Escalator (moving walk)

User manual
(Mechanical part)

NingBo HongDa Elevator Co., LTD

Version number: 201408-Ae1


HD Escalator and HZB moving walk User manual (mechanical part)

Content

Chapter 1 Installation Progress ................................................................................. - 2 -


Chapter 2 Preparation before installation ................................................................. - 3 -
Chapter 3 Hoisting of escalator................................................................................. - 6 -
Chapter 4 Installation of vertical escalator (moving walk) ..................................... - 12 -
Chapter 5 Installation of handrail system of inclined escalator .............................. - 33 -
Chapter 6 Overall debugging .................................................................................. - 36 -
Chapter 7 Preparation before using......................................................................... - 38 -
Chapter 8 Use and maintenance .............................................................................. - 44 -

-1-
HD Escalator and HZB moving walk User manual (mechanical part)

Chapter 1 Installation Progress

Installation procedure of escalator (or moving walk)

Lightering, lifting and locating

Installation of baseboard

Installation and debugging of handrail belt

Installation of inner and outer cover plates Installation of protective device in the entrance of handrail belt

Installation and debugging of electrical part

Overall debugging

Installation of external decoration materials

-2-
HD Escalator and HZB moving walk User manual (mechanical part)

Chapter 2 Preparation before installation

2.1 Familiarity with installation information


Installers shall check and be familiar with the installation technical information and relevant
documents (such as the construction layout drawing, user manual and so on) before construction to
make full preparation for installation.

2.2 On-site investigation


2.2.2 Preparation of shaft way
All inspections must be done in accordance with the requirements of construction design
drawings!
1) Shaft way shall be checked, and horizontal line and center line of the finished floor shall be
clearly marked (done by the employer).
2) Distance between the two terminal supports, and length, depth, lifting height of the pit, length
of shaft way’s diagonal (deviation between the diagonals shall not exceed 40mm) shall be
checked.
3) Opening size of the floor shall be checked.
4) Load bearing capacity of the lifting appliance’s hook on the ceiling shall be checked.

Hook layout

Floor opening
Lifting height

Distance between ends of the whole escalator

Pit length Plumb

Pit height

Deviations between diagonals’ length

shall not exceed 40mm

2.2.2 Organization of personnel and facilities

-3-
HD Escalator and HZB moving walk User manual (mechanical part)

In order to make site qualify the condition of construction, installers shall discuss with
end-user and cooperative parties on personnel cooperation, power and lighting source,
independent grounding, preparation of warehouse and other issues.
2.2.3 Count and storage of materials
1) Before lifting the escalator (or moving walk), accessories such as internal and external cover
plate placed inside, handrail guide rail shall be transported to the temporary warehouse;
2) After unloading the escalator, it is necessary to check if the package is complete to prevent
dust and other sundries from going into the escalator;
3) Installation materials in the wooden boxes shall also be transported to the temporary
warehouse;
4) All accessories shall be counted in line with invoice, stacked and stored properly. Please
contact after-sale service department in time if defects are found in accessories to avoid
affecting installation period.

2.3 When entering into the installation site, installers must wear proper work clothes, shoes
and safety helmet. Safety belt must be fastened to keep from falling when working up high.
Installers must observe safety rules and pay great attention to safety.

2.4 A list of common installation tools

No. Name Specification No. Name Specification

Vacuum chuck of
ripping fence with
1 Combination pliers No. 16 the maximum Pair
lifting force of
100kg
Magnetic Line
2 Diagonal pliers No. 17 5m
hammer

3 Nipper pliers No. 18 Conical hammer 1.2 pound

4 Slot-type Screwdrivers 100mm 19 Oil gun No.

5 Cross-head Screwdrivers 100mm 20 Jointer Set

14~17
Dual-purpose 300
6 17~19 21 Precision level
ring spanner Precision>1mm/m
30~32
14~17
7 Open spanner 17~19 22 Steel square 300
19~22

8 Specialized file 12inch 23 Feeler gauge 0.02~1mm

-4-
HD Escalator and HZB moving walk User manual (mechanical part)

Internal hexagonal 3mm


9 24 Box cutter No.
wrench 5mm
Specialized wire
10 Steel tape 5mm 25 Set
stripper

11 Angular grinder No. 26 Multimeter No.

12 Circlip plier No. 27 Handrail belt hook No.

13 Hacksaw Set 28 Chain block 3000kg

14 Flashlight No. 29 Jack 5000kg

15 Rubber hammer No.

Comment: This tool list is a set of installation and maintenance tools.

-5-
HD Escalator and HZB moving walk User manual (mechanical part)

Chapter 3 Hoisting of escalator


3.1 Hoisting of escalator
3.1.1 Hoisting place

Sling

Ring

3.1.2 Hoisting ways


Integral hoisting Segmental hoisting

3.2 Splicing of truss


3.2.1 Ground splicing

-6-
HD Escalator and HZB moving walk User manual (mechanical part)

3.2.2 Air splicing

3.2.3 Truss splicing

Use soft brush to


clean joint faces!
Tightening torque:
Rust removal!
HT bolt M16: 250Nm
螺栓断裂的
Scale removal! HT bolt M20: 450Nm
Sundries removal! HT bolt M22: 650Nm

Danger of bolts’ breakage! The HT bolt can only be used for once! And only HT bolt of suitable
grade (10.9) can be used!

Lifting must not cause damage to truss and joint! Length of escalator >17m, and lifting must be
connected in air.

Do not forget the locating pin!

-7-
HD Escalator and HZB moving walk User manual (mechanical part)

3.3 Connection of guide rail

Thread plate
Clamping angular part

Thread plate

Thread plate

Angular part

Angular part

Diagram of guide rail connection

1- Hexagon bolt M10×20 2- Lock washer M10

Ø Connect all guide rail of escalator to make sure that the joint is smooth. Jointing clearance
between guide rails of escalator shall be less than 2mm.
Ø After connecting and fixing the guide rails, height difference of guide rail’s face shall be less
than 0.2mm.
3.4 Connection and tension of step chain

Clamp spring

Link plate of connection Interlinkage

-8-
HD Escalator and HZB moving walk User manual (mechanical part)

150~160mm

Notice: Adjust length of springs which are on the


sides of tight vehicle to the required size before
starting escalator. Noise will come out in operation
of escalator if tension frame is not tight, the size
deviation between the left and right tension spring 1mm
shall not be more than 1mm.
connection of cable

3.5 Adjustment of escalator location


l Vertical adjustment

Theoretical A=40mm

Viewing distance A!

-9-
HD Escalator and HZB moving walk User manual (mechanical part)

l Lateral adjustment

Align the central axis with central point!

3.6 Support components


Depth of truss shelf
Base plate beam shall no less than
components 140mm Jack bolt

Notice: measure thickness of base plate components and embedded base plate which is needed by
the ground.
3.7 Horizontal adjustment of escalator
Ø longitude horizontal adjustment

Comb pedal Level

Finished ground

Height adjusting bolt


Adjust by using the height adjusting bolt

- 10 -
HD Escalator and HZB moving walk User manual (mechanical part)

Ø Transverse horizontal adjustment

Level Comb pedal

Step

Place level in the first step which is before comb

Ø Installation and adjustment of intermediate support

Bolt M20×60
Nut M20
Washer 20

Adjusting bolt

Check step above


Straightness of main rail in the
intermediate
intermediate support (300mm
support directly!
length no more than 0.2mm)

3.8 Matters which shall be noticed after placing escalator


1) Interval between angle iron stiffening and three sides of construction pit shall be no less than
20mm;
2) Forbid using cement or other coagulators to connect angle iron stiffening with construction.

- 11 -
HD Escalator and HZB moving walk User manual (mechanical part)

Chapter 4 Installation of vertical escalator (moving walk)


4.1 General
All escalators have passed pilot run, adjustment and test before leaving factory.
4.2 Preparation for installation
The following works shall be done before installing handrail
Ø The whole escalator level has been adjusted as required.
Ø All guide rails of the ladder way have been installed.
Ø Chain of step has been connected.
Ø Protective measures shall be taken in handrail belt to prevent surface being damaged.
4.3 Installation sequence

Install skirt panel

Install step pedal

Check if there are any displacements existing in the installation of glass bracket

Install balustrade with glass panel

Install guide rail of handrail

Install and adjust handrail belt

Install access system of handrail

Install outer cover plate Install inner cover plate

Install floor cover plate

Notice: ensure that joints of all components are flat and smooth for safety.

4.4 Installation of skirt panel

- 12 -
HD Escalator and HZB moving walk User manual (mechanical part)

Seam≤1mm
M6 nut M6 lock washer

Ø Installation of escalator skirt panel Maximum unilateral interval is 4mm,


the maximum sum of both sides is 7mm
M8 very large washer

M8 lock washer

M8 nut

C type
Angled component component

Skirt panel
Connecting bolt components Step

Interval 2±1mm

Ø Installation diagram of moving walk’s skirt panel


Interval between pedal and
skirt panel is 2~4mm

4.5 Installation of step, pedal

- 13 -
HD Escalator and HZB moving walk User manual (mechanical part)

Ø Step installation

Step installation:
Only in tension end station!

ŒPut into steering wall gap!

• Insert step lining!


Ž Check that step is in the center of step
axle!
• Steel sleeve shall be close with lining!
• Fastening steel sleeve shall fasten screw!
‘ Check if the step is tightly fastened!

Ø Pedal installation of moving walk


Screw, spring
Pedal washer

Fixed part of pedal

Pedal installation:
Only in tension
end station!

l Put fixed parts of pedal into chain

plate hole

l Put pedal in

l Use screw to fix pedal!

HT bolt M6*25
l Tightening torque: 12Nm

- 14 -
HD Escalator and HZB moving walk User manual (mechanical part)

4.6 Installation and inspection of glass bracket


Ø For the convenience of transport, glass bracket on the sectioned point of sectional escalator
may be dismantled. Glass bracket on the sectioned point shall be installed firstly, joint seam
between glass brackets shall be no more than 2mm, and inclined plane of glass bracket shall
face to inner side.
Ø In consideration of displacement in the process of transportation, it is necessary to check if
the distances of clamping seats which are at the up, down, left and right ends and glass
bracket are equal, and corresponding adjustment shall be made.

Glass gasket Glass bracket

Distances of up, down, left, right ends are equal

Glass clamping seat

Installation diagram of glass bracket

One for each


clamping position

Place two for the clamping


position which is in the juncture
of ripping fence

- 15 -
HD Escalator and HZB moving walk User manual (mechanical part)

4.7 Installation of glass ripping fence


4.7.1 General
Length of glass ripping fence in incline section is 1798mm, size of the glass ripping fence in
preparation section is decided by the height of escalator. Please refer to the invoice for quantities
of various glasses.
4.7.2 Installation sequence of glass ripping fence

Installation sequence:
ΠGlass ripping fence in lower arc section
•Ž • Glass ripping fence in incline section
• Glass ripping fence in preparation section
‘ Glass ripping fence in upper arc section

Installation sequence diagram of glass ripping fence

Install the glass ripping fence in lower arc section


1) Insert glass ripping fence into pre-prepared glass spacer slowly;
2) Adjust position of the glass ripping fence correctly, and use angle square to make upper
surface perpendicular to glass bracket.
3) Adjust glass ripping fence, use spirit level to make glass substantially perpendicular to the
level, and pre-fasten the glass clamping seat.

Angle square
Spirit level Angle square
Ripping fence in lower
horizontal section

Two horizontal steps Three horizontal steps

- 16 -
HD Escalator and HZB moving walk User manual (mechanical part)

2mm thick rubber


Place 2 “U” rubber strips
blanket
in the connection of
every glass plate

Installation diagram of glass

Reduce or enlarge interval between


ripping fences in straight line section if
seam is not qualified (2~4mm)!

Ø Install the other glasses from bottom to top, and adjust to make the glass seam uniform and
the interval 2-4mm.
Ø Tighten the two bolts in all clamping seats with the tightening torque be 15N·m, then tighten
the nuts on the screw rod.

Pressing plate

Clamping bolt

- 17 -
HD Escalator and HZB moving walk User manual (mechanical part)

4.8 Installation of handrail guide rail of escalator


4.8.1 Tape up
Ø Paste the adhesive tape which can protect glass on the upper surface of glass paneling.
Generally, every escalator is equipped with three tapes.
Firstly, paste tape from the bottom of the front glasses which are in the upper and lower ends to
adjacent glass and to go beyond glass seam for 100mm, then bend the adhesive tape to paste it on
the sides of glass;

Two horizontal steps

300mm
Three horizontal steps

200 mm

Remove the protective film on

the other side of adhesive tape

Fixing

Diagram of pasting adhesive tape

4.8.2 Installation of handrail guide rail

- 18 -
HD Escalator and HZB moving walk User manual (mechanical part)

Œ • Ž ‘

Installation sequence:
ΠEnd support in tension end
• Support in lower curved section
Ž Standard support in straight line
section
• Support in preparation section
• Support in upper curved section
• •
‘ End support in driving end

Ø Positioning the end handrail guide rail

Distance between end


End face’s position
face and skirt panel is on the glass

274mm

Ø Connection and fixing of the handrail guide rail

- 19 -
HD Escalator and HZB moving walk User manual (mechanical part)

Nut GB/T889.1/M4

Connector

Flat, smooth and without burr

Remove redundant
adhesive tape

Screw GB/T819.1/M4×20
Handrail guide rail

Connection diagram of handrail guide rail

Ø After adjusting and finishing all escalators, use knife to remove exposed and redundant
adhesive tape. No seam, burr and distortion existing in the juncture of guide rail.
4.9 Installation of handrail belt of escalator
4.9.1 Installation of handrail belt
Ø Dismantle the skirt support in
the above picture;

Ø Spread the handrail belt and place it into the inner side of the truss

Protected with paper board


Lay down the handrail belt slowly

- 20 -
HD Escalator and HZB moving walk User manual (mechanical part)

Ø Position the handrail belt which is in the return area to make it in the right place;

Install it after finish


the installation of
handrail belt

Ø Use the specialized tool-handrail belt hook to install handrail belt on the handrail support
which is in the upper end of escalator, and ensure that handrail belt doesn’t slip down, pull
handrail belt from top to bottom to make the whole handrail belt installed in the handrail
support.
4.9.2 Adjustment and check of handrail belt
Ø Escalators of two horizontal steps

5
4
3

1-Carrier roller 2-Tension bending components 3- Handrail belt driving friction wheel

4-Handrail belt 5-Roller bending components 6-Pressure belt components

Ø Escalators and moving walks of three horizontal steps

- 21 -
HD Escalator and HZB moving walk User manual (mechanical part)

2
1

5 6

1-Supporting wheel components 2-Handrail belt 3-Roller bending components

4- Tension arc section components 5-Handrail driving friction wheel 6-Pressure belt components

1) Check the running line of handrail belt carefully, especially parts which have smaller
intervals, to ensure that there is no friction between handrail belt and metal parts;
2) Adjust tension bend components and pressure belt components, and tighten the handrail belt.
Ø Pressure belt components and spring preload

About 60mm

Ø Tension components and spring preload of two steps escalator

About 53mm
Adjustable bolt
Control tightness of handrail belt by moving
the tension bending components left and right.

- 22 -
HD Escalator and HZB moving walk User manual (mechanical part)

Ø Tension components and spring preload of three steps escalator and moving walk

About 48mm
3) Reinstall support of skirt board

4) Tightness requirement of handrail: after handrail belt going up for 2-3 laps, free sag in the
central position of the retreating side handrail belt (distance between adjacent carrier rollers
in standard section is 1200mm) is 10-12mm. Handrail belt can go normally when human pull
handrail belt with a force no more than 70kg (in contrast with the direction of handrail belt).

Between every
1200mm

- 23 -
HD Escalator and HZB moving walk User manual (mechanical part)

F~70kg

5) Adjustment of handrail belt deviation

After adjusting handrail belt’s


tightness and driving force, use
detection kit to run escalator and
observe if friction wheel is in the
central of handrail belt’s inner
side.

Ø In order to adjust the upward running deviation, unscrew the adjusting bolt and move roller
bending components towards the opposite direction of the deviation.

Please tighten the


nut after finishing
the adjustment!

Adjusting bolt

Ø In order to adjust the downward running deviation, unscrew the adjusting bolt and move
roller bending components towards the opposite direction of the deviation.

- 24 -
HD Escalator and HZB moving walk User manual (mechanical part)

l Two horizontal steps


Please tighten the
nut after finishing
the adjustment!

Adjusting bolt

l Three horizontal steps or moving walks

Adjust guide
bearing

Adjust the nearest


guide wheel in the
carrier roller to
adjust handrail
belt’s deviation in
downward running.

Notes: Positions of tension bending components and roller bending components have been
adjusted and fixed; generally there is no need to adjust them on the installation site. If
some deviations are caused by delivery or other factors, then professional people can
adjust.

- 25 -
HD Escalator and HZB moving walk User manual (mechanical part)

6) Adjustment of handrail belt in the lower area

Make sure that


guide wheel is
in the center of
handrail belt

Adjust bolt when


escalator runs
downward
Adjust guide
components of handrail
belt when escalator runs
upward

4.10 Installation of handrail’s entrance


Ø 入口触点支架安装
Ø Installation of contact support of the entrance

Make sure that


there is no
friction between
rubber in the
entrance and
handrail belt

GB/T12M8×16 bolt
M8 lock washer
M8 nut

- 26 -
HD Escalator and HZB moving walk User manual (mechanical part)

Ø Panel installation

Left panel

GB/T819.1M4
×12 bolt

Steel nut

Handrail’s entrance has been installed and adjusted in the factory, and left panel is pasted
flatly with skirt panel. Manually check if safety switch works normally: press hard on the entrance
rubber, if safety switch and active plate cannot return to the correct position easily, or can act when
suffering slight pressure, then it needs to be adjusted.
4.11 Installation of inner and outer cover plate of escalator



Ž

Œ
Installation sequence:
ΠCover plate in the lower end
• Cover plate in the lower arc section
Ž Cover plate in the standard straight
line section
• Cover plate in the preparation section
• Cover plate in the upper arc section
‘ Cover plate in the upper end section

Installation diagram of escalator cover plate

- 27 -
HD Escalator and HZB moving walk User manual (mechanical part)



Ž

Œ

Installation sequence:
Œ Cover plate in the lower end • Cover plate in the upper arc section
• Cover plate in the standard straight line section ‘ Cover plate in the upper end section
Ž Cover plate in the preparation section
• 3000mm Standard cover plate (with middle scram mounting seat)

Installation diagram of moving walk cover plate

4.11.1 Installation of clamping strip

Lock clamping strip to edge of the glass support; slightly beat it with a rubber hammer until
clamping strip’s inner groove is completely locked at the edge of glass support. Mind to reserve a
length of 100mm in the escalator entrance, and cut it off after finishing the installation of inner
and outer cover plates of the ends. Seam of clamping strip shall less than 1mm.
4.11.2 Install outer cover plate
1) Install outer cover plate of the lower end firstly, use inner cover plate of the lower end to locate,
then embed outer cover plate of the lower end into the clamping strip with its end aligning with
the end of inner cover plate;

- 28 -
HD Escalator and HZB moving walk User manual (mechanical part)

Inner cover plate of lower end

Two hole center align with


inner cover plate’s end
Ends of inner and outer cover
plates align with each other

2) Slightly beat the cover plate until its edge is completely embedded into the clamping strip;
3) Use the above methods to install other outer cover plates in the sequence which is from bottom
to top. Adjust and finish seams between cover plates with joint clearance no more than 1mm
and height difference of the two cover plates in the seam no more than 1mm.

C type
component
s cover plate
Outer
Supporting angular
Connecting bolt component

4.11.3 Installation of moving walk’s middle scram switch

Dig 2 φ5 holes on
the guide rail of
handrail belt in
accordance with
the hole site in the
mounting plate.

4.11.4 Install inner cover plate


1) Inner cover plate shall be installed and aligned with outer cover plate, and install inner cover
plate of lower end firstly.

- 29 -
HD Escalator and HZB moving walk User manual (mechanical part)

Clamping strip

Inner cover plate

Seam≤1mm

Screw/GB819.1/M4×12

2) Use the above methods to install other inner cover plates in the sequence which is from bottom
to top, front and back dislocation of the inner and outer cover plates shall not be more than
3mm.

Outer cover plate

Seam≤1mm
Clamping strip

Inner cover plate

4.12 Install floor cover plate

Adjust short screw


Nut M10

Adjust long screw


Nut M10

- 30 -
HD Escalator and HZB moving walk User manual (mechanical part)

Adjust supporting surface of end station frame to make


the distance between it and comb plate and finished
floor is 38mm (FOK)!

Floor cover plate 2

Floor cover plate 1

Adjustable bolt components Pattern of


floor cover
plate shall
Frame of floor cover plate align with
pattern of
front plate

Interval between front


plate and floor cover
plate is 6~8mm

2mm interval

Spirit level

Installation diagram of floor cover plate

- 31 -
HD Escalator and HZB moving walk User manual (mechanical part)

1) Weld adjustable bolt and frame of floor cover plate firmly.

Weld the frame to


the adjustable bolt!

2) Cover up the floor cover plate after welding.

- 32 -
HD Escalator and HZB moving walk User manual (mechanical part)

Chapter 5 Installation of handrail system of inclined escalator


5.2.1 Installation sequence of handrail support
Ø Handrail support of lower horizontal section+handrail support of lower bending section→6m
handrail support→3m handrail support→handrail support of preparation section→handrail
support of upper bending section + handrail support of upper horizontal section→handrail
support of upper and lower ends
5.2.2 Installation of handrail support of lower horizontal section

Handrail support of lower horizontal section Handrail support of lower bending section

300

End of skirt panel

Ø Connection of support
l End rotating wheel

Insert locating pin to


locate and fix it

Seam≤1mm

Support connection
l End rotating chain

Installation diagram of handrail support

- 33 -
HD Escalator and HZB moving walk User manual (mechanical part)

Ø Fix other handrail supports in sequence, and then use spirit to check if the end handrail
support is in the same level with handrail support of lower horizontal section.
5.5 Installation of ripping fence

Layout diagram of ripping fence

1- Ripping fence of lower end 2- Ripping fence of lower horizontal section 3- Ripping fence of lower bending

section 4- Ripping fence of standard straight line section 5- Ripping fence of nonstandard straight line section 6-

Ripping fence of 1000mm section 7- Ripping fence of upper bending section 8- Ripping fence of upper horizontal

section 9- Ripping fence of upper end

5.5.1 Installation sequence of ripping fence


Ø Installation of ripping fence of lower bending section

Use sucker to lift ripping fence of lower bending section, press lower edge on the outside of

skirt panel, use angle square to make ripping fence perpendicular to skirt panel, use support and

spring to make lower edge of ripping fence close to skirt panel. Overlap of ripping fence and

handrail profile is about 10mm, and overlap of ripping fence and skirt panel is about 6mm;

- 34 -
HD Escalator and HZB moving walk User manual (mechanical part)

Edge of skirt panel


Angular square
Ripping fence of
Handrail support lower bending section

Pressure plate

Ripping fence

Skirt panel
Support

Ø Install other ripping fences in sequence with interval between ripping fences no more than
1mm.
Ø Install ripping fence of lower horizontal section finally. Adjust interval between ripping fence
of upper horizontal section and the two adjacent ripping fences by adjusting overlap size of
ripping fence of lower end and cover plate of end handrail profile.

Interval≤1mm
Handrail support

Cover plate of end


handrail profile
Interval≤1mm

Handrail belt
Ripping fence of lower
horizontal section
End ripping fence

- 35 -
HD Escalator and HZB moving walk User manual (mechanical part)

Chapter 6 Overall debugging


6.1 General
a) Don’t start if people are in the escalator (or moving walk);
b) Three continuous steps (or pedal) need to be dismantled while commissioning
c) Site protection shall be done before dismantling floor plate or step (or pedal);
d) Only repairing control system can be used to examine running after some steps (or pedal) being
dismantled
e) Overhaul button can be used to change running direction only after steps (or pedal) stop
entirely.
6.2 Preparation work
a) Use a handle to twist into screwed hole of floor cover plate and lift floor cover plate;
b) Remove sundries which are in the step (or pedal) or stuck in the groove;
c) Clean handrail to avoid polluting mechanical transmission parts.
6.3 Electrical pre-test
a) Check power supply (power line, phase sequence, null line, and ground line). Check if power
connection is in accordance with wiring diagram;
b) Check if scram button in the control cabinet and distributing box is reset, if overhaul socket is
covered properly, and connect power switch;
c) Connect overhaul box with control cabinet, use overhaul up or down button to check if the
running direction of escalator (or moving walk) is right, and change two phase connection to
modify if it is necessary.
6.4 Normal running test
a) Disconnect the connection between overhaul box and control cabinet;
b) Use key switch of operation box to turn the key to required running direction to start escalator
(or moving walk)
c) After starting, turn the key to zero position and pull out.
6.5 Stop test of escalator (or moving walk)
a) Normal shutdown (soft-stop): soft-stop is realized by scram switch on the control box;
b) Emergency shutdown: emergency shutdown appears when safety contact is activated.
6.6 Check and lubrication of mechanical parts
a) In machine room which is under escalator, check step axle sleeve and lubrication of step axle,
lubricate them if necessary;
b) When comb plate receives about 70kg horizontal force, safety switch of comb plate shall work;
c) Check whether mesh centers of step (or pedal) and comb is identical or not;
d) Unilateral interval between skirt panel of escalator and step shall not exceed 4mm; sum of two

- 36 -
HD Escalator and HZB moving walk User manual (mechanical part)

sides intervals shall not exceed 7mm;


e) The maximum interval between skirt panel’s lower end surface of moving walk and pedal is
4mm;
f) Check handrail entrance, intervals of handrail belt and guide component shall be roughly equal,
and handrail belt shall not rub guide component;
g) Clean dust on the surface of handrail, use rag which is smeared with some cleaner (gasoline
solution is forbidden) to clean surface of handrail belt forcibly, use dry cloth wipe it again, then
leave it dry for 10 minutes;
h) Lubricating oil shall be inserted into chain link when lubricating step chain (or pedal);
i) Check tension of step (or pedal) chain, tension of the two step (or pedal) chains shall be
uniform.
j) When escalator step is not moving, guide block shall not rub skirt plate.

The final quality checking report:

o Electrical check

o Mechanical check

Cleaning and tail-in work

Clean the following components!

o Step

o Guide rail

o Pit

o Handrail belt

o Handrail

o Remove cushion block in the glass handrail

o Paste mark!

o Check whole appearance of escalator!

- 37 -
HD Escalator and HZB moving walk User manual (mechanical part)

Chapter 7 Preparation before using


7.1 Escalator shall be inspected after installation, debugging and completion, or receiving a major
reformation. The inspection and testing shall be carried out by local competent authorities of
special equipment, and installers shall give cooperation.

7.2 Required documents of national standard including nationally recognized test report of
escalator (moving walk) type, user manuals, construction layout, electrical schematic diagram,
type test report of main components, self-test report of completion acceptance shall be provided
during inspection and acceptance of escalator (or moving walk)

7.3 Register of escalator (or moving walk)


Technical data of escalator (or moving walk) shall be recorded in a register or file, and shall
be recorded when escalator (or moving walk) is put into operation, the latest record of this register
or file shall be kept. Including:
a) Date of putting into operation, feature transformation and alteration shall be indicated in
technical part, general layout and wiring diagram also shall be attached;
b) Inspection and testing reports which are dated and attached comment and accident records
report shall be provided.
The record and file shall be given to those who are responsible for maintenance and those who
carry on checking periodically.

7.4 The parts which are relevant to building interface (self-care parts)
7.4.1 Installation of vertical protective baffle:
1) Some preventive measures shall be taken if building obstacles can cause damages to
personnel.
2) Especially at the floor intersections and the place between escalators which are cross set,
vertical protective baffle with no sharp edges shall be set, height of baffle shall not be less
than 0.3m and the baffle shall extend to lower edge of handrail belt for at least 25mm, for
example: using a set square with no hole.
3) If distance between edge of handrail belt and any obstacles: A≥400mm, vertical protective
baffle is not necessary to be set.
Vertical protective baffle (as set square with no hole) shall be installed in the place which is no
less than 80mm from the edge of handrail belt.
4) Vertical protective baffle (as the set square with no hole) shall be rigidly fixed, but not flexibly
fixed.

- 38 -
HD Escalator and HZB moving walk User manual (mechanical part)

Vertical protective baffle

Vertical protective baffle

7.4.2 Installation of anti-climbing device


1) Place in handrail device shall not bear the normal standing of human.
2) Appropriate measures shall be taken to prevent human from climbing outside of handrail
device if there are any risks of human falling.
To confirm this, climbing device shall be set on the outer cover plate of escalator, the device
is above the ground (1000±50mm) with its bottom crossing with outer cover plate, its
extending length which is parallel to outer cover plate shall be 1000mm at least, and make
sure that there is no place to step on in this range. Height of this device shall meet
requirements of b10 (≥80mm and h10 (25-150mm).
3) Head of exposed fasteners which are used to install climbing device shall be unconventional
one.

- 39 -
HD Escalator and HZB moving walk User manual (mechanical part)

b10

h10
7.4.3 Installation of entrance retention device
1) If human can touch edge of handrail belt in the entrance and cause dangerous situation, such
as falling from handrail device, appropriate protective measures shall be taken. For example:
Ø Set fixed retention device to stop entering into this space.
Ø In the dangerous area, nonfloating rail which is formed by building mechanism shall be
increased to at least 100mm higher than handrail belt, and shall be 80-120mm away
from outer edge of handrail belt.

7.4.4 Installation of retention device


1) When escalator is close to wall and width of outer cover plate exceeds 125mm, retention
device shall be installed at the upper and lower ends to stop human entering into area of outer
cover plate. When escalators are parallel mounted closely and width of their common outer
cover plate exceeds 125mm, retention device shall also be installed.

- 40 -
HD Escalator and HZB moving walk User manual (mechanical part)

2) Head of exposed fasteners which are used to install climbing device shall be unconventional
one.

25~150mm Retention device

120mm max

125mm

Retention device

25~150mm

125mm

7.4.5 Escalator shall provide a minimum free space to prevent collision:


1) Above step of escalator, vertical clear height shall be no less than 2300mm.
2) The vertical clear height shall extend to end of handrail steering end and be applicable to open
areas.

- 41 -
HD Escalator and HZB moving walk User manual (mechanical part)

3) To avoid collision, measuring height h12 from step of escalator shall be no less than
2100mm. When b9≥400, there is no need to comply with the above restrictions. Horizontal
distance b10 between edge of handrail belt and wall or other obstacles shall not be less than
80mm at any circumstances.
4) Vertical distance b12 between lower edge of handrail belt and wall or other obstacles shall
not be less than 25mm.
5) For escalator which is parallel or cross mounted, distance b11 between handrail belts shall
not be less than 160mm.

b10

≥2300mm
b11 b9
h12
b12

7.4.6 Depth metric space: in entrances of escalator’s upper and lower head, it is fully open to
accommodate human.
Ø Width of this area shall be at least distance between outer edges of handrail belt plus 80mm
of each side. Its depth size L shall be at least 2.5m from end of handrail device.

Size of outer edge Size of outer edges of


of handrail belt handrail belt plus
80mm of each side

L≥2.5m

- 42 -
HD Escalator and HZB moving walk User manual (mechanical part)

Ø If width of this area is increased to twice and more as much as sum of distance between outer
edges of handrail belt plus 80mm of each side, and its depth size L is allowed to decreased to
2m. It shall be noted that the open area is part of the whole transport system, and then it
needs to be increased sometimes.

2X (size of outer
Size of outer edge edges of handrail
of handrail belt
belt plus 80mm
of each side)

L≥2m

7.4.7 Safety signs


In order to ensure passenger using escalator (or moving walk) safely, before putting escalator
(or moving walk) into use, signs of operation notice shall be set in appropriate place around the
entrance; it shall contain the following parts:

Bottom Top

- 43 -
HD Escalator and HZB moving walk User manual (mechanical part)

Chapter 8 Use and maintenance


Special techniques are needed in maintenance and service of escalator (or moving walk), only the
company and person who are permitted by the state and with appropriate qualification can
implement maintenance and service.
8.1 Safety protective measures of maintenance
a) In the period of maintenance, repair or inspection and test, protective measures shall be taken
to make sure that escalator (or moving walk) cannot be started without being noticed and
getting permission of professional;
b) When having maintenance, obstacles or sign which says “ongoing maintenance” shall be set
in the upper and lower entrances of escalator (or moving walk);
c) If step (or pedal) needs to be dismantled, only inspection switch can be used to operate;
d) If inspection and repair are happened in the guide rail of escalator (or moving walk) or other
places which may cause damage to human when escalator (or moving walk) starts suddenly,
main power switch must be cut and locked, care shall be given by special personnel or sign
gives notice to ensure personal safety;
e) Do not start escalator (or moving walk) with load.
8.2 Maintenance and maintenance period of escalator (or moving walk)
a) After escalator (or moving walk) put into use for 3 months, a careful inspection and
adjustment shall be taken on important machines and electrical components;
b) Clean of upper and lower machine rooms shall be done each time escalator (or moving walk)
running for half a month;
c) Clean of all roller guide rail shall be done each time escalator (or moving walk) running for 1
month, accumulated oil in oil-water separator of lower machine room shall be cleaned if it is
in the outdoor;
d) Check if all steps are loose or not (clamp ring is loose, step moves left and right) each time
escalator running for 1 month; adjustment and fixation shall be done if they are loose;
e) Check if all bolts of fixed pedals are loose or not each time moving walk running for 1 month,
adjustment and fixation shall be done if they are loose;
f) An overhaul shall be done each time escalator (or moving walk) running for 2~3 years.

No. Item Check method Remedial measures


1 Reducer noise, oil level Check Repair or oil
2 Brake motor, brake band, geared sector Check, functional test Change
3 Auxiliary brake Check, functional test Repair or change
4 Main motor Check, noise test Repair or change
5 Drive chain, chain wheel Check Lubricate and change

- 44 -
HD Escalator and HZB moving walk User manual (mechanical part)

6 Step (or pedal) chain, chain wheel Check Lubricate and change
7 Handrail drive chain, chain wheel Check Lubricate and change
8 Friction wheel or end drive wheel Check Change
9 Step, step accessory ring, pedal Check Clean or change
10 Main axle of step Check Change
11 Guide rail, tangential guide rail, uninstall Check Repair or change
guide rail
12 Handrail belt Check Clean or change
13 Handrail support and guide rail handrail Check Renovate
belt
14 Steering pulley group of handrail belt and Check Repair or change
carrier roller
15 Handrail end drive and steering wheel Check Repair or change
16 Skirt panel Check Adjust or repair
17 Paint components Check Repair and painting make-up
18 Control cabinet Check, functional test Repair or change
19 Maintenance control box Check, functional test Repair or change
20 Key switch and scram button Check, functional test Repair or change
21 Safety device Check, functional test Adjust or repair
22 Ground terminal and static brush Check Repair or change

8.3 Disassembly of floor plate


Floor plate shall be dismantled if maintenance personnel want to enter into the machine room of
escalator (or moving walk). Use special to screw into screwed hole which is in the surface of floor
plate to lift floor plate. Also check if reinforcing rib of floor plate has welding off, overall
deformation or damage.
8.4 Disassembly of step (or pedal) chain
Step (or pedal) chain needs to be dismantled if step (or pedal) chain is over worn, several rollers
are damaged or escalator (or moving walk) needs overhaul. In unnecessary circumstance, step (or
pedal) shall not be dismantled generally.
8.4.1 Disassembly of step (or pedal) chain (build-in roller)

Figure10-3 Disassembly diagram of step chain

- 45 -
HD Escalator and HZB moving walk User manual (mechanical part)

1-Axis ring 2- Connecting chain plate 3-Roller 4-Long pin (step chain) 5-Short pin 6-Sleeve
a) Deliver the step (or pedal) chain segment which needs to be dismantled to lower machine
room;
b) Use circlip plier to take down two axis rings in the connecting chain plate;
c) Dismantle connecting chain plate;
d) Beat slightly the chain plate of short pin, and take it out;
e) Use a special axis to beat sleeve and separate it from the chain;
f) Take roller out.
8.4.2 Disassembly of roller in the step chain (external roller)

Figure10-4 Disassembly diagram of step chain


1-Long axis 2-Bolt M5*20 3-Short axis 4-Clamp ring 5-Axle sleeve 6-Spring pin
7-Roller 8-Chain plate 9-Axis ring 10- Crank roller 11-Pin
a) Deliver the step chain segment which needs to be dismantled to lower machine room;
b) Dismantle upper step of step axis
c) Dismantle two bolts M5*20, move long axis to one end, move short axis, dismantle long axis;
d) Dismantle spring pin and short axis;
e) Use drawing die to pull roller out;
f) Use moulding die to press new step roller in its place
g) Load short axis, spring pin and long axis, use bolt to fix long axis;
h) Load step.
8.5 Tension check of step (or pedal) chain
Check step (or pedal) chain in lower machine room of escalator (or moving walk), pressure spring
shall be compressed to proper length X: 150~160mm.
Tension of two step (or pedal) chains shall be uniform, adjust length of two springs properly, to
ensure the intimacy of escalator. Intervals between two contacts of safety protective switch and
flitch shall be adjusted according to the drawing.

- 46 -
HD Escalator and HZB moving walk User manual (mechanical part)

Figure10-5 Diagram of tension end


8.6 Lubrication of step (or pedal) chain
Lubricate manually the step (or pedal) chain at the first time of using escalator (or moving walk)
after installation. This work shall be done in the lower machine room. Check and operate to make
escalator (or moving walk) move upward, use oil can and brush to lubricate chain piece, and
prevent roller contacting oil as far as possible.

Oil

Lubricate step chain!


Don’t oil chain roller

Figure10-6 Diagram of oiling place


1-Outer chain plate 2-Inner chain plate

Oil must be added to the junction of step axis and axle sleeve!

8.7 Tension and lubrication of main drive chain


When escalator (or moving walk) has no load, main drive chain shall have a sag of 5~10mm. Or
the four bolts in the fixed traction machine can be loosened, use wrench to turn tension bolt to
adjust the tension degree of drive chain and then lock screw tightly. Inspection control makes
escalator (or moving walk) move downward, oil can or brush is used to lubricate main drive chain.
8.8 Tension and lubrication of handrail drive chain
Handrail drive chain is between main axis of step (or pedal) drive and main axis of handrail. After

- 47 -
HD Escalator and HZB moving walk User manual (mechanical part)

dismantling 4 steps (or pedals), move opening to front of upper comb plate and use this opening to
check or tighten drive chain. Loosen eight fixed bolts of flange bearing in the handrail belt drive
axle, and adjust left and right tension bolts uniformly to make sag of handrail drive chain which
has no load is 5~10mm, then tighten fixed bolt.
After dismantling 3 steps (or 6 steps), move opening to upper part of handrail drive chain, shut off
power, and use brush to lubricate handrail drive chain.
8.9 Tension and lubrication of end drive chain of handrail belt
Use bolt to adjust heights of two transitional chain wheels to adjust tension degree of end drive
chain of handrail belt. Make chain sag keep 5~10mm in no-load condition and tension degree of
two left and right chains keep uniformly.
Inspection control makes escalator move upward, and oil can or brush is used to lubricate chain.
8.10 Check and lubrication of step guide block
Check friction condition of step guide block in lower machine room of escalator, guide
components must be changed if they are damaged seriously (wearing loss reaches 1.2mm) because
this will make step hit guide rail and rub with skirt panel also. Lateral interval between skirt panel
and guide components shall be no more than 0.5mm, if necessary, you can adjust skirt panel or
correct step which has changed its place. Add lubricating grease into groove which is in the front
of step guide block.
8.11 Inspection of oil level of reducer
Pull oil scale out to check oil level. Oil shall be added within the scale range of oil scale if it is
necessary. Profession shall carry out maintenance if there is an oil leakage in reducer.
8.12 Inspection of auxiliary brake
After inspection and adjustment, all the moving parts of auxiliary brake shall move correctly,
flexibly, reliably; interval between drop pawl and face of brake block is generally about 10mm in
normal condition.
Pull rod
Drop pawl

Use lock nut to ensure


activity of electromagnet

Electromagnet

Flexible connection Brake block Chain wheel Spring


Structure diagram of auxiliary brake

- 48 -
HD Escalator and HZB moving walk User manual (mechanical part)

8.13 Maintenance of step (or pedal) guide rail


Step (or pedal) guide rail shall be cleaned completely. Cleaning work is finished in the opening of
step (or pedal). At the moment, inspection switch shall be used to give staged operation of
escalator (or moving walk), protective button and main power switch shall be stopped while
cleaning.
8.14 Clean of handrail belt
Use rag which is stained with few handrail belts cleaner to clean surface of handrail belt till the
surface shines, then use a dry rag to rub it dry.
8.15 Maintenance of safety device
Check sensitivity and reliability of safety device frequently, adjust position of safety switch if it is
necessary, and change unreliable safety switch timely.
8.16 Summary sheet of lubrication

Period
No. Lubrication parts Grease code and name Drain period
(month)
VG460 EP industrial gear 1 year (half a year
1 Host reducer 1/2
oil for the first time)

2 Pin point of brake L-AN 68 1/2

Calcium-base lubricating
3 Pinion point of belt brake 1
grease
Automatic lubricating device (if
4 L-AN 68 1
any)

5 Step (or pedal) chain L-AN 68 1/2

Sprocket alveolus of step (external Calcium-base lubricating


6 2
roller) grease

7 Main drive chain L-AN 68 1/2

8 Handrail drive chain L-AN 68 1/2

End drive chain of handrail belt (if


9 L-AN 68 1/2
any)
Rotor (or joint) point of auxiliary Calcium-base lubricating
10 1
brake (if any) grease
Calcium-base lubricating
11 Roller point of tension end 3
grease
Rotor point of step (or pedal) Calcium-base lubricating
12 3
collapsing protective device grease
Calcium-base lubricating
13 Step guide block 1
grease

- 49 -
HD Escalator and HZB moving walk User manual (mechanical part)

Conclusion

The copyright of this manual belongs to NingBo HongDa Elevator Co., Ltd.
Prohibit unauthorized reprint, copy of part or all of this manual.

For description in this manual, the content may be changed for improvement of
product; we will not notice, please understand.

The company strives for perfection in the description of this manual. Please
contact with our Technology Center if you find any doubts or mistakes in this manual.