Professional Documents
Culture Documents
Retrospective Analysis
Karen Best
Introduction
• Why delay Analysis?
• Delays happen
• Many sides to story
• Can give clearer picture
• Topics:
• Definitions
• Methods
• Choosing a Method
• Smoke and Mirrors
Definitions
Definitions
• Delay Analysis
• Exercise to ascertain effect of delay events on
planned programme
• Assess delay to completion, delay to progress,
disruption
• Retrospective Analysis
• Contemporaneous vs Retrospective
• No agreement on rules or terminology; SCL
Protocol gives definitions
• May or may not be critical path analysis
Methods of
Retrospective Analysis
Methods of Retrospective Analysis
• Three types:
1. Cause/effect matrix
2. Scott schedules
Planned bars
1. identify effect
2. allocate a cause
As built bars DELAY
• Two methods
1. As-planned impacted
2. As-built but-for [or collapsed as-built]
As-planned impacted analysis
• Based on the planned programme
• Demonstrate effect of employer delay events
on the planned programme by;
1. Identify the planned programme/ baseline
2. Establish excusable event based on planned intent
3. Add the event to the programme & recalculate the
completion date
4. Claim relief for the shift in timing on the programme
5. Repeat for next event
As-planned impacted analysis
1. Start with
planned programme
foundations
Contractual
Completion
Critical
structure
Date
roof & cladding
inspections
Contractual
Unforeseen ground Completion
Critical
structure Date
Employer’s inspections
risk event
Activity depicting
event
As-planned impacted analysis
Revised
Implied delay 3. Calculate effect Completion
to progress
Date
foundations
Contractual
Unforeseen ground Completion
Date
structure
Limitations
• Limited application - theoretical
• Ignores the as built history of the works
• Ignores the Contractor’s own delays
• Difficult to deal effectively with concurrency
• It ignores the effect of any change in sequence
or acceleration.
As-planned Impacted
Uses
• Fairly quick and easy to carry out
• It can be used where as-built information is
limited/ does not exist
• Can be suitable method of proof if:
• The planned programme was realistic and achievable;
• The critical path remains largely unchanged;
• The events were undisputably on the critical path
As-built-but-for/ Collapsed As built
1. identify 2. allocate a
secondary effect cause
Actual
Delay to
Original
progress Completion
duration Date
Unforeseen ground
foundations
structure
roof & cladding
inspections
Actual dates for activity
3. Convert to
critical path
foundations
program Actual
Completion
Date
Unforeseen ground
structure
Logic link
As-built-but-for/ Collapsed As built
Delay to
Delay to 4. Subtract completion
progress identified effect
foundations
inspections
As-built-but-for: As built programme
Contractual
foundations Completion
Critical
Date
structure
inspections
Planned bar
Time Impact Analysis
Revised
Completion
Updated programme Critical Date
after
Update
Slow
Contractual
progress foundations Completion
Critical
Date
structure
Culpable delay
Time Impact Analysis
Revised
Completion
Updated programme Critical Date
after
Update
Contractual
foundations Completion
Critical
Unforeseen Date
ground
structure
Period of delay
Time Impact Analysis
Revised
Impacted programme Completion
Critical
Date after
Foundations Event
Remainder of
completed to Contractual
foundations
update date Completion
Critical
Unforeseen Date
ground
structure