Professional Documents
Culture Documents
BY:
MOLLA YIMER
ADVISOR:
MAY 2020
Signature____________________________
Date_______________________________
ADVISOR‘S APPROVAL SHEET
As thesis research advisor, I hereby certify that I have read and evaluated this thesis prepared
under my guidance by Molla Yimer entitled ―THE EFFECT OF PROJECT MANAGEMENT
PRACTICE ON PROJECT SUCCESS: A CASE STUDY ON ETHIO-TELECOM‘S ERICSON
CIRCLE (SR, SWR AND SER) MOBILE NETWORK TELECOM EXPANSION PROJECT‖.
I would also like to thank Ethio Telelcom specially employees and the managers who have been
working on Ericsson Circle (SR, SWR and SER) ethio telecom mobile network expansion
Project for their willingness to participate in the study. Last but not my least, special admiration
goes to my family, especially to my wife Alemnesh Tesfaye and children for their care, support
and encouragement as well as, for their tolerance every time I sacrifice my family time for the
project study.
i
Table of Contents
Contents Page
ACKNOWLEDGEMENTS ............................................................................................................. i
Abstract .......................................................................................................................................... ix
INTRODUCTION .......................................................................................................................... 1
2. Introduction .......................................................................................................................... 9
ii
2.3.1 What is Project Management? ...................................................................................... 10
2.6.1 The effect of Project management Knowledge area related practices on project success
............................................................................................................................................... 28
iii
DATA ANALYSIS, INTERPRETATION AND DISCUSSION ................................................ 37
4.2.1 The Relationship between project management practice and SR, SER and SWR project
success. .................................................................................................................................. 52
4.2.2 Relationships between Scope management practice and Project success ................ 53
4.2.3 Relationships between Human resource management practice and Project success.... 54
4.2.4 Relationships between communication management practice and Project success ..... 55
4.2.4 Relationships between stakeholder management practice and Project success ........... 55
4.2.5 Relationships between project planning practice and Project success ......................... 55
iv
4.2.6 Relationships between External factors and Project success ........................................ 56
5.2 Conclusion........................................................................................................................... 69
References: .................................................................................................................................... 74
ANEX I ......................................................................................................................................... 80
v
List of Tables
Table 2.1 Literature review matrix: Most cited PM practices by researchers .............................. 16
Table 4.10 Correlations between project management practices and project success .................. 54
vi
Figures
vii
ACRONYMS AND ABBREVIATIONS
ET............................... Ethio-Telecom
ETC………………… Ethiopian Telecommunication Corporation
GTP………………… Growth and Transformation Program
HLD………………… High Level Design
HR……………………Human Resource
ICT………………….. Information Communication Technology
LLD…………………. Low Level Design
PMBOK………………Project Management body of knowledge
PM……………………Project Management
PMI…………………...Project Management Institute
PMO…………………. Project Management Office
PRO…………………. Project Roll Out
SR……………………. Southern Region
SWR…………………. South Western Region
SER…………………. South Eastern Region
TEP…………………. Telecom Expansion Program
WBS………………… Work Breakdown Structure
ZTE………………….. Zhongxing Telecommunication Equipment
viii
Abstract
The purpose of this study is to assess the project management practices of ethio telecom SR,
SWR&SER mobile network expansion project and their effect on project success. Descriptive
and explanatory design were applied to address the specific objectives of the study and reach at
specific conclusion. Data was gathered using the questionnaire from 107 respondents directly
participated in the project. To have high validity, no sampling technique was used as the whole
target population was considered for the study. Besides, using semi-structured interview
questions, qualitative data was also collected from purposefully selected 3 project managers and
1 program manager. The findings of the study revealed that, PM knowledge area and project
planning practices were moderately practiced except the following observed problems: full
scope of the project was not understood from the very start, training, reward and recognition
were not properly practiced, Stakeholders were not managed well. Project planning was not
practiced well, there was lack of incorporating the view of all stakeholders, lack of allocating
sufficient time for project design, project schedule was not properly determined and the planned
project end date was not realistic, project risk was not identified, analyzed and risk response
plan was not properly developed at the planning stage. Concerning external factors vendor
performance in delivering materials on time and with the right quality was not satisfactory and
vendor project team members lacks commitment to accomplish the project on time. Results from
correlation analysis shows, there is significant positive correlation between the PM knowledge
area practices, project planning and project success but no significant correlation between
external factors and project success. Result from multiple linear regression shows, except
planning the PM knowledge areas and external factors not significantly explain the project
success. Based on these finding, the study recommends: ethio telecom should have to develop an
accurate and efficient project planning before project execution as well as the project scope
should be clearly defined from the very start, better to have a culture of developing appropriate
risk management and lesson learned documentation to prevent unexpected risks and failures in
the future projects.
---------------------------------------------------------------------------------------------------
ix
CHAPTER ONE
INTRODUCTION
1.1 Background of the study
The PMBOK® defines project management related concepts and provides guidelines and best
practices for managing individual projects. The PMBOK® further publishes the generally
recognized standard for project management, which describes the established norms, methods,
processes, and practices, as developed and evolved over time by practitioners, and considered to
be good practices for most projects most of the time. Good practice means that there is general
agreement that the tools, skills, processes, techniques and application of knowledge presented
can significantly improve project success. This does not denote that this knowledge can be
uniformly applied to all projects; the organization and project team must determine which
techniques are appropriate for each given situation using this guidance (PMI, 2013).
The use of project management practices is one of the most essential factors that affect project
success. Empirical research has shown that very often even the basic approach to project
management in organizations is not ideal and it is difficult for senior management to
acknowledge and accept this notion (Alsulamy, Gupta, and Sloan, 2014). The concept of project
management practices being formalized is based on the principal assumption that the use of
commonly accepted project management practices will enhance and improve project outcome
(Papke-Shields, Beise, and Quan, 2010).
The application of project management in the Telecommunication industry has evolved in the
last few decades. Project management is embraced in the industry to proactively manage
telecommunication projects such that expected outcomes (products or services), will fulfill the
purpose upon which they are embarked upon. Several organizations in the industry do face
challenges as they implement these projects even with secure procedures and practices to ensure
success. However, more efforts have been made in identifying and applying procedures,
practices, standards, structures and methodologies towards achieving success in ICT project
implementation management in the Telecommunication industry. (Ogunberu, 2018).
1
Ethio Telecom, previously known as the Ethiopian Telecommunications Corporation (ETC), is
an integrated telecommunications services provider in Ethiopia, providing internet, mobile
communications and telephony services. To improve the service quality and network coverage
Ethio-telecom launched a 1.6 billion USD worth Telecom Expansion Program (TEP) this clearly
shows the commitment of the government and the company towards the development of the
sector. (GTP Report, 2012/13). According to the TEP-Charter (2014), there are several
responsibilities assigned to the governance bodies. The critical success factors summarized in the
charter are: full support from the government, full support of Executive Management Board
(EMB), empowered program managers, qualified and sufficient resources, commitment of the
program management team, appropriate incentives to drive need behavior to deliver the expected
milestones, standard process, quick decision making, resource availability, proper change
management and escalation procedures, realistic schedule and communication at all levels to
create ownership.
While the above critical success factor stated in the TEP charter, the project undertaken by
Ericson failed to meet time cost and Quality Targets in addition to not being compatible with the
existing Ethio telecom network. Therefore, assessing ethio telecom‘s project management
practice effect for the successful accomplishment of the mobile telecom expansion project is
important. Thus, this research shades lights on the below main questions: -
How project management practice is being applied in SR, SWR and SER mobile network
expansion project
What is the effect of project management practices on the project success?
What challenges were faced during project implementation?
2
proclamation No. 131/52 in 1952. The Board had full financial and administrative autonomy and
was in charge of the provision and expansion of telecommunications services in Ethiopia.
After the end of the IP-NGN project, in year 2013, the government planned and executed a
Telecom Expansion Project (TEP) with an investment amount of 1.6 Billion USD. The Telecom
Expansion project was executed in the second half of the first 5 years Growth and
Transformation Plan (GTP I). As of June 2015, the country has achieved high subscription levels
by raising the number of mobile subscribers to 40 Million, and Internet users to 10 Million.
3
The TEP has resulted in Mobile service penetration of 44%, and Internet penetration has also
reached 11%. The Country‘s 85% of geographic area has coverage of mobile service. If only
inhabitable areas are taken, this can be considered as 100% coverage (Wubshet, 2017).
The mobile network coverage consists of 3G and 2G services, and 4G LTE technology
deployment in the capital Addis Ababa. The government has also been working towards
enhancing its international internet gateway capacity/bandwidth through international fiber optic
links via neighboring countries Djibouti, Kenya and Sudan. The current international bandwidth
capacity stands at 27.3 Gbps (Wubshet, 2017).
In 2014, Ethio telecom launched telecom infrastructure expansion project with Ericson being the
main vendor. Ericsson company initially had agreed with Ethio telecom on the four circle of the
company‘s project namely SSWR, SR, SWR and SER of the company. As per the agreement,
Ericsson was supposed to provide Ethio Telecom with its 2G/3G mobile communication related
products and services such as planning, tuning, designing, optimization and deployment for all of
the circles with agreed completion time to be in December 2016. However, as per the
researcher‘s direct observation, due to underperformance of Ericson, one of the circle-SSWR
was given to another Company called Huawei. In addition, Ericson failed to deliver the project
4
on the agreed time and delivered majority of its project targets lately in July 2019. As the local
newspaper called ‗‘the reporter‘‘ reported in 2018, the project undertaken by Ericsson was not
completed as per the time and quality requirements specified on the contact agreement due to
this network quality problem observed specially around towns of Adama, Jimma and Nekemte.
Furthermore, as per the preliminary interview the researcher had with a project manager who has
been directly involved, the project carried out by ET with Ericson company was started before
HLD, site survey and LLD design preparation, Project completion time was decided before
conducting site survey, scope of the project was also not defined properly and there was project
team competency and commitment related problems. This indicates that the presence of project
management practice related gaps. Related studies conducted on Ethio telecom TEP project
implementation also revealed that the presence of gap in Planning, monitoring & Leadership of
projects (Woldemariam, 2019). Nigussie (2018) also found that scope monitoring and control
process was poorly practiced, there was no formal time management process, activity duration
estimation and periodic update of project schedule were poorly practiced. Concerning External
factors, vendors‘ performance, weather condition, geographical topography of the project sites,
regional government bureaucracy, dependency on other organizations and local contractors were
the main external factors challenging project on time implementation (Mideksa, 2017).
What is more is that project management practices of ET, Ericson circle project have not been
studied thoroughly due to confidentially kept project performance data. Plus, there is very
limited available document in the company that clearly indicates studies conducted or lesson
learned in project implementation, in addition, as far as the researcher knowledge the effect of
project management practices and external factors has not been deeply studied taking the case of
ET, Ericson circle. In order to implement huge projects like Telecom expansion program (TEP)
successfully and to meet the functional aim of the projects within their lifetime, an efficient
project management practice and knowing the specific problem of the project undertaking or
conducted is an important for an organization, because the effective implementation of project
management practices and use of the processes, tools and templates of project management
increases the chance of success of a project. Therefore, organizations undertaking projects need
to assess their project management practice. (Crisan, 2010). Thus, it is the researcher‘s intention
to analyze the effect of ET‘s project management practices on the success of SR, SWR and SER
5
(Ericson‘s Circle) mobile network expansion project and to point out best project management
practices that ensure project success.
The study attempted to find answers for the below major research questions:
1. What is the effect of project Management knowledge area practices on project success?
2. What is the effect of project planning practices on project success?
3. What are the effects of external factors on the project success?
The main objective of this research is to identify the effects of ethio telecom‘s project
management practices on the success of SR, SWR and SER TEP mobile network expansion
projects.
To analyze the effect of Project management knowledge area practice on the project
success.
To analyze the level of project planning practice effect on the project success.
Launching and implementing multimillion dollar investment projects require ethio telecom to
deal with highly complex and challenging project issues which may demand advanced project
management practice, knowledge and skills so as to provide scientific and contextually to proved
solutions for problems in each steps of the project. Therefore, this study will help ethio telecom:-
To take a lesson and to improve project management practice gaps on ongoing or future
project and it will help for the company to not repeat similar mistakes.
It will serve as a good input for the companies to know and document best practices of
the project management so as to use in the future projects by making some adjustments.
6
Furthermore, researchers will use this research out comes as a base to investigate more
about country level project management practices in Ethiopia.
No doubt that the research already gave great experience for the student researcher
regarding research methodology and future problem solving activities.
In terms of concept the scope is limited to the study of project management practices (the
Independent Variable-Scope, HR, Communication, stakeholder, project planning and external
factors) and their effect on SR, SER and SWR TEP Phase 1, mobile network expansion Project
success (Independent variable - schedule, budget, project goals and objectives and team
satisfaction).In terms of time scope, the study deals with a 5-year period (2014-2019) to assess
the effects of project management practices on project success. Of course, respondents were
asked, at current point of time, to share their experience considering the 5-year period. Since the
staffs who participated on Ericson‘s circle project were working centrally at Addis Ababa,
geographically, the research study is limited to Addis Ababa, specifically, at Ethio-Telecom‘s
Central Microwave station (Tikur Anbessa area).
Project Management: Project management is the application of knowledge, skills, tools, and
techniques to project activities to meet the project requirements. Project management is
accomplished through the appropriate application and integration of the project management
processes identified for the project.
Practices: Generally accepted management and administrative activities and decisions from the
starting to the ending of a project. They are factors that are practiced in project implementation
and influence project success or failure if not properly managed. Practices may include
techniques, tools, methods, or approaches used effectively to arrive at the desired outcome
7
(Menon, 2015). Accordingly, a best practice is a technique, method, or process that is believed to
be more efficient and effective in achieving a goal than any other techniques, methods and
processes, when applied to a particular condition or circumstance (Ilies, et al., 2010).
Project success: is defined by the level of efficiency the project achieved to reach the project
objectives.
Project Management Plan – The document that describes how the project will be executed,
monitored, and controlled.
Project Planning – The process of thinking through and making explicit the objectives, goals,
and strategies necessary to bring the project through its life-cycle to a successful termination
when the project‘s product, service, or process takes its rightful place in the execution of project
owner strategies (Cleland & Ireland, 2006).
8
CHAPTER TWO
LITERATURE REVIEW
2. Introduction
This chapter presents the theoretical and empirical literatures, and concepts related with the topic
of the study. This literature review part is to provide a summary of previous related studies and
various literatures on the research problem areas. The bodies of literature are discussed based on
the specific nature of the relevant literatures that relates to this study and the available literature
is aimed to review the major concept and research problem related with this research topic.
Projects are temporary, but their deliverables may exist beyond the end of the project. Projects
may produce deliverables of a social, economic, material, or environmental nature. For example,
a project to build a national monument will create a deliverable expected to last for centuries.
(PMBOK, 2017). Thus, in general, the definitions of project emphasize the characteristics of
projects as unique in nature, having a defined timeframe and approved budget.
9
deadline from senior management within which the project is expected to be completed. Budget
or cost constraint limits the project‘s ability to utilize funds on the project. It has a potential of
restricting the project scope. Scope elements define the deliverables and the boundary within
which the project will be implemented. Quality constraints are restricted by the specifications of
the product or service and also the expected standards required. Resource constraint deals with
availability of resources (both internally to the project team and externally to other supports
required for project execution) for project execution in terms of required skills, quantity,
experience and so on (Heldman, 2009).
Projects are a key way to create value and benefits in organizations. In today‘s business
environment, organizational leaders need to be able to manage with tighter budgets, shorter
timelines, scarcity of resources, and rapidly changing technology. The business environment is
dynamic with an accelerating rate of change. To remain competitive in the world economy,
companies are embracing project management to consistently deliver business value (PMI,
2017).
Project management is the application of knowledge, skills, tools, and techniques to project
activities to meet the project requirements (PMI, 2017). It involves planning, organizing,
directing, and controlling of company resources for a relatively short-term objective that has
been established to complete specific goals and objectives (Kerzner, 2009). According to Robert
K.Wysocki (2014) project management is designed to answer what business situation is being
addressed, what does the business need to do, what will you do, how will you do it, how will you
know you did it and how well did you do. Project management is an organized common-sense
approach that utilizes the appropriate client involvement in order to meet sponsor needs and
deliver expected incremental business value. It encompasses many different skills, such as
understanding the interdependencies among people, technologies, budgets, and expectations;
planning the project to maximize productivity; motivating others to execute the plan; analyzing
the actual results; and reworking and tuning the plan to deal with the realities of what really
happens as the project is executed (Howes , 2001).
10
2.3.2 The importance of project management
Effective project management helps individuals, groups, and public and private organizations to:
Poorly managed projects or the absence of project management may result in:
Missed deadlines, cost overruns, rework, uncontrolled expansion of the project, loss of
reputation for the organization, unsatisfied stakeholders and failure in achieving the
objectives for which the project was undertaken (PMBOK, 2017).
11
team-working skills, rather than rigid functional divisions. In summary, key factors to consider
as project management elements in ICT projects include; people, process and technology
(Ogunberu, A.O., Akintelu, S.O. and Olaposi, T.O. 2018). The people are to be developed,
managed and improved upon so that they can effectively manage the processes and activities
involved in implementing telecommunication projects. The project manager must understand the
roles and participation of the people on the project including stakeholders and beneficiaries.
Their expectations and general psyche must be well managed through efficient stakeholders‘
analysis and documentation. This will help, a great deal, in ultimately meeting up with their
expectations since they are the ultimate consumer of the product, result or service of the project.
A well designed procedure and strict adherence to this procure helps the project team to
effectively manage ICT projects including Telecommunication projects. Following such laid-
down approved procedures usually help to discover potentialities and enhance capabilities or
competencies of project team members. Process re-engineering are crucial to the implementation
of ICT projects in order to eliminate redundancies and improve upon the way projects are
implemented (United Nations, 2010). This is achieved through the implementation of project
management in projects execution by telecommunication firms.
According to Ogunberu et.al (2016) Project management is quite essential for a more efficient
telecommunication project implementation and service delivery process that minimizes the risks
of cost overruns, schedule slippages, quality improvement and increases the chances of success.
The use of proper project management is rapidly becoming a requirement in many
telecommunications oriented companies and environments. Use of Project Management tools
and techniques can make the difference between meeting or not meeting project scope, budgetary
and time requirements. Meeting these constraints is becoming more and more critical and the
competition escalates, and companies compete for shares of the market. Sometimes an even
more significant problem is the customer satisfaction which is closely related to producing what
the customer wants, within the required cost and time. Or more accurately, producing what the
customer really wants (Avison and Torkzadeh, 2009).
12
2.4 Project Management success and Project Success
Project success is undoubtedly one of the most popular issues that has been particularly
prominent in academic and business research over the past decades. The notion of what
properties constitute a successful project has been much discussed in the project management
field without being able to highlight a commonly acceptable definition until nowadays (Pinto &
Slevin, 1988a; Baccarini, 1999; Müller & Judgev, 2012). From a scientific point of view,
significant differentiations and deviations between the various considerations and approaches can
be distinguished in respect with the ways that success can practically be attributed to a project.
Project success should be interpreted based on the perspectives of the different stakeholders
(owner, contractor, project manager, client, user, community), as a result a project could be
regarded a success for some parties and a failure for others respectively.
De Wit (1988) considers that a distinction should be made between the project management
success and project success in attempt to properly evaluate success. These are two concepts that
are closely related, but they can show significant differences. Project management success is
determined based on fundamental success criteria/restrictions, while project success refers to the
overall accomplishment of the goals and objective of a project. It is noted that ―good project
management can contribute towards project success but is unlikely to prevent project failure‖
(De Wit, 1988). According to Munns and Bjeirmi (1996), the relationship between project
success and project management success is less dependent than originally believed, as these
notions should be clearly separated so as to assess project success. Both concepts concentrate on
the successful execution of a project, but they reflect completely different objectives and
character. For example, there are projects that were not completed within the predetermined
restrictions (poor project management) and tend to be great successes over time and vice versa
(Munns and Bjeirmi, 1996). On the contrary, Baccarini (1999) distinguishes project success in
two aspects: project management success (focusing on project process and predetermined
restrictions) and product success (focusing on the effects of project outcomes). Complementary,
Lim and Mohamed (1999) suggest two perspectives of analyzing project success, justifying to a
certain extent the usual differences between the various perceptions. Specifically, the macro
viewpoint is related to the implementation degree of the overall plan of a project in the
operational stage and the micro viewpoint refers to the achievement route on the individual
13
levels and components of a project at the completion of the execution stage respectively.
Summarizing, an overlap between project success and project management success can be
detected, but the latter is essentially a subset of the overall success of a project (Munns and
Bjeirmi, 1996).
Furthermore, it is widely accepted that project success consists of two fundamental components,
namely project success criteria and project success factors. Project success criteria are the
dependent variables (principles, measures, standards) that measure and evaluate the successful
outcome of a project, while project success factors are the independent elements of a project (set
of circumstances, facts, elements, and influences) that can increase the likelihood of success. In
other words, success criteria are used to measure success whilst success factors facilitate the
achievement of success respectively (Lim and Mohamed, 1999; Ika, 2009; Turner, 2009; Müller
and Judgev, 2012).
Generally, Time - schedule, cost - budget, user satisfaction, quality-performance, business and
commercial performance are the most frequently used success criteria, followed by technical
specifications and requirements, stakeholders‘ satisfaction, strategic goals/objectives and
competitiveness, functionality, project team satisfaction and safety. Some researchers also refer
to contractor satisfaction, future perspective and environmental impact, while handful are those
that support that effectiveness and suppliers‘ satisfaction can influence project success
(Lamproua, et.al 2018).
The critical factors influencing the success of projects are identified and commonly related
to the following areas:
Project: clear goal, realistic schedule, adequate funds, resources, size and complexity of
a project,
Project management practices: integration, scope, time, cost, quality, human resources,
communication, risk, procurement and stakeholder management
Project manager and leadership: leadership, management of changes, effective conflict
resolution, communication,
Project team members: communication, technical background, qualified team,
Organization: top management support, responsibility and authority chart,
14
External environment: client, technological environment, political environment, social
environment, physical environment.
Based on the above literature, for the purpose of this study the researcher used five Major criteria
to measure the project success
1. Time: The project was successfully completed within the expected time
2. Budget: The project was successfully completed with the planned budget
3. Goals and Objectives: The project successfully met the expected goals and objectives
4. Quality: The quality standard of the project maintained
5. Project team satisfaction
Fraz et.al (2016) by reviewing different literatures they found that among PM practices, project
scope management, project HR management, project communications management, project
stakeholder management and project planning are the most frequently cited PM practices by
researchers
15
Table 2.1 Literature review matrix: Most cited PM practices by researchers
Similarly, Chou and Yang (2012) in their research, found that not all the project management
body of knowledge (PMBoK®) techniques/tools/skills have significant effect on project
performance but performance does have mutual inter-correlations between some PMBoK®
practices. The results however can be limited and affected by the social, cultural and
technological changes in project management practices – they suggesting that it may be
necessary to; ―expand the scale of survey and even a cross-nation comparison‖. According to
Ramabadron et al., (1997) there is a relationship between PM practices and project performance.
Certain PM practices adopted do not necessarily have a significant satisfactory influence on
projects performance whilst some have. There would therefore be the need to promote optimum
practices and a second look taken at others that confront the success of building projects.
Zwikael (2009) ,In order to identify which of the nine knowledge areas have the greatest impact
on project success, used a model that includes the nine knowledge areas as independent variables
and project success as dependent variable which is measured by four variables of success (time,
cost, quality and customer satisfaction). Accordingly, Zwikael ranked the nine knowledge areas
based on their impact on project success as: time, risk, scope, human resource, integration,
quality, communication, cost and procurement from the highest to the lowest and also
summarized different rankings for different industries (construction & engineering, software,
production, communications, services and government).
16
Research indicates that despite the implementation of project management practices across
varying organizations and projects, projects continue to fail in meeting project objectives,
outcomes, and stakeholders‘ expectation (Raz and Michael, 2001). Although, past studies have
suggested that there is little evidence of the relationship between project management practices
and improved project success (Thomas and Mullaly, 2007; Besner and Hobbs, 2013). However,
the extent to which there could be variation in the use of the different project management
practices remains unclear.
More specifically, the questions of which practices within the formal project management
standards managers‘ do use in project implementation remains unresolved. Furthermore, there
are a limited number of studies that have surveyed PMs to examine the relationships between
project management techniques and project success (for example, Dvir, Raz, and Shenhar, 2002;
Besner and Hobbs, 2006; Papke-Shields, Beise, and Quan, 2010; Chou and Yang, 2012). Many
of these studies surveyed the organizations rather than PMs to conclude what practice affects
project success, which is inconclusive, and this area of project management research is under
studied with gaps in the literature.
There are many factors that affect project success such as project management practices
(integration, scope, time, cost, quality, human resources, communication, risk, procurement and
stakeholder management) and project size (number of employees in the project, project costs and
project duration). The PMBoK® guide is the universal standard for project management
published by the renowned Project Management Institute (PMI). According to Ilies, et al. (2010),
the Project Management Body of Knowledge (PMBOK) is a collection of processes and
knowledge areas generally accepted as best practice within the project management discipline.
The effective use of Project Management practices such as those included in PMBoK® can lead
to better project outputs as it contains standard practices, processes to follow, techniques and
tools to adopt, diverse knowledge and required methods for different business operations for
effective results (PMI, 2013).
According to PMI (2013) the PMBOK® structure includes five process groups, ten knowledge
areas, and 47 project management processes. The knowledge areas group the PM processes by
project management content. The 47 project management processes are grouped into five distinct
sets: PMBOK® (PMI, 2013) identifies the standard processes that should be performed by a
17
project manager. Of the 47 processes identified in the PMBOK®, 24 (51%) are planning
processes.
As indicated in PMI 2017 the main activity in the project integration management process groups
are Develop Project Charter, Develop Project Management Plan, Direct and Manage Project
Work, Manage Project Knowledge, Monitor and Control Project Work, Perform Integrated
Change Control, Close Project or Phase.
According to Chou (2012) & Kerzner (2017) Project integration management consists of all
processes and activities which identify and define as well as combining other activities related to
project management. In more detail, in the context of project management, project integration
management consists of the main characteristics of all consolidation, unification, communication
and integrative actions related to the implementation of projects, managing stakeholders in
successful ways and meeting the requirements of the project.
Project integration management also includes making decisions about choices of allocation of
resources, making trade-offs among competing objectives and alternatives and managing
interdependencies among all project management practice areas (ul Musawir, et al., 2017).
2. Project Scope Management
Project scope management is closely aligned with integrated change control and the project
manager needs to focus on what is needed to complete the project successfully (Pheng, 2017).
18
The project scope management process contains the procedures which confirm that project will
be completed as planned and intended if it is only comprises the required work (Al-Rubaiei, et
al., 2018). The PMI (2017) defined the processes of project scope management in the following
ways:
Plan Scope Management: The process of creating a scope management plan that documents
how the project and product scope will be defined, validated, and controlled.
Define Scope: The process of developing a detailed description of the project and product.
Create Work Breakdown Structure (WBS): The process of subdividing project deliverables
and project work into smaller, more manageable components.
Validate Scope: The process of formalizing acceptance of the completed project deliverables.
Control Scope: The process of monitoring the status of the project and product scope and
managing changes to the scope baseline
Project schedule management is the process of comparing actual schedule performance to the
baseline schedule to determine variances, evaluate possible alternatives, and take the appropriate
action (Richman, 2011). The ultimate measure being project success, based on effective control
of time management processes, tools and practices. The development and management of
realistic project schedule and project plan is a primary responsibility of the project manager to
complete the project on time. The project scheduling provides a detailed plan that represents how
and when the project will deliver the products, services, and results defined in the project scope
and serves as a tool for communication stakeholders‘ expectations, and as a basis for
performance reporting (PMI, 2017).
According to the PMBOK, the project schedule management includes the following process:
19
Planning schedule management: is the process of establishing the policies, procedures, and
documentation for planning, developing, managing, executing, and controlling the project
schedule.
Defining activities: is the process of identifying and documenting the specific actions to be
performed to produce the project deliverables.
Sequencing activities: is the process of identifying and documenting relationships among the
project activities.
Estimating activity duration: is the process of estimating the length of time or period needed to
complete individual activities with the estimated resources.
Controlling schedule: is the process of monitoring the status of the project to update the project
schedule and manage changes to the schedule baseline
Project cost management involves several stages such as planning, estimating, budgeting,
financing, funding, managing and controlling costs (Schwalbe, 2015). Therefore, the project can
be completed within the planned and approved budget. Project cost management emphases on
the process of creating policies, procedures and planning and documenting costs, expenditure
and controlling costs. Furthermore, cost management estimates costs through developing
approximation of monetary resources needed to complete the activities of the project. It also
determines the project budget through a process of aggregating the estimated costs of every
activity in the project which will establish an authorized a baseline for the project cost (Alotaib,
2019).
According to the PMI (2017) the project quality management includes the processes for
incorporating the organization‘s quality policy regarding planning, managing, and controlling
project and product quality requirements, in order to meet stakeholders‘ expectations. Project
20
quality management consists of all processes and activities related to performing organizational-
related quality policies, aims and objectives as well as responsibilities (Kerzner, 2017). In
general, project quality management focuses on the process of determining the requirements of
quality and standards for the projects being implemented as well as identifying deliverables and
documenting how the project comply with the quality requirements (Alotaib, 2019). As cited by
Atsbha (2019) from PMBOK this knowledge area consists
Plan Quality Management: The process of identifying quality requirements and/or standards
for the project and its deliverables, and documenting how the project will demonstrate
compliance with quality requirements and/ or standards.
Manage Quality: The process of translating the quality management plan into executable quality
activities that incorporate the organization‘s quality policies into the project.
Control Quality: The process of monitoring and recording the results of executing the quality
management activities to assess performance and ensure the project outputs are complete,
correct, and meet customer expectations.
21
7. Project Communication Management:
It describes the possible means by which an information can be sent or received, either through
communication activities, such as meetings and presentations, or artifacts, such as emails, social
media, project reports, or project documentation (PMI, 2017). Generating, collecting,
distributing, updating, and storing project-related data and documentation in a standardized
manner and ultimately disposing of project related information is important to achieve effective
information exchange (Sherif, 2006). There are 3 project communication processes in the PMI
(2017).
Monitoring communications: is the process of ensuring the information needs of the project
and its stakeholders are met.
Risk is an event or condition that disrupts the implementation of a project and reduces chances of
achieving schedule, cost, and quality objectives of projects if it is not mitigated timely. Every
project has its own risk and if not properly managed can result in a failure of the project. Risk
management is the process of identifying, analyzing, mitigating or responding and monitoring
risks in order to decrease its impact on project success. Many researches accepted risk as one of
the main factors influencing projects success (Karadsheh, et al., 2009; Eid, et al., 2015; Bhatia &
Kapoor, 2011; De Bakker, et al., 2010).
According to the PMI (2017), risk management includes the following processes:
Plan Risk Management: is the process of defining how to conduct project risk management
activities.
22
Identify Risk: is the process of identifying individual project risks and the sources of overall
project risk, and documenting their characteristics.
Risk Analysis: Risk analysis includes qualitative and quantitative methods. Qualitative risk
analysis is the process of prioritizing individual risks for further analysis or action by assessing
their source of uncertainty, their impact or other characteristics. Quantitative risk analysis is the
process of numerically analyzing each identified project risks or other sources of uncertainty on
the project objectives.
Plan Risk Response: is the process of developing options, selecting strategies, and agreeing on
actions to address or mitigation of overall risk exposure and uncertainty, treat individual project
risks.
Monitor Risks: Monitoring risk is the process of monitoring the implementation of agreed-upon
risk mitigation plans, tracking identified risks, identifying and analyzing new risks, evaluating
risk process effectiveness throughout the project.
Conduct Procurements: The process of obtaining seller responses, selecting a seller, and
awarding a contract.
Stakeholders are individuals, peoples and organizations related with the project who may affect
the project or be affected by the project. According to McElroy & Mills (2000), Stakeholders are
individuals or a group of individuals, who are influenced by or able to influence a project.
23
Project stakeholders may include top managements, project manager, resource manager, project
team, peers in the projects, customers, suppliers or vendors, contractors, government and so on.
Managing stakeholders is about identifying stakeholders, their interest level, and their influence
potential to the project; and managing and controlling the relationships and communications
between stakeholders and the project. In addition, McElroy & Mills (2000) indicated that the
purpose of stakeholder management is to achieve project success through the continuing
development of their interrelationships. Therefore, appropriate project stakeholder management
practices are important in project implementation success. The PMBOK (PMI, 2017) described
Project Stakeholder Management processes as follows:
Identify Stakeholders: The process of identifying project stakeholders regularly and analyzing
and documenting relevant information regarding their interests, involvement, interdependencies,
influence, and potential impact on project success.
24
Planning Process Group. Those processes required to establish the scope of the project,
refine the objectives, and define the course of action required to attain the objectives that
the project was undertaken to achieve.
Executing Process Group. Those processes performed to complete the work defined in
the project management plan to satisfy the project requirements.
Monitoring and Controlling Process Group. Those processes required to track, review,
and regulate the progress and performance of the project; identify any areas in which
changes to the plan are required; and initiate the corresponding changes.
Closing Process Group. Those processes performed to formally complete or close the
project, phase, or contract.
According to PMI (2017) the Planning Process Group consists of those processes that establish
the total scope of the effort, define and refine the objectives, and develop the course of action
required to attain those objectives. The processes in the Planning Process Group develop the
components of the project management plan and the project documents used to carry out the
project. The nature of a project may require the use of repeated feedback loops for additional
analysis. As more project information or characteristics are gathered and understood, additional
planning will likely be required. Significant changes that occur throughout the project life cycle
may initiate a need to revisit one or more of the planning processes and, possibly, one or both of
the Initiating processes. This ongoing refinement of the project management plan is called
progressive elaboration, indicating that planning and documentation are iterative or ongoing
activities. The key benefit of this Process Group is to define the course of action to successfully
complete the project or phase.
The project management team seeks input and encourages involvement from relevant
stakeholders while planning the project and developing the project management plan and project
documents. When the initial planning effort is completed, the approved version of the project
management plan is considered a baseline. Throughout the project, the Monitoring and
Controlling processes compare the project performance to the baselines.
25
Figure 1. Key Planning Process Group activities.
The goal of the planning phase of a project is to prepare the structure for project execution and
control. Planning is an important factor for project success (Cooper & Kleinschmidt, 1995;
Fortune & White, 2006; Zwikael, Shimizu, & Globerson, 2005) and as such is recognized as one
of the critical success factors of project management (Johnson et al., 2001; Pinto & Slevin, 1988;
Zwikael and Sadeh, 2007). However, some criticism of project planning practices can also be
found in the literature, especially as regards the ability to accurately estimate cost and schedule
during planning. For example, Flyvbjerg, Holm, and Buhl (2002) investigated 258 transportation
infrastructure projects, worth US$90 billion and representing different project types,
26
geographical regions, and historical periods. The authors found overwhelming statistical
significance that the cost estimates used to decide whether such projects should be builtare
highly and systematically misleading. They suggest that one should not trust cost estimates and
cost-benefit analyses produced by project promoters and their analysts. This can lead to high cost
overruns at the end of the project (e.g., Keil, Rai, Ellen, Mann,& Zhang, 2003). Bigelow (1998)
criticizes the importance of planning by quoting project managers who claim that planning takes
too much time and that customers do not know what they want.
Project planning involves specifying a set of decisions concerning the way in which project work
should be executed in the future. The primary purpose of planning is to establish a set of
directions in sufficient detail that the project team can be told what must be done, when it must
be done, and what resources to use in order to successfully produce project deliverables
(Meredith & Mantel, 2006). The major benefits from quality planning are: (1) to eliminate or
reduce uncertainty, (2) to improve efficiency of the operation, (3) to obtain a better
understanding of project objectives, and (4) to provide a basis for monitoring and controlling
work (Kerzner, 2006). A project manager is responsible for completing the project to the
satisfaction of all relevant stakeholders. Therefore, project managers should not only make
certain that their actions are executed according to plan, but more importantly, that the plan is
reliable and properly represents Stakeholders‘ requirements.
According to Kerzner (2009), most individuals recognize the quantitative tools for planning,
scheduling, and controlling work. It is essential that project managers comprehend completely
the operations of each department. The only way to minimize risk is for organizations to plan
better.
Yeo (1995) stated that in pre-project planning, the planning and learning process undertaken is
more important that the plans actually produced. Yeo (1995) noted that during the planning
process, participants and participating organizations are constructing mental models of the
complex economic, technological, social and political variables that will influence the project.
Although the project plan may continue to change and evolve, the knowledge gained through the
process of planning will allow improved teaming and decisions throughout the duration of the
project.
27
2.6 Empirical review
2.6.1 The effect of Project management Knowledge area related practices on project
success
Mukopi (2016), studied the factors that influence implementation of telecommunication network
equipment projects in the case of Safaricom Limited and he concluded that: scope management,
time management, cost management, procurement and communication managements are the
most critical success factor for the successful implementation of telecommunication network
equipment projects.
Zwikeal (2009) analyze the relative importance of knowledge areas by calculating the impact of
their related planning processes on project success. A knowledge area is important to project
success when the higher extent of use of its related processes significantly improves project
success. In the study first, the degree of use of each knowledge areas were calculated as an
average of its related planning processes. Then, a multivariate regression analysis was conducted
with all nine KAs as independent variables and four project success measures as the dependent
ones. He found that seven knowledge areas have a substantial impact on project success. This
means that the more frequently planning processes—which are related to these knowledge areas
—are performed, the better project success is. The knowledge areas that most contribute to
project success during planning are Time, Risk, Scope, Human Resources, and Integration. Cost
and Procurement are the knowledge areas that contribute least to project success, maybe because
they are practiced mainly during project execution.
This finding is aligned with the Pareto principle (or, ―20/80 Rule‖), which claims that 20% of all
possible causes impact 80% of the result (Craft & Leake, 2002). The project planning knowledge
areas that most influence project success results are Time, followed by Risk, Scope, and Human
Resources. The knowledge areas that have the lowest impact on project success are Cost and
Procurement. Although these results do not suggest that some KAs are not important, still a more
focused approach that prioritizes potential investment in different project management processes
is required.
Nigussie (2018) in her study ―Assessment of core Project constraints Management Practice: In
the Case Of Information System Project In ethio-Telecom‖ regard to project scope management
28
her finding implies that relevant stakeholders were involved in scoping process, and the presence
of formal process to prepare scope management plan are practiced properly while standardized
tool in the scope defining process, in preparing scope dictionary, and in scope monitoring and
control process were poorly practiced . Concerning project time management, the project has
approved time schedule. Even though there was worthless application of formal time
management process, use of WBS in scheduling, identified activities sequenced in the schedule,
estimated activity duration. Particularly the project found to be in poor practice on periodic
update of project schedule.
Wahid (2018) in his study about ethio telecom project management maturity level indicated that
―Project stakeholder management, project quality management, integration management and
scope management have maturity level greater than 2.2 and none of the ten project management
knowledge areas, nor any of their processes, is rated at a maturity level of 5. This shows that
especially Scope and Stakeholder knowledge areas are not well practiced in ethio telecom
Telecom expansion projects.
Belete (2019) studied about Stakeholder management practice in Ethio telecom and indicated
that ethio telecom fails to organize separate functional unit for managing stakeholder
relationship, conflict of interest, change of requirement, and there is lack of clear understanding
on stakeholder management processes.
Numerous researchers and studies have identified planning as a critical success factor to project
success (Fortune & White, 2006; Murphy, Baker, & Fisher, 1974; Pinto & Slevin, 1987). In an
empirical study of IT projects, Aladwani (2002b) found that project planning can significantly
influence the variation in the success of organizational IT projects. Conversely, failure to
document milestone deliverables and due dates in project plans (Kappelman et al., 2006), failure
to reconcile project schedule deadlines with project plans, and ignoring early project delays
without revision to the overall project schedule (McKeeman, 2001), were all found to be
significant contributors to IT project failure.
One experiment by Dvir, Raz, and Shenhar (2003) found that project success was not influenced
by the level of implementation of traditional project management processes and procedure.
29
However, they found that the development of both functional requirements and technical
specifications did result in improved project success. Saarinen (1990) found that IT projects that
have problems with requirements specification are more likely to fail than those that do not.
A study by Nebiyat belay (2017) on ―Examining the practice of ethiopian airline in planning and
scheduling of aircraft heavy maintenance projects‖ found that The imposition of the flight
operator on the planning and scheduling process due to downtime of aircrafts during
maintenance, the lack of benchmarks for work processes, lack of clear work description among
organization units, low involvement of the project manager in the planning and scheduling
process are the issues identified in the study.
Müller and Turner (2001) reported a correlation between post-contract planning (detailed
planning after a contract had been signed) and project schedule variance. They report that a
quality of post-contract planning that is at least good is required to meet schedule goals. As cited
by serrador (2013) Tausworthe (1980) also, notes the impact of the work breakdown structure
(WBS) as an important planning tool with demonstrated benefits on software project success.
MEDHIN HAFTOM (2019) studied Project management practice with especial focus in project
lifecycle and he found that TEP was good in practicing Initiation, planning, execution,
monitoring & control and closing phase activities but the project Lack identifying possible risks
and detail scope statement preparation at planning phase, lack of timely escalation of problems
impeding project team‘s performance to execute the project and regularly updating project
schedules at execution phase, lack of proper identification and documenting of lessons learned at
closing phase. Lack of proper coordination with stakeholders also one of the challenge for the
successful implementation of the project. According to the result from his multiple linear
regression analysis, except planning all the other project phase practices and challenges
significantly explain the project success.
Tadesse (2019) in his assessment on practice and challenges of project planning in commercial
bank of Ethiopia he found out that the major challenges that the Commercial Bank of Ethiopia
faces in the project planning process are lack of adequate and effective project time
management, lack of integration between projects, lack of experienced project managers, lack of
qualified and experienced project teams, lack of project management training, inefficient and
30
insufficient communication between project managers and team member and absence of
documenting lessons learned and best practices.
The conceptual framework specifies the crucial process, which is useful to show the direction of
the study. Mugenda (2008) defines conceptual framework as a concise description of
phenomenon under study accompanied by a graphical or visual depiction of the major variables
of the study. According to Young (2009), conceptual framework is a diagrammatical
representation that shows the relationship between dependent variable and independent variables.
By considering different literatures and studies the below will be used as a frame work for this
study.
Source: Adapted based on Fraz et.al (2016) and developed by the researcher based on
previous studies.
31
CHAPTER THREE
RESEACH METHODOLOGY
This chapter presents the research design, population and sampling, sources of data, data
Collection method and methods of data analysis. It will also describe the data processing and
data analysis methods.
32
established by the name TEP office which includes program director, program managers, project
managers, project coordinators and supervisors, and project professionals (TEP-Charter, 2013).
So, the target population for this study will be 150 Ethio Telecom employees in PRO and
Engineering department under network division, specifically TEP program Manager, project
managers, Supervisors, coordinators and Experts and staffs who participated on the project
implementation of SR, SWR and SER mobile network expansion project. PRO and Engineering
department are selected for this study because these teams are the one who have the overall
responsibility for the successful initiation, planning, design, execution, monitoring, controlling
and closure of mobile network expansion project of the Ethio telecom.
33
dealing with reliability test, Cronbach‘s alpha coefficient was made on each variable. Cronbach‘s
alpha reliability coefficient normally ranges between 0 and 1. The closer Cronbach‘s alpha
coefficient is to 0, the lesser the internal consistency of items in the scale and the closer to 1.0
Cronbach‘s alpha the greater the internal consistency of the items in the scale. Based on this, as
we can see from the SPSS result table 3.1, the Cronbach‘s alpha coefficient for each item was
tested and the result shows there is high internal consistency. Because based on George and
Mallery, (2003) rule of thumb, a Cronbach‟s alpha coefficient greater than 70% (.7) is good.
According to the Cronbach‘s Alpha values presented in table 3.1, the value of individual
variables ranges from minimum 0.713 to maximum value of 0. 875.Henece, the researcher
conclude that it has internal consistency and is reliable for further analysis.
―Validity refers to the extent to which a test measures what we actually wish to measure.
Validity is the most critical criterion and indicates the degree to which an instrument measures
what it is supposed to measure. Validity can also be thought of as utility. In other words, validity
34
is the extent to which differences found with a measuring instrument reflect true differences
among those being tested‖ (Kothari, 2004).
o The research questions, the conceptual framework, the data collection instruments and
questioners were aligned to make sure the study focus on what it expects to measure.
o Besides, both content and face validity of the questionnaire was investigated with the
support of experts in the area of Project management. The supervisor of the study, 2
classmates, 2 experts were asked to rephrase or edit any items found unclear,
inappropriate or irrelevant.
o To ensure high validity and generalizability, the study takes all the target population
using census
o The conceptual framework was adapted from the existing reviewed literature forwarded
by known researchers in the area of project management and modified a little bit to suite
the objectives of the study.
In order to assess the effect of independent variables on dependent variable multiple linear
regression is applied. The model applied to show this effect is presented as follows;
Where:
35
β0 = Intercept (value of Y when X= 0)
β1 = Slope
X5=External factors
ε = the error
36
CHAPTER FOUR
DATA ANALYSIS, INTERPRETATION AND DISCUSSION
This chapter deals with analysis, interpretation and discussion of the gathered data from Telecom
expansion project in ethio telecom SR, SER&SWR region through structured questionnaires and
key informants‘ interviews. The chapter organized in three main parts. The first part is concerned
with the demographic characteristics of respondents and the second part focused on analyzing,
interpreting and discussion of the collected data from close ended Questioner and interviews.
This Section summarizes the gender of respondent, age of respondent, work experience (service
years) in the organization, experience in TEP implementation, educational level and respondents
position (Level) in the organization. The main focus of this section is to show the proportion of
female and male respondents, their work experience in the company, their experience in
37
implementing TEP, educational level of employees in the projected. Based on this, we will see
all the demographic characteristics of the respondents one by one as below
38
4.2.1. Gender of the respondents.
As shown in the above Table 4.1, 78.5 present of the respondents were male and 21.5 percent
were female respondents. This may imply that the gender proportion of employees in the project
is not balanced.
39
4.2.6 Project Work Experience
Regarding to how long the respondents have been assigned and working in SR, SER and SEW
telecom expansion project, 94 (87.9 %) of the respondents have above 4 years‘ experience and 8
(7.5%) of the respondents have an experience of 2-4 years while 3(2.8 %) employees are having
experience between 6monthts- 2 years and 1.9 of them have below 6 months‘ work experience in
SR, SER and SEW telecom expansion project. This may imply that majority of the respondents
have adequate experience of implementing Telecom expansion project in this project circle and
have enough understanding to consider and value their response equally in this research.
(1=strongly disagree, 2=Disagree, 3=Neutral, 4=Agree, 5=strongly agree), and the analysis of the
mean score is based on the below assumptions from Robert Burns,(2008) the mean score has been
computed for each component of the variables and analysis is presented for each variables. The
average mean result together with their respective variables was separately presented analyzed
and interpreted,
o If the mean statistical value is between 0 to 1.5 it implies the respondents strongly
disagreed.
o If the mean statistical value is between 1.5 to 2.5 it implies the respondents disagreed.
o If the mean statistical value is between 2.5 to 3.5 it implies the respondents were
undecided or neutral.
o If the mean statistical value is between 3.5 to 4.5 it implies the respondents were agreed.
o If the mean statistical value is above 4.5, it implies that the respondents were strongly
agreed.
40
Consequently, Ericsson circle project participants were asked whether scope of the work was
identified at high level in the project lifecycle or not. The response collected on how the scope
management is practiced in the project is presented as follows and the Mean is interpreted based
on the above Robert Burns,(2008) assumption.
41
As illustrated in the above table, the practice of collecting, defining and understanding project
requirements were observed to a moderate extent as shown by mean value of 3.04 but with the
largest variation in responses received as indicated by the standard deviation of 1.088. in terms
of frequency, significant number of respondents (40.4%) clearly disagreed to the fact that ethio
telecom has implemented collected, defined and understood project requirements. similarly,
practices of project scope verification, project work breakdown, project scope control and project
scope change management were also observed to moderate extent as shown by mean value of
3.16, 3.59, 2.79 and 3.58, respectively. Among project scope management practices, project
scope control practice has the least mean value of 2.79 but still with large variability in response
as shown by standard deviation of 1.062.
Generally, the practices of scope management i.e. project requirement understanding, practices
of project scope verification, project work breakdown, project scope control and project scope
change management are observed to a moderate level, if not to great extent, as shown by mean
value of 3.23 but with great variability in response as shown by 0.988 standard deviation.
Clearly, moderate level of practice is not enough especially for today‘s complex and costly
projects.
42
Qualified and 3.44 1.020
sufficient human
resource have been
supplied for project
implementation. 5.6% 15.9% 14% 57.9% 6.5%
Project management 2.54 1.118
training was provided
for project team 19.6% 32.7% 25.2% 18.7% 3.7%
Project team 2.46 1.049
performance were
evaluated and best
performer recognized
and reward 19.6% 35.5% 26.2% 16.8% 1.9%
Average Mean Value 2.93 1.068
Table 4.3 discusses on human resource management practice on the project. From the frequency
table more respondents 48(44.9%) agreed that Staff Appointed for the project was based on
educational qualification and experience with the mean value 3.21. Regarding to Selection of
Managers/coordinators 39(36.4%) respondents agreed that the selection was based on integrity
and leadership quality while 30(28.0%) of the respondent was neutral which is the largest
respondent number next to agreed respondents with mean value 3.02. Project participants were
asked whether Qualified and sufficient human resource have been supplied for project
implementation or not and majority of the respondents 62(57.9%) were agreed with the mean
value 3.44. Similarly, respondents in this section were asked whether Project management
training was provided for project team and Project team performance were evaluated and best
performer recognized and reward and majority of the respondents were disagree and strongly
disagree with mean value 2.54 and 2.46 respectively. So from this finding we can understand that
project management training and reward and recognition were not practiced well in the project.
4.1.2 Project Communication Management
The response collected on how the project communication management practice in the project is
presented as follows: -
43
Table 4.4. Project communication management practice
Std. 1=SD 2=D 3=N 4=A 5=SA
Mea
Items Deviatio
n % % % % %
n
There was timely communication 19.60 26.20 33.60 11.2%
3.18 1.156 9.30%
of project information % % % )
44
Project stakeholder management practice
The response collected on how the project stakeholder practice in the project is presented as
follows: -
45
4.1.3 Level of project planning practice
In this sub section, respondents were asked to express their level of agreement on how the
presumed project planning practice were under taken in the SR, SWR and SER ethio telecom
mobile network telecom expansion project. The responses were rated from 1 (strongly disagree)
to 5 (strongly Agree) to all questions regarding project planning practice.
The response collected on how the level of project planning practiced in the project is presented
as follows: -
46
development
In this section, respondents were asked whether High level document that defines how the
project is to be executed, monitored and controlled and closed was prepared before the project
execution was prepared or not, Majority of the respondents 60(56.1%) with mean of 3.55 agreed
that High level document was prepared before the execution phase.
Most projects have multiple stakeholders with different views on the project‘s purpose and
different expectations of what the project must achieve (Lyytinen & Hirschheim, 1987). These
stakeholders might include the people who originally identified the need for the project, those
47
who fund the project, those who stand to benefit from the project, the people who are impacted
by the project and its outputs, the project team members, and the people who have to oversee the
project. Each has a vested interest in the project‘s outcome, with different expectations and
perceptions. Regarding to stakeholder management planning practice the respondents were asked
whether the view of all stakeholder incorporated in the planning phase or not, significant number
of respondents disagree with mean value 2.48. Majority of the respondents 63(58.9%) with mean
value 3.57 are agreed that the role of the stakeholders was identified during the planning stage.
Respondents were asked whether The project scope, Major Deliverables, assumption and
constants was well defined in the planning phase, significant number of respondents are not in
agreement with the idea and improvement is needed in this regard because well-defined project
scope will help as a reference for the project manager during project execution to perform the
required activities only and keep the project within quality, budget and schedule. Similarly,
respondents were asked to answer whether project planning activities are completed prior to
project execution and majority of them uncertain and have disagreement tendency this might
show that the detail plan (project site survey) of the project not completed before the project
execution.
Concerning Project schedule management planning the project participants were asked whether
Sufficient time is given for project design and quantity preparation/ development and majority of
the respondents 70% with mean value 2.16 are disagreed. Similarly, respondents were asked
whether Schedule of the project was appropriately determined, accordingly significant number of
respondents are uncertain and disagree. Majority of the respondents are uncertain and in
disagreement state about the project schedule is updated regularly and about the incorporation of
unplanned work as needed. Lastly under project schedule management planning part Majority of
the respondents 68% with mean value 2.04 agreed that the Planned project end date was not
realistic. From this finding generally project schedule management planning was not practiced
properly in SR, SER and SWR ethio telecom TEP.
Regarding project human resource planning practice the respondents were asking 3 questions to
state their agreement or disagreement whether project team members are motivated and
committed to participate in the planning process and project human resource management plan is
prepared during the planning phase and the majority do not agree with the statement or remain
48
neutral and this might show that there was a gap to engage project team during the planning
process and number of human resource for the project was not planned properly in accordance
with WBS.
Finally, under the level of project planning practice section the respondents were asked about
project risk management practice. Majority of the respondents are remaining uncertain and do
not agreed for the identification of project risk at the project planning stage with mean value
2.85. Similarly, majority of the respondents are uncertain whether project risk analysis is
conducted and quantified during the planning stage and the preparation of risk response planning
at the project planning stage with mean value 2.87 and 2.75 respectively.
Generally, the finding under the level of project planning practice shows that except project
integration management practice, Project scope planning, project schedule planning, human
resource planning and Risk planning were not practiced well. In an empirical study of IT
projects, Aladwani (2002b) found that project planning can significantly influence the variation
in the success of organizational IT projects. Conversely, failure to document milestone
deliverables and due dates in project plans (Kappelman et al., 2006), failure to reconcile project
schedule deadlines with project plans, and ignoring early project delays without revision to the
overall project schedule (McKeeman, 2001), were all found to be significant contributors to IT
project failure.
49
Table 4.7. External factors
1=SD 2=D 3=N 4=A 5=SA
Std.
Items Mean
Deviation % % % % %
The vendor supplied
Materials needed as per 1.97 0.976 38.30% 36.40% 15% 10.30%
the schedule
The vendor supplied
Materials needed as per 2.09 0.937 31.80% 34.60% 26.20% 7.50%
the desired Quality
Manpower from vendor
side were professional 3.44 0.569 3.70% 48.60% 47.70%
and Experienced
Manpower from Vendor
side were Committed to
2.07 0.418 5.60% 82.20% 12.10%
accomplish the project as
per the baseline plan
Local contractor (SME)
capacity was the main
2.81 0.848 40.20% 44.90% 8.40% 6.50%
challenge for project
delay
Land acquisition process
was the main challenge 2.93 1.007 2.80% 37.40% 32.70% 18.70% 8.40%
for project delay
There were Electric
Utility & Road
Availability problem to 2.94 1.097 11.20% 25.20% 25.20% 34.60% 3.70%
implement the project on
time
Over all Mean Average 2.61 0.836
Source: SPSS output (2020)
As illustrates in the above table 4.7, Majority of the respondents 80(74.7%) with mean value
1.97 agreed that the vendor was not supplied the needed materials for the project on time.
Similarly, majority of the respondents 71(66.4%) are agreed that the vendor didn‘t supplied the
materials as per pre-defined qualities. Regarding to whether the manpower presented by the
vendor were professional and their project experience 52(48.6%) of the respondents are neutral
while 51(47.7%) of the respondents agreed as the man power supplied by the vendor were
professional and have experience in the project work. Concerning the commitment level of
Vendor manpower to accomplish the given work on time Majority of the respondents 93.8%
50
with mean value 2.07 are agreed that the they were not committed to accomplish the project
work on time. Generally regarding to Vendor related cases the finding sought that big gap from
vendor side.
As part of the external factors respondents were asked to state their agreement and disagreement
about local contractor‘s capacity, Land acquisition process as the main challenges for the project
delay majority of the respondents are disagreed with respective mean value 2.81 and 2.93.
Regarding to Electric Utility & Road Availability as a main challenge for the project delay
significant amount of the respondents 37(34.6%) with mean value 2.94 agreed that Electric
Utility & Road Availability were challenge during project implementation.
Regarding whether the intended objective and goal of the project achieved or not Majority of the
respondents 66(61.7%) with mean value 3.56 agreed that the intended objective and goal of the
project achieved. The majority of the respondents 86(80.4%) with mean score value 1.87 are not
51
agreed for the on time completion of the project. Similarly, the project participants were asked
whether the project utilized the planned budget efficiently or not, in this regard majority of the
respondents 51(47.6%) with mean score value 2.45 are not agreed. Similarly, majority of the
respondents were not agreed with all the quality standard of the project was delivered and the
project team members are satisfied with respective mean score 2.39 and 2.31.
Brandon (2006) in his definition of project success explained that ―Cost, time, and quality (often
referred to as the Iron Triangle) have formed the prime basis for measuring project success for
the last 50 years. This classic criterion remains the most broadly used measure of project success.
Its core value is in offering a simple, direct measure of performance of a project and the project
management expertise applied to complete the project within the limits of the most immediate
design parameters (time, cost, and scope). However, it has major restrictions. Most critically, it
focuses on the means rather than the ends of the investment from the organizational perspective.
It takes limited or no account (depending on how scope is defined and measured) of whether the
main project deliverable fulfilled the purpose for which it was intended and whether the
objectives of the project‘s investors were achieved. For example, it is not unusual, especially in
IS projects, for a project that is late, over budget and/or under-delivered against specifications to
be declared a success, because it still delivered a benefit to the client/users and/or to the investing
business. This suggests that the presence of additional project success measurement.
(Bannerman,2008)
If we evaluate SR, SWR and SER project success in terms of the iron triangle (Time, Cost and
Quality) the project was not successful but based on the finding the intended objective and goal
of the project is achieved though still the project team members were not satisfied.
52
indicating that there is a strong relationship between the variables being correlated whereas
values closer to 0 indicate that there is little or no linear relationship. The sign of a correlation
coefficient defines the type of relationship between the variables being correlated. A positive
correlation coefficient shows that there is a positive linear relationship between the variables
(Field, 2009).
The level of significance and interpretation of the correlation result was made based on Somekh
and Lewin (2005) criterion for evaluating the magnitude of a correlation.
r values between 0 and 0.33 (0 and −0.33) indicate a weak positive (negative) linear
relationship.
r values between 0.34 and 0.66 (-0.3 and −0.66) indicate a moderate positive (negative)
linear relationship.
r Values between 0.67 and .99 (−0.67 and −99) indicate a strong positive (negative) linear
relationship
53
Table 4.10 Correlations between project management practices and project success
Scope HR Communica Stakeholder Planning Externa Project
tion l factors success
Scope 1
HR .405** 1
Communication .169 .483* 1
*
4.2.3 Relationships between Human resource management practice and Project success
In similar way the relationship between Human resource management practice and project
success of SR, SER and SWR was measured and as can be seen from Table 4.10 above the
degree of association between Human resource management practice and project success is
tested. Project success and human resource management practices are significantly correlated at
1% level of significance; P- value is 0.000 which is less than 1% or we have more than 99%
level of confidence. The coefficient of correlation (r) between Human resource and performance
is 0.443 which is greater than the minimum cutoff point (0.33) but less than the strong
association cutoff (0.66) and this imply that the two variables are moderately correlated and they
have significant correlation. The coefficient of correlation has also positive sign and this show
the two variables are positively correlated or they move in same direction. From this we can say
that as Human resource management practices are properly practiced the project success will be
increased to moderate extent.
54
4.2.4 Relationships between communication management practice and Project success
As shown in table 4.10 above, project success and Communication management practices are
significantly correlated at 1% level of significance or P- value is 0.001 which is less than 1% or
we have more than 99% level of confidence. The coefficient of correlation (r) between
Communication management practice and project success is 0.319 which is below the cutoff
point and this may imply that the two variables are weakly correlated though they have
significant correlation. The coefficient of correlation has also positive sign and this
demonstration the two variables are positively correlated and they move in same direction. From
this we can say that as Communication management practices are properly practiced project
success of SR, SWR and SER will be increased to some extent.
As we can observe from Table 4.10 above the relationship between Stakeholder management
practices and the project success are significantly correlated at 1% level of significance; P- value
is 0.001 which is less than 1% or we have more than 99% level of confidence. The coefficient of
correlation (r) between Stakeholder management practice and project success is 0.439 which is
above the cutoff point and this may imply that the two variables are moderately correlated. The
coefficient of correlation has also positive sign and this show the two variables are positively
correlated and they move in same direction. From this we can say that as stakeholder
management practices are properly practiced the project success of SR, SWR and SER will be
increased to some extent.
In this subsection we will see the level of correlation between project planning practices and the
project success of SR, SWR, SER. As we can see from Table 4.10 above the relationship between
planning practices and the project success is checked by Pearson correlation (2-tailed) and
significantly correlated at 1% level of significance or P- value is 0.000 which is less than 1% this
implies we have more than 99% level of confidence. The coefficient of correlation (r) between
planning practice and project success is 0.547 which is above the cutoff point and this may imply
that the two variables are moderately correlated. The coefficient of correlation has also positive
55
sign and this show the two variables are positively correlated or they move in same direction.
From this we can say that planning practices are properly practiced the project success of SR,
SWR and SER will be increased to some extent.
In this subsection we will see the level of correlation between External factors and the project
success of SR, SWR, SER. As we can observe from Table 4.10 above the relationship or degree
of association between External factors and the project success is checked by Pearson correlation
(2-tailed) and the result reveled that External factors doesn‘t have that much significant relation
with the project success.
Regression analysis is a way of forecasting an outcome variable from one predictor variable
(simple regression) or several predictor variables (multiple regressions) (Field, 2009). This study
tried to assess the effect of project management practices on project success. Project
Management Knowledge areas practice, project planning practice and the external factors were
considered as independent or explanatory variables and project success (Schedule, Budget,
Project goals and objectives and Tem satisfaction) as dependent variable.
Before estimating the coefficients, some tests are made like multi collinearity, normality,
linearity, Homoscedasticity and presence of influential outliers to check whether the model is
properly formulated or not.
Multi collinearity test is mainly intended to check whether the explanatory variables are linearly
correlated each other or not. Because if independent variables are highly correlated each other,
they are talking about the same thing and cannot be considered as independent. Multi collinearity
can be tested with the help of tolerance and variance inflation factor (VIF). As rule of thumb, If
the value of tolerance is less than 0.2 or 0.1 and, simultaneously, the value of VIF 10 and above,
then the multi collinearity is problematic. Kutner et.al (2004) suggest that if VIF is greater than
56
10 then multi collinearity is high. Accordingly, the model was tested whether it is free from this
problem or not and as can be seen from below table 4.11 there is no problem of multi collinearity
in the model.
This assumption tested by looking at the P-P plot for the model. The closer the dots lie to the
diagonal line, the closer to normal the residuals are distributed. As illustrated in the below figure 3
the P-P plot for the model suggested that the assumption of normality of the residuals have been
met i.e. the values of the residuals are normally distributed.
57
4.3.1.3 Assumption of Linearity and Homoscedasticity test
Our final assumption tested by the Cook‘s Distance statistic for each participant. Any values
over 1 are likely to be significant outliers, which may place undue influence on the model, and
should therefore be removed and your analysis rerun. In our case, Case No.63 found as an outlier
and removed before conducting the analysis.
The multiple linear regression part in this study is mainly intended to assess whether the
presumed explanatory variables are significantly affecting the dependent variable or whether the
practices and external factors have significant effect on project success. Based on this,
58
coefficient of the four knowledge area practice, planning practice and External factors were
estimated as below. Coefficients of Planning, is significant at 1% level of significance. But
coefficient of scope management practices, stakeholder management practice, communication
management and human resource management practice and External factors are not significantly
explaining project success at all as the probability value is greater than 5%.
Furthermore, the overall significance of the model is also tested using F-statistics and it is
significant at 1% level of significance but the overall variation in the dependent variable
explained by the explanatory variables is only 58.7% (adjusted R squared) and the remaining
41.3 % variation on the dependent variable is explained by other unobserved factors that are not
included in the model.
It can be inferred from the regression result that the most critical factor (practice) that is highly
and significantly explaining SR, SER and SWR project success is planning practice with
coefficient of 0.88 and P < 0.01. This may indicate that as practices in the project panning are
properly practiced and increase by one unit while other factors remain unchanged, SR, SER and
59
SWR project success increased by 0.88. And this may imply that as planning practice in project
properly planned and efficiently practiced, Project success will be enhanced with .88 proportion
and thus, SR, SER and SWR project success is highly determined by the effectiveness of project
planning practice.
B Std. Error
(Constant) .468 .464 3.009 .050
Scope Management practice .021 .092 .824 .103
HR management Practice .131 .111 1.978 .082
Communication Management .169 .114 1.487 .090
practice
Stakeholder management practice .220 .149 2.472 .074
Project Planning practice .881 .152 6.833 .000
External factor .208 .117 1.775 .119
Source: SPSS output (2020)
Project managers are assumed to have bigger picture in understanding the ups and downs of their
project starting from planning up to completion and this make them the right contact persons for
the researcher to have better broader understanding regarding their project management
practices, challenges faced/ lesson learned during the implementation of SR, SER and SWR
(Ericson circle) project. Accordingly, the qualitative data gathered from 3 project managers and
1 program manager, via the interview data collection method, is summarized below:
To understand the general view of project managers regarding the extent of project management
practices being implemented in Ericson‘s circle project, respondents were asked about what
project management practices they have commonly or less commonly observed/practiced. To
support the respondents in remembering the practices, lists of possible project management
60
practices were also mentioned to them. Accordingly, all of the 4 respondents indicated that
almost all Project management practices such as Quality planning, Risk management planning,
communication scope management practices, human resource management practices and project
planning practices are most commonly observed/practiced. whereas, practices such as Project
stakeholder management practices and project communication management practices are less
commonly observed/practiced. As Fraz et.al (2016) pointed out, best project management
practices that involve the most common ones like scope management, human resource
management, project planning, project stakeholder and project communication practices are
crucial for the success of today‘s complex projects. So at this level, it is possible to indicate that
the respondents have basic understanding of project management practices about which the study
focus on.
To have a general understanding about how project managers view project success, respondents
were asked how they define project success. All the respondents commonly indicated that they
categorize a given project as successful if the project is completed within the planned budget and
time, meeting the planned goals and objectives of the project. With this view, respondents were
asked if the Ericson‘s circle ethio telecom project was successful or not. Accordingly,
respondents commonly agreed that the Ericson circle project was not considered as successful as
it was not completed with the planned budget and schedule, in addition there was repetitive
rework to improve the network quality but at the end with lots of effort the project quality has
been maintained. Regarding to achieving high level objectives and goals like increasing the
network coverage and capacity of mobile network, swap the old legacy network equipment and
providing 2G/3G service up to the rural level, the project was successful.
61
the literature has no final list of critical project success factors but the respondents mentioned
almost commonly cited project success factors. The fact that ET‘s project managers mentioned
commonly cited project success factors indicates their level of understanding regarding what
makes a given project successful. Besides, most of the mentioned project success factors are also
component of our main independent variables-PM knowledge area practice and project planning
practices.
Accordingly, all respondents commonly agreed that all the PM practices mentioned have positive
contribution to the success of projects but only if they are practiced appropriately. 2 managers
indicated how poor project management practices like scope management practices negatively
affected the Ericson‘s circle project success particularly in terms of meeting the exact objectives
and goals of the project within the planned schedule.
After understanding how the project managers view the critical factors, respondents were asked a
follow up questions which ask what factors they think are important for the unsuccessful
completion of the Ericson‘s circle project in terms of time and budget. Accordingly, 2
respondents indicated poor implementation of project governance and poor scope management
practices as the main factors while 1 manager indicated lack of flexible project management
practice from the vendor side according to him the vendor was very procedural and while 1
project managers cited the external factors like quality or capacity problem of the vendor,
country wide infrastructural problems like limited power supply etc.
62
among project participants can negatively affect the completion of projects
effectively and efficiently.
o 2 project managers indicated that the project scope was poorly defined and
frequently changed. As Pheng (2017) indicated project scope management is
very critical in terms of meeting the desired needs of a project within the
planned budget and schedule. Poorly prepared project scope affects project
performance in terms of cost, schedule and quality.
o 1 respondent indicated that Lack of well-established project risk identification
and mitigation strategies was observed.
o 1 respondent indicated that Project were not conducted (implemented) in
accordance with the project charter, the project charter was well prepared by
including lesson learned from NGN.
o All 4 respondents commonly indicated that there Lack of project management
skills and experience from the vendor as well as from ethio telecom side.
2) Other Gaps in relation with external factors
o 2 project managers indicated Vendor‘s side manpower competency problem
especially at the beginning phase the man power from the vendor side were lacks
appropriate knowledge and skill to implement the project.
o 1 program manager also indicated resource and logistics related gaps especially
at the beginning-the right resources were not available at the right time, project
materials were not properly managed and some materials were even missed from
o According 2 project managers and 1 program manager, there was frequent power
interruption and poor backup battery performance
o 2 project managers indicated gaps in relation external factors competency
problems like small enterprises that built poor foundation for network that could
not carry the desired network tower.
63
o 3 respondents clearly indicated the need for proper project planning and scope
management practice. As respondents indicated, at the beginning, the project plan
and scope was not properly prepared and it was being changed frequently leading to
inefficient budget and time management. Poorly prepared project scope could also
lead to unrealistic project completion deadlines for the vendor which may result in
failure of the vendor to meet the target. So, respondents pointed out the need to
improve the practice of project planning and scope management practices.
o 1 program manager indicated that in sectors like telecommunication, the technology
changes frequently and investing huge project that don‘t give further flexibility will
be costly. With this in mind, the project was made to be scalable that allows network
upgrading from 2G up to 4G with low fixed cost. Thus, the need to have open ended
projects that enable further possibility of flexibility/upgrading with less additional
cost is important lesson learned.
o 2 project managers indicated that they have learned a lot in project management due
to TEP specifically in Ericson circle ethio telecom projects. This is very important
for future projects ethio telecom manages as PM knowledge area practices are one of
the critical success factors for projects. Accordingly, Ethio telecom project managers
learned mainly the need to enforce vendors to transfer their knowledge/skill to ET
staffs after completing their projects. The need for more project management
knowledge, skill and experience in conducting future projects is another lesson
learned from Ericson project
o 1 program manager indicated that they have learned for the need for effective
stakeholder‘s management practices specially at the beginning phase of projects as
they faced challenges in securing the needed electric power and lands. To mobilize
and effectively utilize all the resources required by the project, involving and
managing all the stakeholders is very important to successfully complete a given
project with desired objectives, time and schedule. Securing Organizational and
government support is crucial in getting all the resources required for a project.
64
4.4 Discussion
The purpose of this study was to assess the ethio telecom Project management practices and
investigate the relationship with the project success a case study on SR, SWR and SER Mobile
network telecom expansion project. The study identified four practice from Project Knowledge area
management, Level of project planning practices and External factors and tried to analyze the data
from the respondents which were participated in the project. All the variables had an acceptable level
of reliability with Cronbach‟s alpha > 0.7.
Project management body of knowledge covers all aspects of managing projects from inception
to completion using methods and methodologies, tools, decision making techniques, risk
assessment tools, and approaches to improve successful project outcomes and achieve business
objectives (Raz and Michael, 2001). In our descriptive statistics analysis, the selected four
project management knowledge area were practiced Moderately. From scope management
knowledge area, the majority of the respondents were agreed on the presence of WBS and the
approval of the scope change by the top management. The application of project scope
management practices has significantly impacted project success leading to fulfilled customer
expectation and satisfaction; better resource allocation and timely project delivery.
Telecommunication firms should therefore make it mandatory for scope management practices
to be employed in the implementation of all telecommunication projects since low success rates
were recorded in projects implemented without scope management practices. (Ogunberu,2018)
The respondents were not satisfied on the presence of project management related training and
best performer were not selected and recognized during the project implementation, so to keep
the team motivation and accomplish the project as per the bassline ethio telecom need to work
strongly in this areas. According to the survey, it can‘t be decided that the information need of all
stakeholders was not satisfied at the required level throughout the project lifecycle. Since there
are different stakeholders who needs different kind of information at different time the
communication has to be designed and implemented effectively. Regarding to stakeholder
management practice the stakeholder was properly identified, concerning managing the
stakeholder and providing relevant information in regular basis to the stakeholders the
respondents were uncertain. Proper project stakeholder management make a difference in the
performance of a project, the survey finding also revealed this, to have successful stakeholder
65
management there should be well-organized and separate project stakeholder management unit,
in this project most responsibility was on the shoulders of the project directors and managers.
Heerkens (2002) also explained that, project management really consists of two major phases doing
the right project and doing the project right. Ensuring that your project is based upon a true need and
that it is justified from a business standpoint are two important aspects of doing the right project.
Project planning, on the other hand, is all about doing the project right. Project planning gets more
attention than any other aspect of project management and justifiably so. It‘s hard to imagine how a
project could be successful without some planning. In regression results as can be seen from the table
4.11 above, it has the highest coefficient from all the factors and is significantly explaining the
project success. The finding from interview also shows that the project planning was not practiced
properly and they consider poor planning as the main reason for the project delay and over budget
utilization.
The descriptive statistics findings indicated that from external factors vendor related factor were the
major reasons which affects the SR, SER and SWR project performance Electric power availability
and the SME performance on the civil work were among the reasons for the project delay while ethio
telecom was good in cooperating with local administration for land facility but still there was some
limitation to provide land for mobile network tower installation in the towns.
66
CHAPTER FIVE.
o From the descriptive statistics analysis, majority of the respondents with M=3.23
SD=.988 believed that Scope management practices were neither strongly practiced nor
totally forgotten. The interview result also shows that ethio was not good in scope
management practice.
o The finding reveled that human resource management was moderately practiced with
M=2.93 SD=1.068 while the respondents feel that project management training and
reward and recognition were not practiced well in the project. From the interview
analysis sufficient man power were assigned but the knowledge and skill of the project
member was not strong enough to support and control the vendor at the required level.
This result is supported by the interview analysis.
o Though the mean value M=2.93, SD=1.026 reveled that respondents are moderately
agreed on the communication management practice from the frequency distribution table
also shows that most respondents were uncertain about the proper practice of
communication management during the project.
o From Stakeholder management practice survey the respondents were uncertain about the
presence of proper coordination with stakeholders, whether project status updates are
provided to key stakeholders regularly or not and Stakeholders‘ participation in the
project was managed well. Majority of the respondents agreed only on the proper
identification of the stakeholders with mean value M= 3.61, SD=. 810.The interview
result also revealed that ethio telecom project team as interface with different
stakeholders they were faced different challenges, there was conflict of interests even the
project was suspended due to vendor underperformance and the work resumed after
serious negotiation with the top management.
67
o Based on the survey finding the integration management planning activity was only well
practiced but the remaining planning activity were not practiced properly and needs
improvement.
o The interview finding also revealed that proper planning was not done before the project
execution, project scope, human resource and materials for the project estimated and
ordered based on the nominal plan. The actual work of the project was beginning before
basic project plan like HLD, Site survey and LLD preparation and the plan was prepared
parallel with project implementation. Regarding Time (schedule) management, the
planned project end date other schedule related elements were not estimated properly
o Furthermore, the data gather from the interview revealed that the potential risks of the
project were not identified properly, risk mitigation and response strategy were not
developed.
o Majority of the respondents with mean value M=1.97, SD= 0.976 agreed that the vendor
didn‘t supplied project related material on time; similarly, the majority of the respondents
with mean value (M=2.09, SD= 0.937) agreed that project materials were not supplied as
per the standard and the manpower from the vendor side were not committed to
accomplish the project work as per the bassline plan. This finding also supported by the
interview, as compared with other vendors who were participated in the project the
overall performance of the vendor who awarded SR, SWR and SER TEP mobile role out
project was not satisfactory. This accounts the significant contribution for the schedule
delay and over budget utilization.
o The performance of SME, availability of Electric utility and land acquisition process
were not challenge in the project implementation. In fact, according to the finding from
the interview there was power interruption but due to strong coordination with EEU the
impact of the problem was minimized.
o Accordingly, as per the survey result, majority of respondents indicated that the project
was not completed within the planned budget and schedule, and the quality standard of
the project was also not satisfied but through strong close follow, monitoring and
evaluation at the end the quality standard improved.
o The degree of association between project management practices with project success
was assessed using correlation analysis. The result shows, Scope management and
68
Communication management practice have weak but positive correlation with project
success. Human resource management, Stakeholder management & planning practices
have positive and moderately strong association and Communication and External factors
have no association with project success. To assess the effect of each project practice and
External factors on project success, regression analysis was conducted and the result
shows, planning have strong significant positive effect on project success. While the four
knowledge management practice, External factors have no significant effect on project
performance.
5.2 Conclusion
Based on the findings of the study, the below conclusions are drawn:
Considering the moderate level of project scope management practices as well as the
frequent scope changes observed in ET‘s Ericson circle project especially at the
beginning phase, it is possible to conclude that ET was not in a position to collect all the
project requirements and objectives at the initial stage and failed to develop a complete
and long lasting project scope that eventually affected the success of the project.
As the findings indicates, there was lack of project management skill and experience and
lack of project staff motivation. This indicates that among human resource management
practices, ET has shown low level of project management training and
reward/recognition management practices.
The study concludes that ET has less significant level project planning, stakeholder
management and human resource management practices while managing Ericson‘s circle
projects.
The finding indicates that there is positive and statistically significant relationship
between Project stakeholder management practices and project success. This result shows
that Project stakeholder management practices is one of the factors affecting project
success in mobile network expansion project of Ethio telecom.
The finding also shows that project human resource management practice and project
success has statically significant relationship. This indicates that proper human resource
69
management practice is one of the factors affecting project success in mobile network
expansion project of Ethio telecom.
Though the project was not successful in terms of the traditional project success
measurement and project team satisfaction, it was good in achieving its goals, objectives and
delivering telecommunication service with good quality with some incompatibility problems.
From this the project was good in delivering all the expected deliverables and currently
giving the required service to the society except elapsing extra budget and to a great extent
extended in its completion date from 2 years almost to 5 years.
5.3 Recommendations
o Before starting a project, Ethio-Telecom should properly identify project requirements and
objectives by involving all concerned work units and experts so as to develop the right
project scope that enable the company completes a project within the desired quality, budget
and schedule.
o McElroy & Mills (2000) indicated that the purpose of stakeholder management is to achieve
project success by involving stakeholders and securing their cooperation. In relation with, ET
needs to improve its stakeholder management practices especially at the beginning stage of
projects as it is critical to secure all the necessary project resources before starting a project.
In addition to enhancing the job of program directors to involve more stakeholder
management tasks, establishing a separate stakeholder management section could be more
supportive.
o Communication is possibly the most important success factor since there is the need to
build stronger cooperative relationship through continuous engagement and information
sharing as well as harmonization of stakeholder plans at all levels. So as to facilitate the
fulfillment of this strong need well designed and appropriate communication plan should
always be in place. Moreover, the top- down and the Top up communication should be
effective so as to make all the project stakeholder on the same page.
o To successfully accomplish the project within the required standard, focus, essential
elements, budget and schedule and the correct sequence, ethio telecom should have to
prepare the project plan before project execution and unplanned work should be
incorporated in the master plan as needed.
70
o Sufficient lead time should also be allocated for site survey and approval of low level
design (LLD) before project execution. This will minimize the contract amendment and
scope change made at different level of the project implementation.
o It would be better if project schedule estimation done based on work package and activity
with clear resource requirements. Clear activity sequencing and critical path mapping will
help ethio telecom as well as the vendor to set realistic project accomplishment time.
o Recognizing lessons learned and correctly documenting them for future use is very
helpful, ethio telecom should develop a strong culture of lessons learned documentation
at every project performed by the organization this will be helpful not to repeat similar
mistakes in the future projects.
o Ethio telecom should take great care in selecting and awarding vendors, vendor
performance should be monitored and evaluated regularly and based on the needs,
selective support should be provided to the vendor. In addition to keep the project on
schedule and budget ethio telecom top management should take corrective measure
wisely for any discrepancies as fast as possible.
o SR, SER and SWR project was not completed within the planned budget and schedule.
Thus, ethio telecom should have to develop an accurate and efficient planning of
resources and activities as well as scope managements, risk identification and mitigation
plans and strong auditing system should be practiced to avoid additional budget and time
requests in future projects. Specially the project schedule should be realistic and
estimated by using scientific methods like CPM, this method helps ethio telecom to know
the maximum, minimum and the total time required to complete the projects.
Data collection was also limited by the busy schedules of the respondents. The researchers had to
exercise utmost patience and make extra effort in reminding respondents and making constant
follow-ups so as to acquire sufficient data from respondents. Some of the respondents
approached were reluctant in giving some information fearing that the information sought would
be used to intimidate them. The researcher handled the problem personally convincing and
assuring respondents that the information will be treated as confidential and would be used
purely for academic purposes. The other possible limitation is the fact that some respondents
71
may not exactly remember project practices they implemented. Besides, it is likely that some of
the subjective responses obtained from the respondents may minimally affect the objectivity of
the research inputs.
The fact that there is a limited/almost non available accumulated knowledge on project
management practices or secondary documents like project performance reports made the
research process challenging but interesting one. The last but honest limitation is the fact that the
student researcher lacks thorough practical experience in conducting such research.
However, to reduce the negative impact of the limitations described above, the following major
actions were taken:
o Related studies conducted locally and in other related closely related developing
countries were reviewed together with extensive study about issues of project
management practices.
o While collecting data, briefed respondents/personally administering data collection
instruments/ about the purpose of the study and contents of the data collection
instruments so as to ensure respondents give the right information without being confused
or without making assumptions.
o Not to be affected by possible wrong memory of respondents, to let respondents use a
questionnaire with listed choices to pick
o In addition to following/implementing the feedback of this research‘s adviser, books
written on research methods as well as previously prepared thesis papers, journal articles
were reviewed so as to quickly improve/refresh the student researcher‘s knowledge
regarding the processes of research.
This study was limited to one company project case Specifically Ethio telecom TEP -Ericson‘s
circle projects (SR, SER and SWR), and hence its findings cannot be generalized to other Ethio
telecom TEP or other public organizations in Ethiopia and else. What is more is that there is no
enough study conducted on project management practices and their effect on project success
especially considering vendors‘ side project management practice. Therefore, this study suggests
similar studies to be conducted on non-telecom other sectors including vendors that directly
72
provide their service based on projects. Furthermore, the study does not end up with list of
ultimate or universally agreed project management practices that guarantee project success.
Therefore, the study suggests others to research further and attempt to develop best project
management practices/standards for each sectors/project types. Besides, other external factors
that can potentially affect the performance/success of projects such as the role of vendor
financing on the quality/performance of projects, political environment, socio-cultural
environment, technology need to be studied further.
73
References:
Adeyemi, I. (2013). Effects of Project Management on the Performance of a Construction Firm
in Nigeria. American International Journal of Contemporary Research, 3(6), 54-
58.
Ahmed Fraz (2016) Effect of Project Management Practices on Project Success in Make-to-
Order Manufacturing Organizations. Indian Journal of Science and Technology,
Vol 9(21),
Alotaibi, A. B. (2019). Project Management: The Implication of Project Management Practices
on Project Success in Saudi Arabia. Portsmouth: University of Portsmouth.
Alsulamy, S., Gupta, N., & Sloan, B. (2014). Factors influencing municipal construction project
performance. Municipal Engineer, 167(ME2), 108-117.
doi:10.1680/muen.13.00029
Al-Turfi, Sadeq (2017) Best practice project management for the sustainable regeneration of
Holy Karbala Province in Iraq. PhD thesis, University of Bolton. UK
Anbessie, M. (2017). Assessment on Performance and Challenges of Ethio Telecom
Infrastructure Expansion project Implementatio, Monitoring and Evaluation.
Addis Ababa: Unpublished.
Atsbha,2018. Assessment of Telecom Project Implementation Practices in Ethiopia: The case of
Telecom Expansion Project: Addis Ababa, Unpublished.
Avison, D.E. and Torkzadeh, G. (2009), Information Systems Project Management: SAGE
Publications, New Delhi, USA.
Beleiu, I., Crisan, E., & Nistor, R. (2015). Main Factors Influecing Project Success.
Interdisciplinary Management Research, 59-72.
Belete, Y. (2019). Assessment of Project Stakeholder management practice in the case of ethio
telecom.Addis Ababa. Unpublished.
Bannerman, Paul. (2008). Defining Project Success: A Multi-Level Framework.
Bogale, W. (2005). A Background Paper on Telecom and Telecom Statistics in Ethiopia. Addis
Ababa: Unpublished.
Chou, J.-S., & Yang, J.-G. (2012). Project Management Knowledge and Effects on Construction
Project Outcomes: An Empirical Study. Project Management Journal, 43(5), 47-
67.doi:10.1002/pmj.21293.
74
Cleland, D. I., & Ireland, L. R. (2006). Project management: strategic design and
implementation (5th ed.). New York: McGraw Hill.
Cooper, R. G., & Kleinschmidt, E. J. (1995). Benchmarking the firm‘s critical success factors in
new product development. Journal of Production Innovation Management, 12,
374–391.
C.R.Kothari. (2004). Research Methodology, Methods and Techniques (2nd ed.). New Delhi:
New Age International Limited Publisher.
Cresswell JW, Plano Clark VL. Designing and conducting mixed method research. 2nd Sage;
Thousand Oaks, CA: 2011. [Google Scholar]
Crişan; Liviu Ilieş and Irina Salanţă, (2010), Management Best Practices Used in Romanian
Logistics Customer Service Planning, The AMFITEATRU ECONOMIC journal,
12, (27), 215-227.
Cooper, D and Schindler P. (2003) Business Research Methods, 8th edn., New Delhi : Tata
McGraw-Hill Publishing Company Limited, p120.
De Wit, A., (1988) ‗Measurement of project success‘, Project Management Journal, 6(3), p.164-
170.
Damoah, I., Akwei, C. & Mouzughi, Y., 2015. Causes of government project failure in
developing countries – Focus on Ghana... Portsmouth University, BAM-British
Academy of Management.
De Wit A. Measurement of project success. International Journal of Project Management. 1998;
6(3):164–70.
Egginton, B. E. & Fitz-Gerald, A. M. (2012). Learning from the East African experience:
PROFIDE—a model for improved program management in the security and
development environment. Paper presented at PMI® Research and Education
Conference, Limerick, Munster, Ireland. Newtown Square, PA: Project
Management Institute.
Ethiopia Telecoms, Mobile and Broadband Statistics and Analyses 2019 -
ResearchAndMarkets.com | Business Wire
Ethiotelecom, (2013). Telecom expansion program charter. Ethio-Telecom
Field, A. (2009). Discovering Statistics Using SPSS (3rd ed.). London: SAGE Publication Ltd.
75
Flyvbjerg, B., Holm, M. S., & Buhl, S. (2002). Underestimating costs in public works projects:
Journal of the American Planning Association, 68(3), 279–295
Fortune, J., & White, D. (2006). Framing of project critical success factors by a systems model.
International Journal of Project Management, 24(1),53–65.
Francis O. (2015) Constraints to Expansion of the Telecommunication Sector in Kenya: Public
Policy and Administration Research www.iiste.org ISSN 2224-5731(Paper) ISSN
2225-0972(Online) Vol.5, No.3, \ 2015
Growth and Transformation Plan Annual Progress Report for F.Y. 2012/13
Haron, N. A., Devi, P., Hassim, S., Alias, A. H., Tahir, M. M., & Harun, A. N. (2017). Project
management practice and its effects on project success in Malaysian
construction industry. In IOP Conference Series: Materials Science and
Engineering, 291(1), 214 -218
Ika, L. & Saint-Macary, J., 2014. Special Issue: Why Do Projects Fail in Africa? Journal of
African Business, 15(3), pp. 151-155.
Ilies I, Crisan E, Muresan I. Best practices in project management. Review of International
Comparative Management. 2010; 11(1):1–3.
Johnson, J., Karen, D., Boucher, K. C., & Robinson, J. (2001, February/March). The criteria for
success. Software Magazine, 21, 1, S3.
Jakobsson, U., 2004. Statistical presentation and analysis of ordinal data in nursing research.
Scandinavian Journal of Caring Sciences, 18(4), pp. 437-440.
John S. Reel (1999) Critical Success Factors in Software Projects: IEEE software May / June
1999.
Jugdev, K., & Müller, R. (2005). A retrospective look at our evolving understanding of project
success. Project Management Institute.
Karadsheh, L. et al., 2009. A Theoretical Framework for Knowledge Management Process:
Towards Improving Knowledge Performance. s.l.:Communications of the IBIMA.
Kerzner, H. (2006). Project management: A systems approach to planning, scheduling and
controlling (9th ed.). New York : John Wiley and Sons.
Kerzner, H. (2009), Project management: A system approach to planning, scheduling, and
controlling. 10th ed., John wiley& sons, IncNew Jersey.
Kerzner, H. (2017). Project Management (12th ed.). Hoboken, NJ: John Wiley & Sons.
76
Keil, M., Rai, A., Ellen, J., Mann, C., & Zhang, G. P. (2003). Why software projects escalate:
The importance of project management constructs. IEEE Transactions on
Engineering Management, 50(3), 251.
Lim, C.S., Mohamed, M.Z., (1999) ‗Criteria for project success: an exploratory re-examination‘,
International Journal of Project Management, 17(4), p.243-248.
Lyytinen, K. & Hirschheim, R. (1987). Information systems failures: A survey and classification
of the empirical literature. Oxford Surveys in Information Technology, 4, 257-
309.
McElroy, B. & Mills, C., 2000. Managing stakeholders. In Gower Handbook of Project
Management. 4th ed. Aldershot, UK: Gower.
Haftom, M. (2019). Assessment of Projct Managmnet Practice and Challenges: The Case of
Telecom Expansion Project (TEP) in Ethio Telecom.
Menon, S., 2015. Best Practices and Implementation Challenges in Effective Project
Management, Minneapolis, Minnesota: s.n.
Meredith J. R., & Mantel S. J. (2006). Project management: A managerial approach (6th ed.).
New York: John Wiley and Sons.
Mugenda, O. M. & Mugenda, A. G. (2003). Research methods: Quantitative and qualitative
Approaches. Nairobi: African Centre for Technology Studies.
Mulcahy, R. (2009), PMP Exam Prep: Rita’s Course in a Book for Passing PMP Exam Sixth
Edition, RMC Publications. United State
Müller, R., Jugdev, K., (2012) ‘Critical success factors in projects
Müller, R. & Turner, J. R. (2001), 'The impact of performance in project management
knowledge areas on earned value results in information technology projects',
International Project Management Journal, vol. 7, no.1, 44-51.
Munns, A. K., Bjeirmi, B. F., (1996) ‗The role of project management in achieving project
success‘, International Journal of Project Management, 14(2), p.81-87.
Nigussie, T. (2018). Assessment of Core Project Constraints Management practice: In the case of
Information system projects: Ethio telecom.
Ogunberu A.O., Olaposi T.O. and Akintelu S.O. (2016), ―Factors affecting the choice of project
scope management practices among telecommunication organizations‖, Global
journal of management and business research, Vol. 16 No. 3
77
Ogunberu, A., Akintelu, S., Olaposi, T. (2018). Application of project scope management
practices on project success among telecommunication organizations in Nigeria
Pinto, J.K., Slevin, D.P., (1988a) ‗Project success: definitions and measurement techniques‘,
Project Management Journal, 19(1), p.67-73.
PMI,2013. A guide to the project management body of knowledge (PMBOK® Guide) (5th ed.).
Newtown Square, PA, USA: Project Management Institute (PMI)
PMI, 2017. A Guide to the Project Management Body of Knowledge (PMBOK® Guide). 6th ed.
Newtown Square, PA: PMI Publishing.
Richman, L., 2011. Successful Project Management. 3rd ed. New York: AMACOM, American
Management Association International.
Ramadan, W. H., & Tu, Z. (2012). Project Management Literature: Gaps and Opportunities.
Berlin: ELeader.
Robert Burns, a. R. (2008). Business research methods and statistics using SPSS. London: SAGE
Publications Ltd.
Sherif, M. H., 2006. Managing projects in telecommunication services. New York: John Wiley
and Sons.
Shenhar AJ, et al. (220). Refining the search for project success factors: A multivariate,
typological approach. R&D Management, Oxford. 2002; 32(2):111–27.
Somekh, B. & Lewin C. (2005). Research Methods in Social Sciences. Sage Publications.
London: Thosusand Oaks
Papke-Shields, K. E., Beise, C., & Quan, J. (2010). Do project managers practice what they
preach, and does it matter to project success? International Journal of Project
Management (28), 650-662.
Patton MQ. Qualitative research and evaluation methods. 3rd Sage Publications; Thousand
Oaks, CA: 2002. [Google Scholar]
Paul, H. (2016). The Challenge of Project Leadership. International Project Management
Association (IPMA). [Online] Available at: https://www.ipma.world/the-
challenge-of-project-leadership/ (Accessed 3, August 2019)
Saunders, M., Lewis, P. & Thornhill, A. (2009). Research Methods for Business Students. (5th
ed). England: Financial Times Prentice Hall.
78
Serrador, P. (2012). The importance of the planning phase to project success. Paper presented at
PMI® Global Congress 2012—North America, Vancouver, British Columbia,
Canada. Newtown Square, PA: Project Management Institute.
Thomas, M.; Jacques, P. H.; Adams, J. R. & Kihneman-Woote, J. (2008), 'Developing an
effective project: planning and team building combined', Project Management
Journal, vol. 39, no. 4, 105-113.
Thomas w.et al (2012) telecom business transformation: A network transformation success case
of an operator in Latin America.
United Nations Asian and Pacific Training Centre for Information and Communication
Technology for Development (2010), ICT project Management in Theory and
Practice, Briefing Note 7 available at: https://pdfslide.net/documents/ict-project-
management-in-theory-and-practice-565485c5504a2.html (accessed 14 Dec,
2019).
Woldemariam, S. (2019). Critical success factors of leading IS Projects. Un published.
Wubshet, M. (2017). Assessement of Logistics Practice in Project Context, The case of
ethiotelecom expansion project. Addis Ababa: Unpublished.
WangRui & Guhongfei ,2016: Determinant Factors influencing the use of Balanced Scorecard in
China. Master‟s thesis, Uppsala universitet
World Bank: project implementation document (PID), 2019.
Wysocki, R. K. (2014). Effective Project Management: Traditional, Agile (7th ed.). Indianapolis,
Indiana: John Wiley & Sons, Inc.
Zwikael, O., & Globerson, S. (2004). Evaluating the quality of project planning: a model and
field results. International Journal of Production Research, 42(8), 1545-1556.
Zwikael, O., Shimizu, K., & Globerson, S. (2005). Cultural differences in project management
processes: A field study. International Journal of Project Management, 23(6),
454–462.
79
ANEX I
Alpha University College School of Graduate Studies
Department of Project Management
Dear respondents, the purpose of this questionnaire is to gather data on ―The Effect of Project
Management Practice on Project Success: a case study on Ethio teleom Ericson’s Circle
(SR, SWR and SER) Mobile network Telecom Expansion Project‖. The study is purely for
academic purpose and thus not affects you in any case. So, your genuine, frank and timely
response is vital for successfulness of the study. Therefore, I kindly request you to respond to
each items of the question very carefully.
In order to examine the effects of project management practice on project success in ethio
telecom, the researcher prepared the following questions with regard to Ericsson Circle
(SR,SWR &SER mobile network expansion projects, please put tick (√) on the appropriate box
to indicate the extent to which you agree or disagree with each statement. It will take 15 to 20
minutes of your time to complete the questionnaire. In case of any question please contact me via
mobile +251 9-11-50-98-42.
Instruction: In all cases where answer options are available, tick (√) inside the given box.
Manager Director
80
Part II: Project Management Practice
Kindly tick (√) on the five scale of all questions under each category that best describes your
perception/observation/Experience of how project management is being practiced in relation
with Ericson‘s project circle (SR, SWR & SER).
Project scope control was made against the planned one for every scope
statement
Qualified and sufficient human resource have been supplied for project
implementation.
81
Project management training was provided for project team
When the budget or schedule was revised, the changes and reasons for the
change were communicated to all members of the project team.
82
B) Level of project Planning practice, please put (√) in the Choice box
The view of all project stakeholders are taken into account in every steps
of project planning
preparation/ development
project execution
83
Project Human Resource Management Plan is prepared during the
planning phase
The vendor (Ericson) supplied Materials needed as per the desired Quality
Local contractor (SME) capacity was the main challenge for project delay
Land acquisition process was the main challenge for project delay
There were Electric Utility & Road Availability problem to implement the
project on time.
84
Part III: SR, SWR &SER TEP Project Success Measurements
Think of the TEP project you have been participated (SR, SWR, SER) and put (√) in the box that best
describes your agreement and disagreement to the following Project Success Measurements.
85
Annex II - Interview Questions
Alpha University College School of Graduate Studies
Title of the thesis ―The Effect of Project Management Practice on Project Success: a case
study on Ethio telecom Ericson’s Circle (SR, SWR and SER) mobile network Telecom
Expansion Project.
Interview Questions for Project Managers and Program manager in Network Division of
Ethio Telecom:
❖ Questions related with overall Project management practice, challenges during project
implementation and Ericson Circle (SR, SWE &SER) project Performance.
1. What do you know about project management practices? Can you mention those practices
you have observed in ET?
2. Would you explain how was project team members assigned(organized) from both parties
and their contribution for the accomplishment of the project as per the bassline plan?
3. How do you define a successful project? What criteria do you see to categorize a given
project as successful?
4. What factors do you think affect project successes? Can you explain in it in relation with the
Ericson project?
5. What gaps have you observed in the implementation of Ericson‘s project?
6. What lessons did you learn from the Ericson project?
Thank you!
86