Professional Documents
Culture Documents
1 ROOF CATCHMENT
1.1 Preparation and Installation of gutter
1.2 Preparation and Installation of downspout
1.3 Installation of screens
1.4 Cleaning of roof catchment
3 WATERING POINT
3.1 Excavation
3.2 Preparation of foundation
3.3 Preparation and installation of rebars and forms
3.4 Installation and installation of rebars and forms
3.5 Installation of plumbing fixtures
3.6 Concreting
3.7 Removal of forms
3.8 Finishing
3.9 Site Cleaning
I.D. UNIT COST TOTAL COST
DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
1 WELL REHABILITATION
1.1 Deepening of well by digging
1.2 Well lining
1.3 Well cleaning
1.4 Pumping test
1.5 Preparation of well head, cover, pumpstand and apron with gutter
1.6 Preparation and installation of rebars and forms
1.7 Concreting
1.8 Removal of forms
1.9 Finishing
3 PUMP INSTALLATION
3.1 Handpump
3.2 Electric pump
5 TRANSMISSION PIPELINE
5.1 Trenching
5.2 Pipelaying
5.3 Installation of valves,air vents, drains,breakpressure tanks
5.4 Backfilling (except at joints)
5.5 Construction of pipe supports and thrust blocks
5.6 Construction of valve boxes
7 WATERING POINT
7.1 Excavation
7.2 Preparation of foundation
7.3 Preparation of rebars and forms
7.4 Installation of rebars and forms
7.5 Installation of plumbing and fixtures
7.6 Concreting
7.7 Removal of Forms
7.8 Finishing
7.9 Site cleaning
9 SYSTEM DISINFECTION
I.D. NO DESCRIPTION UNIT QTY
1 WELL CONSTRUCTION
1.1 Clearing and set up rig
1.2 Drilling
1.3 Well cleaning
1.4 Preparation of casing and screens and casing
1.5 Well cleaning
2 WELL DEVELOPMENT
4 PUMPING TEST
5 PUMP INSTALLATION
5.1 Handpump
5.2 Electric pump
7 TRANSMISSION PIPELINE
7.1 Trenching
7.2 Pipelaying
7.3 Installation of valves,air vents, drains,breakpressure tanks
7.4 Backfilling (except at joints)
7.5 Construction of pipe supports and thrust blocks
7.6 Construction of valve boxes
11 SYSTEM DISINFECTION
UNIT COST TOTAL COST
GRAND TOTAL
MATERIAL LABOR MATERIAL LABOR
UNIT COST
I.D. NO DESCRIPTION UNIT QTY
MATERIAL
SPRING DEVELOPMENT
1 SPRING INTAKE BOX CONSTRUCTION
1.1 Cleaning the area and digging
1.2 Rechanneling/ diverting of spring flow
1.3 Preparation of foundation
1.4 Stabilization of uphill face of excavated pit
1.5 Preparation of rebars and forms
1.6 Installation of rebars and forms
1.7 Installation of plumbing fixtures
1.8 Concreting
1.9 Removal of forms
3 WATERING POINT
3.1 Excavation
3.2 Preparation of foundation
3.3 Preparation of rebars and forms
3.4 Installation of rebars and forms
3.5 Installation of plumbing and fixtures
3.6 Concreting
3.7 Removal of Forms
3.8 Finishing
3.9 Site cleaning
4 TRANSMISSION PIPELINE
4.1 Trenching
4.2 Pipelaying
4.3 Installation of valves,air vents, drains
4.4 Backfilling (except at joints)
4.5 Construction of pipe supports and thrust blocks
4.6 Construction of valve boxes
7 SYSTEM DISINFECTION
UNIT COST TOTAL COST
GRAND TOTAL
LABOR MATERIAL LABOR
I.D. NO DESCRIPTION UNIT QTY
WATER SOURCE DEVELOPMENT
1 Well Construction
1.1 Clearing and set up rig
1.2 Drilling
1.3 Preparation of casing and screens
1.4 Well cleaning
1.5 Installation of screens and casing
1.6 Well cleaning
1.7 Well Development
1.8 Power installation/connection
1.9 Pumping test
2 Installation of pump
2.1 Construction of pumphouse
3 TRANSMISSION PIPELINE
3.1 Trenching
3.2 Pipelaying
3.3 Installation of valves,air vents, drains
3.4 Backfilling (except at joints)
3.5 Construction of pipe supports and thrust blocks
3.6 Construction of valve boxes
5 DISTRIBUTION PIPELINE
5.1 Trenching
5.2 Pipelaying
5.3 Installation of valves,air vents, drains
5.4 Backfilling (except at joints)
5.5 Construction of pipe supports and thrust blocks
5.6 Construction of valve boxes
6 SERVICE PIPELINE
6.1 Trenching
6.2 Pipelaying
6.3 Backfilling (except at joints)
6.4 Construction of pipe supports and thrust blocks
9 SYSTEM DISINFECTION
UNIT COST TOTAL COST
GRAND TOTAL
MATERIAL LABOR MATERIAL LABOR
I.D. NO DESCRIPTION UNIT QTY
1 SPRING INTAKE BOX DEVELOPMENT
1.1 Clearing the area and digging
1.2 Rechanneling/diverting of spring flow
1.3 Preparation of foundation
1.4 Stabilization of uphill face excavated pit
1.5 Preparation of rebars and forms
1.6 Installation of rebars and forms
1.7 Installation of plumbing fixtures
1.8 Concreting
1.9 Removal of forms
2 Gravel packing and backfilling of uphill side of intake box
2.1 Construction of draining canal
2.2 Digging of run-off diversion trench
2.3 Building of fence
2.4 Site cleaning
3 TRANSMISSION PIPELINE
3.1 Trenching
3.2 Pipelaying
3.3 Installation of valves,air vents, drains
3.4 Backfilling (except at joints)
3.5 Construction of pipe supports and thrust blocks
3.6 Construction of valve boxes
5 DISTRIBUTION PIPELINE
5.1 Trenching
5.2 Pipelaying
5.3 Installation of valves,air vents, drains
5.4 Backfilling (except at joints)
5.5 Construction of pipe supports and thrust blocks
5.6 Construction of valve boxes
6 SERVICE PIPELINE
6.1 Trenching
6.2 Pipelaying
6.3 Backfilling (except at joints)
6.4 Construction of pipe supports and thrust blocks
9 SYSTEM DISINFECTION
UNIT COST TOTAL COST
GRAND TOTAL
MATERIAL LABOR MATERIAL LABOR
I.D. NO DESCRIPTION UNIT QTY
1 INTAKE STRUCTURE CONSTRUCTION
1.1 Construction of diversion wall (mound, dike)
1.2 Excavation/dredging
1.3 Preparation of foundation
1.4 Preparation of rebars and forms
1.5 Installation of rebars & forms
1.6 Installation of plumbing fixtures
1.7 Concreting
1.8 Removal of forms
1.9 Site cleaning
4 TRANSMISSION PIPELINE
4.1 Trenching
4.2 Pipelaying
4.3 Installation of valves,air vents, drains
4.4 Backfilling (except at joints)
4.5 Construction of pipe supports and thrust blocks
4.6 Construction of valve boxes
6 DISTRIBUTION PIPELINE
6.1 Trenching
6.2 Pipelaying
6.3 Installation of valves,air vents, drains
6.4 Backfilling (except at joints)
6.5 Construction of pipe supports and thrust blocks
6.6 Construction of valve boxes
7 SERVICE PIPELINE
7.1 Trenching
7.2 Pipelaying
7.3 Backfilling (except at joints)
7.4 Construction of pipe supports and thrust blocks
10 SYSTEM DISINFECTION
UNIT COST TOTAL COST
GRAND TOTAL
MATERIAL LABOR MATERIAL LABOR