PROJECT:
PROPOSED G+M OFFICE, WAREHOUSE AND ALLIED SERVICES
ON PLOT NO: 5320248 DUBAI INDUSTRIAL CITY, DUBAI –
UAE.
The contractor reserves the right to adopt the methods used according to
the site needs and conditions and if required this method statement will
be revised and re-submitted for review and approval (if any)
PURPOSE;
This Method Statement is applicable for the erection work of the steel
structure only.
The following shall be checked and provided before the arrival of the steel
to the job site.
Correct foundation positions with respect to the building lines and bench
marks
The anchor bolts positions have been checked after the concrete has been
poured
STORAGE;
Each place of steel should be marked and identified as per drawing before
sending to site
SHEETS STORAGE
The bundles of sheets shall be elevated above the ground with one end
higher than the other to allow water drainage. There shall be air
circulation spaces between the bundles and the whole stack should be
covered using a tarpaulin in times of rain or high humidity
This practice when followed helps protect the sheets if keep in prolonged
storage
ERECTION;
Prior to beginning the erection of any steel structure, the contractor shall
develop a detailed steel erection plan, includes, risk assessment,
temporary supports, and erection equipment used and the sequence of
erecting of these structures, and the plan shall be submitted to the
consultant engineer for approval
A steel erection contractor shall not start steel erection unless ensuring
that concrete has attained and has sufficient strength to support the loads
imposed during steel erection, and obtains approval of the consultant
engineer according to the project specifications
The contractor shall provide his employees with all necessary personal
protective equipment and shall ensure their effective use
Ensure all cranes and lifting tackles are thoroughly tested and approved
Third party as per national regulations and certificates available at site
Ensure that all operators are licensed trained and competent as per
national regulation
If possible visibility of the lost and rigger and operator is not feasible
proper communication facilities must be provided
Ensure a safe working platform with proper hand rail and intermediate
rail
Ensure all elevated working areas have proper hand barriers/hand rail all
around and install intermediate rails where employees need to carry out
then works in a crouching position
Ensure employees use proper fall arrest system such as full body harness
and hood the harness to a proper anchorage point wherever fixing hand
rails is not practicable
Train employees on work height safely and the use of fall arrest system
Don’t lift any erection Steel materials, MEWP must be only used for
lifting working personals.
The columns for the braced bay base plate shall be set, base plates shall
be shimmed and anchor bolts & nuts shall be tightened sufficiently to
prevent columns from rocking
The rafters shall be raised in to position between the columns, the beam
shall be held in position with hoisting equipment while required bolts are
installed through the column splice plate, the bolts shall be tightened to
snug fit
The rafter shall be tied with cables extending lengthwise of the building,
the bracing shall be located in the center near the ridge, quarter of the
purlin in between are installed for permanent bracing, the temporary
bracing between the erected beams shall be released, the remaining roof
purling at every purling location shall be placed
Before proceeding further, the first bay shall be made plumb and square,
temporary braces shall be used to pull the columns into plumb, all anchor
bolts eave strut bolts and columns to beam bolts shall be fully tightened
SHEETING;
Use a chalk line for accurate drilling and screwing. This gives better
appearance and less risk of leakage due to mis drilling
At the end of each working day clean the roof with a soft brush, sweep off
old drill bits, pop reverts, sward from drill or cutting. These items can
cause rusting if they are not removed
When walking on the roof, do not stand on high ribs; stand only on the
low ribs, preferably over the purlin line. Standing on the high ribs can
cause severe damage which could lead to possible leakage. Not that stitch
crews are required at side laps on roof sheets
Do not walk on sky lights sheets if any, mark out the sheeting along the
length of the building, this will give the correct overlaps and avoid creep
Mark the notch as per cover width as an aid to keeping the correct sheet
coverage, take note of the starting dimensions’ shown on the erection
drawing, proceed with roof fixing from valley from valley gutter to ridge.
Direction of erection shall be as per drawing.
Final Check
All bolts and place and high strength bolts tightened to correct tension
LOYAL BUILDING CONTRACTING LLC
Check that roof and gutter are clear or debris and ferrous metals