1. SCOPE OF WORK
This document describes Construction Procedure pertaining to the activities
associated with the installation of Structured Cabling System Works at SM Mega
Tower. And include the furnishing of all materials, tools and equipment required
to complete the activity.
This document shall be read in conjunction with the relevant Specification,
Engineering Standards & drawings, Industry codes and any other additional
requirement as set forth by the Consultant.
The scope of work is for Chipping Works only.
2. REFERENCE DOCUMENTS
a. Lists of Forms
b. FCD Plan/Specification
c. Approved Materials
3. SEQUENCE OF WORKS
a) Determine the structure that would be affected on the chipping activity.
b) With reference to the approved shop drawing, mark the area to be chipped.
c) Outlined the portion of concrete to be chipped off by saw cutting or grinding at both
sides.
e)
5. SAFETY PRECAUTIONS
8.1 Housekeeping
Prior to installation make sure that the area is free from cluttered materials to
avoid any unwanted incident that may cause harm to the installation of EMT pipe
or damage to property.
Conduct housekeeping before and after works. Maintain good housekeeping during
installation.
Keep the staging area and working area free from scattered materials.
Ensure that electrical wires during installation are secured to avoid tripping hazard.
Follow the 5S procedure for good housekeeping.
Coordinate to the General Contractor for the procedure of waste disposal and
temporary staging area for generated waste.
Project In-charge, Safety Officer and Foreman on site shall conduct daily toolbox
prior to start of daily work to provide proper instruction and to plan on how to
execute the job properly and safely.
All workers are required to join the daily toolbox meeting and sign on the daily tool
box attendance.
8.5 Access
Workers will use the A type ladder or approved design of scaffolding. When
climbing up and down, always follow the 3 point contact rules and always use the
hand rail of scaffold (2 hands I foot, 1 hand 2 feet).
8.7 Supervision
In order to ensure that the workers are performing the job safely, full supervision of
foreman/ supervisor, safety officer and or assigned team leader are required to
ensure that all workers are executing the job safely.
All workers carrying out the installation are required to wear basic Personal
Protective Equipment (i.e. Hard hat with chinstrap, Goggles, Visibility Vest, and
Safety Shoes).
All workers expose to excessive noise are required to wear ear plug or ear muff .
Wear hand gloves when handling materials or any object with sharp edges.
Face shield is required if the workers are performing cutting and grinding activity.
Safety goggles and dust mask are required during drilling of floor to protect the
eyes from flying particles and to avoid dust inhalation.
When the workers are performing his activity from 1.8 meters or above, full body
harness with double lanyard is required.
7. QUALITY ASSURANCE/CONTROL
Inspections
7.1 The execution of work will strictly follow the project quality procedure.
a. Work permit and inspection test plan
b. Test requirements and as per plan specifications or contract requirements
APPENDICES
Appendix A – Job Hazard Analysis