Professional Documents
Culture Documents
As-Built Technique
This technique is also termed as the
net impact technique [2]. This technique
simply compares the calculated dates on an
as-built schedule with an as-planned sched-
ule. This technique was implemented by
comparing the as-planned total float with
the delayed events of each activity [7]. Figure 1 — As-Planned Technique (Gross Measure)
Figure 3 shows the flowchart of this tech-
nique.
The adjusted as-built technique has
the same concept as the as-built technique
[1]. The adjusted as-built technique is used
when an as-built schedule is not available.
The as-planned schedule is adjusted by
inserting delay events as new activities to
the schedule. Then, one adjusts the
sequence of the project.
One of the negative sides of an as-built
technique is not considering the real time
delay during the progress of the work. In
addition, the concurrent delay issue is not
addressed. Consequently, this technique is
not a favorite one to use.
Concurrent Delay
Any delay analysis system must take
into account the concurrence of delayed
activities to avoid the error of multiple
counting of the project delay days.
The type of delay on each of the con-
current activities should also be known for
distributing the delay between the responsi-
ble parties. Concurrent delays occur in par-
Figure 7 — Window Snapshot Technique
Pacing Delay
The definition of pacing delay is as fol-
lows. “Deceleration of the project work, by
one of the parties to the contract, because
of a delay to the end date of the project
caused by the other party, so as to maintain
steady progress with the revised overall
project schedule.”
The ‘means and methods’ clause
grants the contractor the right to decelerate
his work in order to lower his/her cost and Figure 8 — Window But-For Technique
• concurrent delay;
• real time delay; and
• pacing delay.
T
each of the project activities should
be determined, and tabulated. rently available delay analysis 1. Al-Gahtani, Khalid S. and Satish
• The delay in project completion techniques, and brought out the B. Mohan, Total Float
date, and the changes in total floats weaknesses of each of them. Of the ten Management for Delay Analysis,
of all noncritical activities because techniques, the but-for and windows 2005 AACE International
of one-day delay events should be techniques are most often used. These Transactions, CDR.16, AACE
recorded. techniques have improved over the earli- International, Morgantown, WV,
• The project schedule should be er techniques, but have some weakness- 2005.
updated each day, including all es. An ideal delay analysis technique has 2. Alkass, S., M. Mazerolle, and F.