20 Fri 02/10/20 32 Painting Vendor 0 0 0 RS*.5.1.2 Painting Vendor
34 Fixtures 3 days Tue 07/01/20 Thu 09/01/20 0 0 0 RS*.5.2
35 Install Plumbing Fixtures 2 days Mon 28/09/20 Tue 29/09/20 33 Plumber 0 0 0 RS*.5.2.1 Plumber
36 Install Lightning Fixtures 3 days Mon 28/09/20 Thu 01/10/20 33 Electrician 0 0 0 RS*.5.2.2 Electrician
37 Floors 7 days Tue 07/01/20 Thu 16/01/20 0 0 0 RS*.5.3
38 Install Carpenting 5 days Mon 31/08/20 Mon 07/09/20 32 Floor Layer 0 0 0 RS*.5.3.1 Floor Layer
39 Install Floor Finishes 7 days Mon 31/08/20 Thu 10/09/20 32 Floor Layer 0 0 0 RS*.5.3.2 Floor Layer
40 Punch List 5 days Thu 01/10/20 Thu 08/10/20 0 0 0 RS*.6
41 Punch List/Touchup and 5 days Thu 01/10/20 Thu 08/10/20 33;35;36;38;39 Carpenter;Electrician;Laborer;Painting 0 0 0 RS*.6.1 Carpenter;Electrician;Laborer;Painting Vendor;Plumber
Cleanup Vendor;Plumber
42 Complete Construction 0 days Thu 08/10/20 Thu 08/10/20 41 0 0 0 RS*.6.2 08/10

Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: Rio Saputra_4TA01
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Tue 30/11/21
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress