CONTRACT NO# 1018743- /New IPS 1489173rev6 # TRS-35-001 FOR THE SALE OF
POWER GENERATION EQUIPMENT signed on 23rd December, 2020.
www.ge.com GE hereby informs Customer regarding the following Inspections of the equipment
GT Serial Number#850305.
Test / Inspection: Dynamic Balancing
Date of Inspection: 19th November, 2021
Starting: 9:00 a.m.
Duration: One (1) day
GE Energy Product France SNC
Loge de Garde 47 (rue de la Découverte)
Meeting Point
90007 Belfort - France
Please take into account the following recommendations for your visit to the factory area :
= Safety glasses with side shields (provided by your GE contact or at your disposal at the factory
entrance doors) to be worn in the workshop / test bench
= Workshop circulation : floor marking (yellow marked aisle ways) is to be respected
= Cameras / phones : photography is forbidden ; cameras or camera phones are not allowed within
the manufacturing / test facilities. As far as possible, cell phones should be turned off, especially in
the test bench.
= If the inspection results do not comply with GE specifications, the inspection may be rescheduled
for the following day
= The date of notification is tentative according to current manufacturing schedule and subject to
change
We are taking additional EHS measures due to the COVID 19 situation for any external visit. Can
you please confirm :
= Have you personally been to any of the COVID 19 affected zones in the past 14 days (China, South
Korea, North Italy, etc….) ?
= Have you been in contact with someone who has travelled to any of the COVID 19 affected zones
in the past 14 days ?
= Do not present any symptoms: fever, sickness or others ?
Yours Sincerely,
Philippe Mégnin
Senior Project Manager