Professional Documents
Culture Documents
Page
1.CONSTRUCTION METHOD STATEMENT …………………………. 1
1.1 Scope of Works………………………………………………… 1-2
2.WORK FLOW OF SANITARY/PLUMBING WORKS……………… 3-5
3.METHODOLOGY OF INSTALLATION FOR PLUMBING PIPES
AND FITTINGS ……………………………………………………………. 6
3.1 Sewer/Vent/Storm/Condensate Pipes …………………… 6
3 . 2 Cold Water Line Pipes (BI/GI Pipes)… … … … … … … … … … … … … . . 6
3 . 3 Hot Water Line Pipes Riser/Down feed/Distribution (PPR Pipes)…..... 6
3.4 Sewer/Storm Pipes (HDPE Pipes)……………………….. 7
3.5 Roughing-ins Hot & Cold Water Lines (PPRPipes).. 8
3.6 Pipe Hanger Installation……………………………………. 8
3.7 Screw Fittings installation………………………………… 8
3.8 Installation Method of Valve with Flange End
Connection……………………………………………………….. 8-9
3.9 Valve with Screw Connection Installation ……………. 9
4. TESTING AND COMMISSIONING……………………………………. 9
4.1 Scope of Works…………………………………………………. 9
4.2 Reference Documents……………………………… ………… 9-10
5. METHODOLOGY OF TESTING FOR SANITARY SEWER
SYSTEM……………………………………………………………. 10
6. METHODOLOGY OF TESTING FOR WATER LINE SYSTEM… 11
7. METHODOLOGY OF TESTING FOR INSTALLED PLUMBING
FIXTURES……………………………………………………… 12-14
8. METHODOLOGY OF TESTING FOR DISINFECTION OF
WATER DISTRIBUTION SYSTEM AND WATER
TANKS……………………………………………………………… 15
9. METHODOLOGY OF TESTING FOR FLOW TEST………………. 16
10. SEALANT APPLICATION…………………………………………… . 17
11. SYSTEM TURNOVER………………………………………………… . 17
12. REFERENCES AND STANDARDS………………………………… 18
1. CONSTRUCTION METHOD STATEMENT
Page 1 of 18
o Installation of shower valve, head and faucet.
o Installation of washing machine faucet.
o Installation of urinals.
o Installation of floor and shower drain.
o Installation of floor cleanout.
o Installation of grease trap, kitchen sink and accessories.
o Installation of balcony drain.
o Installation of water meter and accessories.
o Installation of pressure reducing valve and accessories.
o Functionality and flow testing of fixtures shall be done to assure that it functions
properly.
o After all installations and testing, final paint shall immediately follow by their
designated color (Sanitary – Black / Plumbing – Blue) and in-house punch
listing shall be conducted.
o Installation of all Pumps (sump pump, elevator pump, transfer pumps & booster
pumps)
o Installation of controllers & other accessories.
o Start-up procedures
o Rectification of defects, if any.
o Punch listing
o Installation of Bladder Tank
o Installation of Gate Valves
o Tagging of Normal Closed & Normally Open
Page 2 of 18
2. WORK FLOW OF SANITARY / PLUMBING WORKS
Issued Construction
Plan/Proposed Shop
Drawing
Submit / Resubmit
proposal
Pipe Spool
Pipe Sleeve/Stub out Installation
Installation (Pump Room)
Page 3 of 18
Layout of Cold Water Line (Riser, Layout of Soil, Waste, Vent Line
Downfeed & Roughing-ins) (Stacks & Branch line)
Installation of
Installation of Installation of
Storm Drainage
Soil, Waste, Vent Cold Water Line
Line
Repair
Installation
NOT APPROVED
APPROVED
Page 4 of 18
Installation of Installation of
Installation of Installation of
Installation of Pumps & Elevated Water
Plumbing Valves &
Drains Controller (By Tank
Fixtures Accessories
others) (By others)
Functionality Testing
Potability Testing
Repair
Installation
Testing &
Commissioni
ng
System
Turnover
Page 5 of 18
3. METHODOLOGY OF INSTALLATION OF PLUMBING PIPES AND FITTINGS
Page 6 of 18
3.4 Sewer/Storm (HDPE Pipes)
Pipe size 4’’(DN 100) and above sizes shall be butt welded. Pipe shall be welded
only by special welding machines produced specially for HDPE welds.
Welding sections shall be free of debris, dust, oil etc. in order to have a qualified
penetration in the bonding beads.
Welding machines shall be energized from the existing power system or
generators. The power of the machine shall be minimum 4 kW. Welding units are
generally 220/240 Volts-50 Hz.
o To make the welding, pipes shall be installed on the welding units by clamps
specially designed for holding the pipe in position.
o By the skid mounted shaving units (trimmer), the bevels of the pipe shall be
shaved (trimmed) to make the surface smooth and clean.
o Heating mirror (iron) shall be energized to the required welding temperature.
(See attached butt welding parameters data sheet.
o Shaving units shall be removed between the pipes and eccentricity shall be
controlled to make sure that the pipes are in the same axis.
o Teflon (or Silverstone) coated heating iron shall be placed between the
pipes and pipes shall be heated until they reach the welding temperature.
(See attached butt welding parameters data sheet).
o Remove the heating iron and push the pipes to each other, under a pressure
of 0,18 Mpa to 0,22 Mpa by a special lever operator which is placed on the
welding unit. Pulling apparatus to push the pipes are operated manually or
by hydraulic power and the type depends on the pipe size.
o Pressure shall be applied until having the correct size of the weld seam
thickness according to project requirements. Weld bead thickness and width
shall be controlled by special thickness and width gauge.
o Pipes shall be kept under that pressure until the cooling period of the weld
is finished according to the requirements
o Under rainy and windy conditions, welds shall be protected from the effect
of the bad weather conditions. A sheltered or tented area is recommended
under heavy weather conditions. If the required protective conditions are not
supplied, the welding work will not be done.
Page 7 of 18
3.5 Roughing-ins Hot & Cold Water Line Pipes (PPR Pipes)
o Pipe layout as required by approved plumbing plan.
o Pipe cutting, assembly and jointing by the use of fusion machine.
o Provide provision for Hydro testing.
Page 8 of 18
o Connect the valve with the pipe flange. The pipe flange shall be square with
the associated pipeline.
o When the valve is in proper position, install the bolts into the holes. Tightening
the nuts one by one evenly. Repeat the above steps for the other.
The main task of the method statement is to test and know the standard
procedure of testing. Leakage of all water supply and distribution system,
drains, waste, sewer and venting system plus pressure testing and
disinfection of the water supply and distribution system, testing for leakage
and disinfection of water tanks and test run of transfer, booster &sump
pumps and other equipment under Plumbing Works
According to the construction process, quality and safety measures shall
be confirmed between Tritech Macrosystem Inc. and General Contractor.
Page 9 of 18
4.2 REFERENCE DOCUMENTS
For standard Pressure or allowable leakage per 100 joints per inch of pipe
diameter at pressure coming from General Specification for Plumbing and
Sanitary System: Aside from that all the methodology formed are based
on actual procedure with corresponding standards by the consultant for
testing.
➢ Material Submittals
➢ Approved Construction Shop Drawing (CSD)
➢ Approved For Construction Drawing (FCD)
Page 10 of 18
o Failed – if the level of water is different with its initial reading, with
tolerance of 3 cm.
If failed the testing.
o Inspect all the connection of fittings to fittings and fittings to pipe
whether it does not intact with each other, or if the pipes or fitting
have cracked or damaged immediately drain the water and repair.
Then fill it again with water
o After passing the leak test, it will immediately tap the system in
sanitary riser.
Handover
o After satisfies everything and passed the test, we can now
proceed to handover of tested system with corresponding
signatories in this activity.
Page 11 of 18
o Passed – if the pressure is the same with its initial reading
o Failed – if the pressure is different with its initial reading, with
tolerance of 2 psi.
o If failed, locate the leak and repair until such the pressure will
maintain.
Checking of Pipes and Fittings
o After the completion of the test all exposed pipes, fittings, valves,
Handover
The work area is for all the fixtures placed inside of toilets. Application will be
carried out as a subsection of the installation.
Water Closet
o Flushing of Water.
o Observation.
Page 12 of 18
Fixtures Testing tool Testing Medium Water Head Permitted Holding /
Head Loss Draining Time
Water Closet Stop watch Water / Toilet Paper n/a n/a 15 sec
o If the draining of water is less than or exactly with the allowable factor
mentioned in the above table, test will be completed; if not, repeat the
o Drain the water by removing the plug and get the time until it drains.
o Record the draining time of medium according to the above table with
Page 13 of 18
Shower Drain / Floor Drain
Urinal
Preparation of necessary equipment and modules.
e. Listing of fixtures showing exactly where it is installed, as agreed with
Page 14 of 18
8. METHODOLOGY OF TESTING FOR DISINFECTION OF WATER
o Clean the water storage tank (ELEVATED Water Tank) after all works
o From the main water supply line fill the water tank with water to its
volume of water
o Supply water through the elevated water tank to each unit per floor
o Drain the water from the supply of each unit from fixtures
o Collect water sample from upper, middle, lower part of water supply
of the building if it the same by each other and test the water if it is
o Repeat supplying water to each unit the water cleared and approved
Page 15 of 18
9. METHODOLOGY OF TESTING FOR FLOW TEST
o Preparation of Fabricated Drain Plug.
o Tag the pipe with a hydro testing certificate or either a caution sign and
place it nearby informing that there is ongoing hydro testing in that
particular area.
o Plugging of drain plug to the end of PVC Pipe.
o Checking of the slope of the PVC pipe.
o Provide Table tennis ball(ping-pong) in preparation for the flow test.
o Upon preparation, drain the water from the pipe after being used by the
gravity test.
o Make sure that the water inside the pipe is drain by cutting off the drain
plug.
o Hold and point the ball against the opening of the lateral pipe where the
starting point of the flow begun.
o Release the ball with five gallons of water until such that the ball will
come out of the pipe.
o Filling of water shall then be repeated until the ball will come out at
the end of the pipe.
o Observation.
o The ball is expected to come out of the pipe after being filled with
water and should be declared passed.
o -If Failed: the flow test will only be failed if there is no water flowed out
together with the ball, if this happen rechecked the sloping of the pipe
and fittings and repeat the testing.
o After satisfies everything and passed the test, we can now proceed to
handover of tested pipe with corresponding signatories in the flow test
activity.
o Take photo of the installation and testing for documentation and
proceed to backfilling.
Page 16 of 18
10. SEALANT APPLICATION (PLUMBING FIXTURES)
For sealants in the bathroom, the preferred sealant application is by
caulking gun. Sealant in a tube or a silicone-based product is very
easily dispensed through the use of a caulking gun. The sealant is
applied in a very fine bead by moving the caulking gun slowly and
steadily along any cracks or gaps that are to be filled. This type of
sealant dries rapidly and clean-up is easy.
Prepare the area that needs to be sealed.
o This means ensuring that the area is free of dirt and grime, removing
any left-over old sealant and making sure that the entire area is clear
ready for you to get started.
Apply the sealant.
o Depending on the type of sealant you use there are lots of different
ways to apply it. You might need a sealant gun, or the sealant might
come in a tube so you can apply it directly. Just make sure to follow
the instructions.
Smooth the sealant.
o You can do this as you go along with either your finger or a sealant
smoothing tool.
Let it dry.
o Leave it to dry for the time specified by the instructions.
Page 17 of 18
12. REFERENCES AND STANDARDS
o Technical Specifications for Plumbing and Drainage Services Project No.
P1102 – MEP Philippines Building Services Inc.
o The Philippine Society of Environmental and Sanitary Engineers (PSEnSE)
o Revise National Plumbing Code of The Philippines
o Philippine National Building Codes
o The Rules and Regulations of Local Authority
o British Standard Institution
o NFPA 90A
o Plumbing and Drainage Institute
Page 18 of 18