Ain Shams Engineering Journal 12 (2021) 1153–1162

Contents lists available at ScienceDirect

Ain Shams Engineering Journal


journal homepage: www.sciencedirect.com

Architectural Engineering

A study of lean construction and visual management tools through


cluster analysis
Subhav Singh ⇑, Kaushal Kumar
Department of Civil Engineering, K R Mangalam University, Gurgaon, India
Department of Mechanical Engineering, K R Mangalam University, Gurgaon, India

a r t i c l e i n f o a b s t r a c t

Article history: There are various Lean tools available to increase the value of construction projects, this paper mainly
Received 18 January 2020 talks about the Visual Management tools that help in improving the efficiency and value of the construc-
Revised 1 April 2020 tion project. The methodology adopted for the study is to collect the data using structured survey on the
Accepted 19 April 2020
usefulness and importance of 12 lean tool and techniques identified from the literature review. A five
Available online 18 July 2020
point likert scale have been used for collection of data from pan India basis. A total of 153 valid response
were received and analysed using Excel spread sheets and SPSS 23 software. Reliability analysis, relative
Keywords:
importance index, cluster analysis were performed on the data collected. The findings of the study con-
Lean construction
Visual management
cludes that the most significant and important lean tool and techniques were Big rooms, 5S, LPS, and BIM
Construction management having a RII value of 92%, 91%, 90%, and 88% respectively.
Project management Ó 2020 The Authors. Published by Elsevier B.V. on behalf of Faculty of Engineering, Ain Shams University.
This is an open access article under the CC BY-NC-ND license (http://creativecommons.org/licenses/by-nc-
nd/4.0/).

1. Introduction Transportation Waiting [5] (see Figs. 1–7 and Tables 1–5).

The term Lean Construction is developed after the ground-


1.1. Visual management
breaking success of Lean concepts in the manufacturing industry
implemented by Toyota [1]. Lean Principles came into play after
The Construction industry is the much-fragmented industry
understanding the demerits/drawbacks of craft & mass production
where a large number of stakeholders are involved in every single
[2]. Lean Principles is all about reducing waste (Muda) and maxi-
project. The bad thing about this is not all the stakeholders travel
mizing the value [3]. The value mentioned here is the relation
together through the entire project, every contractor has their
between time, cost, quality and function [4]. To achieve this, the
own specialization and they will contribute their role towards that
perception of clients should be understood at the initial stage,
and leave the work to his following contractor. Hence a proper
which is mainly supported by 14 principles [5] and various Lean
communication and relation are not maintained among the
Tools. Talking about wastes, there are seven types of wastes identi-
involved stakeholders in the project, which ultimately leads to
fied, which acts as a hindrance for the successful completion of the
the decrease in value of the project [5]. The main moto of Visual
project. The identified wastes are
Management is to enhance the extensive flow of information
Rework
within the workplace and removing the barriers in the flow of
Inventory
information [6,7].
Over Production
In order to increase the value, these wastes should be identified
Processing Over Motion
and eliminated in the workplace. One of the effective tools for elim-
inating these wastes is Visual Management. Visual Management is
⇑ Corresponding author. a Lean Tool that makes important information visible to all. It
E-mail address: er.subhav@hotmail.com (S. Singh). shows the information through visual signals instead of texts,
which makes easier to understand for every stakeholder involved
in the project. The design should be displayed in an emphasized
manner so that it can be quickly grasped and communicated among
the stakeholders, in order to increase the efficiency, value, and clar-
Production and hosting by Elsevier
ity [8–10].

https://doi.org/10.1016/j.asej.2020.04.019
2090-4479/Ó 2020 The Authors. Published by Elsevier B.V. on behalf of Faculty of Engineering, Ain Shams University.
This is an open access article under the CC BY-NC-ND license (http://creativecommons.org/licenses/by-nc-nd/4.0/).
1154 S. Singh, K. Kumar / Ain Shams Engineering Journal 12 (2021) 1153–1162

Years
60

50

40

30

20

10

0
25-30 years old 31-40 years old 41-50 years old 51-60 years old Above 60 years

Fig. 3. Age demography analysis of the respondents.

Fig. 1. Sample project performance chart.


English, so that any information displayed through the help of lan-
guages might not reach out everyone, in addition to this the time
taken by an individual in reading the information and understand-
Visual Management increases, ing them will be more, and we can’t assure that they had under-
stood the correct meaning that the management is trying to
I. Communication convey through the displayed information. In order to overcome
II. Transparency these issues, Visual Management is practised in the workplace,
III. Self-management Capabilities of the stakeholders [5,11]. which helps to grasp the information in a faster and effective man-
ner [17–20].
The Visual Management helps one to know about 5W & 1H Visual management makes the organization more transparent
(Who, What, When, Where, Why & How) within 5 min of examin- [10,11,21] by making the information available to every stake-
ing the visual workplace. Visual Management Boards are kept in the holder involved in the project. Through visual management, all
heart of the workplace, with all the relevant data in an updated the information that every stakeholder required to know is dis-
manner. Every day in the workplace, work starts with a 15- played so that it helps in increasing the self-management, as one
minute meeting with the help of Visual Management Board, where can go through the displayed information and understand the situ-
responsible employees are required to update the Visual Manage- ation in an effective manner. Visual management also increases the
ment Boards before the start of the meeting, so that in meeting they team coordination, as daily meetings were conducted including the
can decide what are the deliverables, constraints, demands etc., of necessary stakeholders so that everyone can raise their own
the project [12–16]. demand to increase the value of the project and an effective solu-
Another reason for practising Visual Management is everyone in tion can be drawn with the help of those meetings, it also helps
the workplace may not be familiar with a common language like in increasing the relation/understandings among the involved
stakeholders. Visual management helps in maintaining better pro-
mises as a proper monitor is been kept on the schedule and neces-
sary timely steps are taken in order to prevent all possible risks and
delays associated with the project. The control for the management
is also made easier through visual management, as because the
workplace is very well organized with the help of visual manage-
ment tools. The workplace environment can be improved through
the help of visual management [10,11,21–23].
There are many Visual Management Tools available and some of
them are,

Numbers
70

60

50

40

30

20

10

0
North India South India East India West India

Fig. 2. Sample big room organizational chart. Fig. 4. Project location of the respondents.
S. Singh, K. Kumar / Ain Shams Engineering Journal 12 (2021) 1153–1162 1155

Years
45
40
35
30
25
20
15
10
5
0
0-5 years 6-10 years 11-15 years 16-20 years 21-25 years Above 25
years

Fig. 5. Years of experience of the respondents.

Fig. 7. Cluster size.

1.1.1. Standard signs with specific colors (display boards)


Fig. 6. Model summary.
These are signboards with a combination of standard signs along
with specific colour. Some of the types of signboards are as follows,
Table 1.1 Sample Components and Purpose of Display Boards.

1.1.2. Colour coding


Standard Signs with Specific Colors (Display Boards) Colour
It is a reliable and efficient way to organize different items pre-
Coding
sent in the workplace and visually locate them if something is being
Visual Display of Data in the form of Graph 5S
misplaced, few examples are,
Augmented Construction Field Visualization BIM
Collaborative Process Mapping/LPS End Product Sampling
(1) Colour Coding for Pipes (Different colours for different pipes
Heijunka
based on their function, example Water pipes can be coded
Big Room
with blue colour)
(2) Coloured Sticky Notes or Colored Magnets are used in Visual
Signalling (Andon)
Management Boards like production boards in order to mon-
itor, track, notify and update the process and project status. A
Response Guiding (Kanban)
sample format is described below:
Mistake Proofing (Poka-yoke) [4]

Table 1
Sample components and purpose of display boards.

Purpose Sign Shape Colour


Communicating an Order Circle a. Red & Black on White (Prohibition) b. White on Black (Mandatory) Example:
a. Don’t Cross
b. Wear Helmet
Communicating a Warning Triangle a. Black on Yellow (Caution) b. White on Red Example:
(Danger) a. High Voltage Electricity
b. Danger for Life
Communicating an Information Rectangle a. White on Blue b. White on Green Example:
(General Information) (Emergency) a. Process Description
b. Fire Exit
1156 S. Singh, K. Kumar / Ain Shams Engineering Journal 12 (2021) 1153–1162

Table 2 Sort
Color coding.

< one week One – four weeks > one month Set in Order
Red Color Tag High Priority Shine
Yellow Color Tag Medium Priority Standardize
Green Color Tag Less Priority or Completed Sustain [30]

1.1.5. Augmented construction field visualization


Augmented Construction Field Visualization is all about project-
ing a 3D model of the proposed design of the upcoming structure
Table 3 with all functions in the proposed site with the help of a mobile
Type and purpose of graph and chart. device, virtual reality, etc., With the help of Augmented Construc-
Type Purpose
tion Field Visualization contractors can emphasize on the project
progress, method of execution to achieve the desired output. The
Line Chart To represent the nature of data over a period of time
Column Chart To compare the data in order to identify the performance
contractors can also motivate their employees and labours by dis-
playing the virtual prototype of the proposed structure which is
going to be stable in the future. So, the stakeholders will get a clear
picture of the structure which is going to be constructed. If any
changes are supposed to made by the client on seeing the output
Table 4
of Augmented Construction Field Visualization, it’s easy to make
Reliability analysis.
in this stage as not much manpower, the cost will occur in this
Cronbach’s alpha value No of attributes No of samples stage when compared to the execution stage [30–32].
0.869 12 153

1.1.6. BIM
BIM is a 3D model which helps Architecture, Engineering, Con-
(3) The successor can pull the information from the predecessor struction (AEC) professionals to plan, design and construct on a
by viewing the updated Visual Management Board. This common platform and manage them effectively. For example, a
makes the entire workplace more transparent thereby elim- software called Navisworks can take output from various software’s
inating the chances of delay in conveying of information and like Revit, MEP consultants etc. and feed them in a common plat-
moreover any of the stakeholders can understand the situa- form where quantification can be done, clash detection can be done
tion that is prevailing in the workplace by examining the which helps in sorting the errors in a design stage through effective
Visual Management Board for 5 min [24,25]. design, which ultimately results in increasing the value of the pro-
ject [33–35].

1.1.3. Visual display of data in the form of graph 1.1.7. Collaborative process mapping/LPS
Representing information’s in the form of numbers will be very Last Planner System is a holistic system, that involves the plan-
vague, it makes difficult for everyone to understand the data repre- ning team to prepare a plan for the work that needs to be per-
sented. Hence these data should be represented in the form of formed in the fore coming weeks. It has five major parts namely
graphs for a better and quick understanding [26,27]. Some forms
of graphs with their functions are listed below: Master Planning
Phase Planning
1.1.4. 5S Make Ready Planning
5S is a workplace organization technique, used for organizing Weekly Work
and setting up the quality of the workplace. It is a tool for cleaning, Planning Learning
sorting and arranging the workplace. 5S helps in improving effi-
ciency by eliminating waste [28,29]. 5S was initially developed in The planning team should be ready with the above-mentioned
Japan means plan/schedule so that the possible hindrances can be identified,

Table 5
RII value.

Sr. No. Sum of the scores Number of responses RII value Lean tools/technique
1 707 153 92% Big Rooms
2 693 153 91% 5S
3 689 153 90% LPS
4 671 153 88% BIM
5 659 153 86% Display Boards
6 651 153 85% Augmented Construction Field Visualization
7 648 153 85% Poka-Yoke / Mistake Proofing
8 641 153 84% Color Coding
9 632 153 83% Kanban cards
10 576 153 75% End Product Sampling
11 557 153 73% Andon
12 553 153 72% Heijunka
S. Singh, K. Kumar / Ain Shams Engineering Journal 12 (2021) 1153–1162 1157

and proper mitigation measure can be taken in order to perform the possible variations, abnormalities, wastes etc., thereby enhancing
work seamlessly thereby increasing the value of the project. The the efficiency of the project [41].
LPS is also called as Pull Planning. There are various factors which can improve the efficiency of the
construction project. There are around 15 factors listed [42,41,4]. As
1.1.8. Heijunka there are plenty of Visual Management Tools available in the Lean
Heijunka helps in reducing overproduction, it helps in producing house, the factors listed are clubbed under 9 groups because each
according to the customer needs, which helps in the reduction of tool has a specific purpose to perform. The groups are namely,
inventories and facilities. This helps in increasing the value of the Administration
project. Heijunka can be done with the help of LPS as the quantity
of inventory required is been determined with the help LPS and Work Environment
that much inventory can be procured and stored in the facility if Culture
required. Heijunka also promotes the Just in Time procurement Human Resource
practice, which helps in reducing the facility space for storing the Compliance
inventories. This also reduces the risk of damages in the inventory Management
when stored in the facility [36,37]. Planning

Rework
1.1.9. Big room
The big room is an important lean tool were all the information
Transparency
regarding the project is displayed with the help of display boards,
colour coding, LPS, everything is displayed there. Hurdle meetings
[4].
take place in the big room which is a 15-minute standup meeting,
These factors can be enhanced with the help of Visual Manage-
where construction professionals come and discuss the problems,
ment. The success of Visual Management completely depends on to
schedule, cost etc., which they are facing in the site with the help
what depth the stakeholders understanding interaction with Visual
of the various visual tools displayed in the big room. The big room
Management tools. Visual management helps in increasing the
helps to a greater extent in improving the efficiency of the project.
transparency of the workplace, it also helps in enhancing the self-
The big room is made available to all the respective stakeholders
management by making the information available to all stake-
and all the information about the project, LPS, status, the progress
holder involved in the project. the visual management also
of the project etc., every detail is made visible, so that the organiza-
increases the plan percentage complete as it helps in working in
tion becomes more transparent and risks can be avoided, resulting
accordance with the commitments made by the organization
in increasing the value of the project [36–38].
[17,29,31,42,43].
The control for the management is made easier and also the
1.1.9.1. Andon. Andon is a visual aid which helps in throwing light workplace conditions were also improved as because of proper
on areas where action to be taken. If any flaw is identified in a con- alignment through the application of visual management tools [10].
struction process the work should be stopped and proper attention Visual management helps in increasing the transparency, disci-
should be given there so as to encounter the issue. This is done with pline, job facilitation, continuous improvement of the project, orga-
the help of caution lights in the place which is turned on when a nization, and its workplace [11]. it also helps in improving the
flaw is encountered. So that proper action can be taken by the organizational performance by aligning & combining the organiza-
responsible or authorized person in order to stop further progres- tional mission, vision, values, objectives etc. with the necessary
sion of the flaw and to mitigate the flaw [33,34]. stakeholders, the process of work, work environment, etc. [11].
Visual management helps in maintaining the consistency among
1.1.10. Poka-Yoke all levels of the project, which helps in preparing an effective look-
Poka-Yoke is also called a mistake-proofing. It helps in reducing ahead plan with underpinning the risks associated with them and
the mistake at the origin, rather than taking a mitigation plan after also the respective mitigation plan for those risks [23]. Unlike the
encountering the risk. This helps in reducing the cost, time and manufacturing industry, the construction industry is much frag-
resources which is been incorporated to mitigate the risk. In other mented and the number of stakeholders, clients involved in every
words, poka-yoke is making sure that all attributes which are project is considerably very large. Moreover, all the contractors
required to start a process are readily available and a proper miti- won’t travel together in all the stages of the project. every contrac-
gation plan to mitigate if any risk arouses during the process. It tor has their own specialization and they perform their task and
helps in preventing errors that are supposed to happen in a process leave the next to their successors. Hence it’s very difficult to estab-
[30,33,35]. lish proper communication and relation between them which ulti-
mately leads to the decrease in the value of the project
[13,17,43,44]. hence in order to enhance the communication and
2. Literature review
make the respective stakeholders about the situation prevailing in
the site every information is made visible to the stakeholders,
Visual Management is a Lean Tool which mainly helps in
thereby making the organization more transparent [22].
improving the efficiency of the construction if utilized effectively.
Communication is one of the main hindrances for improving the
value of the project, which can be improved through Visual Man-
agement and its tools. Visual Management helps in the seamless 3. Research methodology
flow of communication between all stakeholders by displaying
the necessary information in display boards. Other than communi- The research methodology adopted for this study has used both
cation, operation and process can also be controlled in real-time a quantitative and qualitative approach. The qualitative approach is
with the help of Visual Management [1,23,30,33,35,39,40]. VM also done through personal interviews with selected professionals and
increases the project transparency, which eliminates almost all employees, whereas the quantitative approach is done through reli-
1158 S. Singh, K. Kumar / Ain Shams Engineering Journal 12 (2021) 1153–1162
S. Singh, K. Kumar / Ain Shams Engineering Journal 12 (2021) 1153–1162 1159

ability analysis, RII (relative importance index), and cluster analysis The introductory part, the main questionnaire using all the
[45,46,4]. A typical flowchart of the research method is as follows, attributed identified from the literature review, and lastly the feed-
back section about the questionnaire and the study.
The respondents were requested to provide their responses
Questionnaire Survey about the applicability of Visual management tools on the horizon-
tal side and the factors were listed on the vertical side of the excel
spreadsheets of the questionnaire. on the basis of a Likert scale
3.1. Questionnaire survey process ranging from 1 to 5, where
1 – Not Applicable
2- Less Applicable
3- Applicable
4- Highly Applicable
5 – Most Applicable

3.2.1. Sample size


The structured questionnaire survey has been shared with 725
people associated directly and indirectly with the Indian construc-
tion industry. The population selected for the study is the mix of
professionals working with contractors, developers, PMC’s, inde-
pendent consultants, government bodies, and academic profession-
als working in the same field. A total of 153 complete and valid
forms were received with a response rate of 21%.

4. Data analysis and results

The data from the collected questionnaire were extracted and


analyzed with the help of Microsoft Excel. Comparing the value
increasing factors and the listed tools from the received data, the
following result is drawn.

4.1. Reliability analysis

Years of experience of the respondents

4.2. Relative importance index (RII)

RII is one of the best tools to analysed and prioritise the set of
attributes on the basis of their weighted average values. RII is very
much useful in defining the attributes and giving them the value on
the basis of the Likert scale values given by the respondents. RII
have been used in project management and construction manage-
ment by a number of researcher and it is highly reliable to predict
the most important attributes from a list of attributes [47–53].

4.2.1. The most significant lean tool/techniques


The most significant lean tool and techniques based on the RII
value were Big rooms, 5S, and LPS having a RII value of 92%, 91%,
and 90% respectively.

4.2.2. The significant lean tool and techniques


The significant lean tool and techniques based on the RII value
were BIM, Display boards, and Augmented Construction Field Visu-
alization having a RII value of 88%, 86%, and 85% respectively.

4.2.3. The least significant lean tool and techniques


The significant lean tool and techniques based on the RII value
were Poka-Yoke / Mistake Proofing, Color Coding, Kanban cards,
End Product Sampling, Andon, and Heijunka having a RII value of
85%, 84%, 83%, 75%, 73%, and 72%respectively.
3.2. Questionnaire format
4.3. Two-step cluster analysis
For this study a structured questionnaire survey used and the
data is collected using both modes of data collection i.e. Online sur- Cluster analysis have been used for the current study because of
vey and on-site data collection using the hard copy of question- its benefits to partition the data on the basis of explorer tree anal-
naires. The questionnaire mainly divided into three parts: ysis within the data. This technique used on a group of data set
1160 S. Singh, K. Kumar / Ain Shams Engineering Journal 12 (2021) 1153–1162

Fig. 8. Predictor importance.

which is closely inherent and homogeneous with other attributes of proposed 6 clusters. The cluster quality is fair refer the model sum-
the group. For this study the cluster analysis has been performed mary figure).
using SPSS 23.
Out of 12 attributes the first six as attributes has been selected
4.3.2. Cluster sizes
on the basis of their a value and two step class train within the
The two step clustereing proposed 6 clusters. The size of the lar-
groups has been performed [54–58].
gest cluster is 32.9%, and the smallest cluster is 3.9%.

4.3.1. Model summary cluster analysis 4.3.3. Predictor importance


The model summary of cluster analysis is having six input vari- The predictor importance is clearly demonstrate the importance
ables (highest ranked attributes on the basis of RII value), and it of BIM and shows that it is having a value of 1, followed by Aug-

Fig. 9. Cluster sizes.


S. Singh, K. Kumar / Ain Shams Engineering Journal 12 (2021) 1153–1162 1161

mented Construction Field Visulaization, and 5S. Fig. 8 predictor will contribute a lot to the construction industry in the future, as
importance contractors are nowadays becoming aware of visual management
and its role in increasing the value of the project.
4.3.4. Clusters on the basis of inputs The most common visual management tool used in the Indian
Fig. 9 cluster sizes construction industry is 5S, Display Boards, Color Coding, Kanban
Cards, and Big Room. The Big room itself consists of other tools like
Display Boards, Color Coding Kanban Cards. Heijunka is the lesser-
5. Conclusion known tool among the available visual management tools, which
will contribute more to the increasing value of the project if uti-
The application of visual management is gaining its presence in lized/implemented properly.
the construction industry due to its value increasing the potential The findings of the RII validate the fact that the use of BIM is not
of the project. but still many of the sites lack visual management that much popular among the construction industry professional as
due to lack of knowledge about visual management, they were a Lean toll, on the other hand the finding of cluster analysis tells us
not aware of the pros of visual management and its role in increas- that importance of BIM over all other tools and techniques. In the
ing value to the project and benefiting the organization. Through predictor importance it shows the highest impact on all other Lean
visual management we can achieve a barricade less communication tools with a predictor value of approx. 1.
i.e. one-piece flow (flow of information between the respective 5.1. Recommendations
stakeholders without any break or hurdles), the transparency of
the organization will be increased as there is no blockage in the Use of Heijunka visual management tool can be encouraged, it
information sharing, the information grasping capacity of the helps in increasing the value of the project by reducing the inven-
stakeholders is increased as all the necessary data of the project tories and facilities.
is made visible to all the stakeholders in the project so that they Big Rooms is always equipped with other visual management
can examine the displayed data in display boards and understand tools like display boards, colour coding, LPS, Kanban cards etc.
the situation, and act accordingly. Work becomes easier with the Motivational factors for employees like identification of best-
help of visual management because the entire workplace remains performed employees and displaying their achievement in the dis-
organized with the application of visual management tools and play boards and making them visible among other employees
the workplace to remains clean and tidy. The studies on visual which encourage others to perform well.
management are found to be lesser-known topics that would con- Proper training of every stakeholder about the available visual
tribute to the lean community if pursued. Hence I conclude by say- management tools and making them aware of their functions and
ing that visual management helps a lot in enhancing the value outcomes on their application.
increasing factors of the construction sites. There are plenty of lean
visual management tools available in the industry, each having
their own characteristics like 5S is used for organizing the work-
Appendix A
place, BIM for a 3D view of the entire plan, etc. Visual management
1162 S. Singh, K. Kumar / Ain Shams Engineering Journal 12 (2021) 1153–1162

References [35] da C T, Milberg C, Walsh KD. Exploring lean construction practice, research, and
education. Eng Constr Archit Manage 19(5); 2012:512–525..
[36] Brioso X. Teaching lean construction: pontifical catholic university of peru
[1] Salem O, Zimmer E. Application of lean manufacturing. Lean Constr. J. 2005;2
training course in lean project & construction management. Procedia Eng
(October):51–4.
2015;123:85–93.
[2] Howell G. What is Lean Construction. In: 7th Proc Int Gr Lean Constr. no. July, p.
[37] Gosling J, Naim M, Fearne A, Fowler N. Defining the lean and agile
104, 1999..
characteristics of engineer-to-order construction projects 2007:1(July)..
[3] Toyota. TPS - The Toyota Production System,” no. January; 2013..
[38] Howell GA. What is lean construction. Proc Seventh Annu Conf Int Gr Lean
[4] Patel VV, Karia N, Pandit D. Identifying value enhancing factors and
Constr 1999:1–10.
applicability of visual; 2018. p. 282–293..
[39] de Carvalho ACV, Granja AD, da Silva VG. A systematic literature review on
[5] Liker JK. The 14 Principles of the Toyota Way : An Executive Summary. 14 Princ
integrative lean and sustainability synergies over a building’s lifecycle. Sustain
Toyota W. An Exec. Summ; 2003.p. 35–41..
2017;9(7)..
[6] Meiling J, Backlund F, Johnsson H. Managing for continuous improvement in off
[40] Ogunbiyi O, Goulding JS, Oladapo A. An empirical study of the impact of lean
site construction. Eng Constr Archit Manage 2012;19(2):141–58.
construction techniques on sustainable construction in the UK. Constr Innov
[7] Aziz RF, Hafez SM. Applying lean thinking in construction and performance
2014;14(1):88–107.
improvement. Alexandria Eng. J. 2013;52(4):679–95.
[41] Mostafa S, Chileshe N, Abdelhamid T. Lean and agile integration within offsite
[8] Ballard G, Tommelein I, Koskela L, Howell G. Lean construction tools and
construction using discrete event simulation. Constr Innov 2016;16
techniques. Des. Constr. - Build. value; 2002. p. 504..
(4):483–525.
[9] Jamil AHA, Fathi MS. The integration of lean construction and sustainable
[42] Tomilo M et al. Renal Pre-Competitive Consortium (RPC2): discovering
construction: a stakeholder perspective in analyzing sustainable lean
therapeutic targets together. Drug Discov Today 2018;23(10):1695–9.
construction strategies in Malaysia. Procedia Comput. Sci. 2016;100:634–43.
[43] Dixit S, Mandal SN, Sawhney A, Singh S. Area of linkage between lean
[10] Tezel A, Aziz Z. Benefits of visual management in construction: Cases from the
construction and sustainability in Indian construction industry. Int J Civ Eng
transportation sector in England 2017; 17(2)..
Technol 2017;8(8):623–36.
[11] Tezel A, Koskela LL, Tzortzopoulos P. Visual management in construction: study
[44] Kenley R. Productivity improvement in the construction process. Constr
report on Brazilian cases. SCRI Res. Rep., no. March; 2010. p. 36..
Manage Econ 2014;32(6):489–94.
[12] Engineers Australia WA Division. Recommended Practices for the Application
[45] Martens ML, Carvalho MM. Key factors of sustainability in project management
of LEAN Construction Methods to Building New Australian LNG Capacity. Eng
context: a survey exploring the project managers’ perspective. Int J Proj
Aust 2012..
Manage 2017;35(6):1084–102.
[13] Jørgensen B, Emmitt S. Lost in transition: the transfer of lean manufacturing to
[46] Built T, Review HE. Evaluating research methodology in construction
construction. Eng Constr Archit Manage 2008;15(4):383–98.
productivity studies. Built Hum Environ Rev 2010;3(1):63–85.
[14] Bernstein H, Jones S. Lean construction - Leveraging collaboration and
[47] Kothari C. Research methodology: methods and techniques; 2004..
advanced practices to increase project efficiency 2010;3(2)..
[48] Shah MN, Dixit S, Kumar R, Jain R, Anand K. Causes of delays in slum
[15] Dixit S, Sharma K, Singh S. Identifying and analysing key factors associated with
reconstruction projects in India. Int J Constr Manage 2019:1–16.
risks in construction projects. Emerg Trends Civ Eng 2020:25–32.
[49] Dixit S, Mandal SN, Thanikal JV, Saurabh K. Evolution of studies in construction
[16] Dixit S, Sharma K. An empirical study of major factors affecting productivity of
productivity: a systematic literature review (2006–2017). Ain Shams Eng J
construction projects. Emerg Trends Civ Eng 2020:121–9.
2019;10(3):555–564.
[17] Khodeir LM, Othman R. Examining the interaction between lean and
[50] S. Dixit, S. N. Mandal, J. V Thanikal, and K. Saurabh, ‘‘Construction Productivity
sustainability principles in the management process of AEC industry. Ain
and Construction Project Performance in Indian Construction Projects,” vol. m,
Shams Eng J 2016;9(4):1627–34.
no. July, 379–386, 2018..
[18] Björnfot A, Sardén Y. Prefabrication a lean strategy for value generation in
[51] Dixit S, Mandal SN, Thanikal JV, Saurabh K. Critical analysis of factors affecting
construction. Proc 14th Int Gr Lean Constr 2006;265–277..
the on-site productivity in Indian construction industry 2018;38–45..
[19] Al Sudairi AA. Evaluating the effect of construction process characteristics to
[52] Dixit S, Pandey AK, Mandal SN, Bansal S. A study of enabling factors affecting
the applicability of lean principles. Constr Innov 2007;7(1):99–121.
construction productivity: Indian scnerio. Int J Civ Eng Technol 2017;8(6)..
[20] Koskela L, Ballard G, Howell G, Tommelein I. The foundations of lean
[53] Dixit S, Saurabh K. Impact of construction productivity attributes over
construction. Des Constr Build Value 2015:211–226..
construction project performance in Indian construction projects. Period
[21] Tezel BA, Koskela LJ, Tzortzopoulos P. The functions of visual management. Int
Polytech Archit 2019.
Res Symp 2009:201–219..
[54] Dixit S. Analysing enabling factors affecting the on-site productivity in Indian
[22] Murata K, Tezel A, Koskela L, Tzortzopoulos P. Sources of waste on construction
construction industry. Period Polytech Archit 2018;49(2):185–93.
site : a comparison to the; 2018:973–981..
[55] Wilks DS. Cluster analysis. Int Geophys 2011;100:603–16.
[23] Brady DA, Tzortzopoulos P, Rooke J, Formoso CT, Tezel A. Improving
[56] Cui X, St Charles J, Potok T. GPU enhanced parallel computing for large scale
transparency in construction management: a visual planning and control
data clustering. Futur Gener Comput Syst 2013;29(7):1736–41.
model. Eng Constr Archit Manage 2018;25(10):1277–97.
[57] Wang L et al. Energy-aware parallel task scheduling in a cluster. Futur. Gener.
[24] Marhani MA, Jaapar A, Bari NAA. Lean construction: towards enhancing..
Comput. Syst. 2013;29(7):1661–70.
[25] Sustainable Construction in Malaysia. Procedia Soc Behav Sci 2012;68:87–98..
[58] Wu X, Benjamin Zhan F, Zhang K, Deng Q. Application of a two-step cluster
[26] Zhang L, Chen X. Role of lean tools in supporting knowledge creation and
analysis and the Apriori algorithm to classify the deformation states of two
performance in lean construction. Procedia Eng. 2016;145:1267–74.
typical colluvial landslides in the Three Gorges, China. Environ Earth Sci.
[27] Ansah RH, Sorooshian S. Effect of lean tools to control external environment
2016;75(2):1–16.
risks of construction projects. Sustain Cities Soc 2017;32(December
2016):348–356..
[28] Dixit S, Mandal SN, Sawhney A, Singh S. Area of linkage between lean
construction and sustainability in indian construction industry. Int J Civ Eng Subhav Singh is currently working with K R Mangalam
Technol 2017;8(8).. University. He is an active researcher in the field of
[29] Dunlop P, Smith SD. Planning, estimation and productivity in the lean concrete Construction, Civil works, Lean construction, and Sus-
pour. Eng Constr Archit Manage 2004;11(1):55–64. tainable construction. He has published more than 10
[30] Issa UH. Implementation of lean construction techniques for minimizing the
articles in different journals.
risks effect on project construction time. Alexandria Eng J 2013;52(4):697–704.
[31] Sowards D. Applying the 5S ’ s for Lean Construction. Qual Support Serv. Inc.;
2012. p. 127..
[32] Salvatierra Garrido J, Pasquire C. Value theory in lean construction. J Financ
Manage Prop Constr 2011;16(1):8–18.
[33] Loganathan S, Kalidindi S. Masonry Labor Construction Productivity Variation :
an Indian Case2015;1–9..
[34] Sweis GJ, Hiyassat M, Al-Hroub FF. Assessing lean conformance by first-grade
contractors in the Jordanian construction industry. Constr Innov 2016;16
(4):446–59.