1 Scope
This Specification together with the Purchase Order and appropriate specification sheets
covers the minimum requirements of pressure preservative treatment for wood piles,
timbers and ties.
2.1 Any conflicts between this specification and other applicable Saudi Aramco
Materials System Specifications (SAMSSs), Engineering Standards (SAESs),
Standard Drawings (SASDs), or industry standards, codes, and forms shall be
resolved in writing by the Company or Buyer Representative through the
Manager, Consulting Services Department of Saudi Aramco, Dhahran.
2.2 Direct all requests to deviate from this specification in writing to the Company or
Buyer Representative, who shall follow internal company procedure SAEP-302
and forward such requests to the Manager, Consulting Services Department of
Saudi Aramco, Dhahran.
3 References
The selection of material and equipment, and the design, construction, maintenance, and
repair of equipment and facilities covered by this specification shall comply with the
latest edition of the references listed below, unless otherwise noted.
Page 2 of 4
Document Responsibility: Onshore Structures 09-SAMSS-002
Issue Date: 21 June 2011 Pressure Preservative Treatment
Next Planned Update: 8 October 2013 for Wood Piles, Timbers and Ties
4 Special Requirements
4.1 Definitions
All terms used in this Specification are defined within AWPA Standard M5.
4.2.1 Land and Fresh Water Application. The type of preservative used shall
be as specified in the Purchase Order and shall be in accordance with
applicable AWPA Standards P1, P2, P3 or P8. The preservative
treatment shall be in accordance with applicable AWPA Standards C1,
C2, C3 or C6.
4.3 Re-Treatment
Page 3 of 4
Document Responsibility: Onshore Structures 09-SAMSS-002
Issue Date: 21 June 2011 Pressure Preservative Treatment
Next Planned Update: 8 October 2013 for Wood Piles, Timbers and Ties
4.4 Inspection
Revision Summary
8 October 2008 Revised the “Next Planned Update". Reaffirmed the contents of the document, and reissued
with updated committee members list.
21 June 2011 Editorial revision to remove the committee members list.