COMMENTS RESOLUTION SHEET

Project : RDMP RU V Balikpapan


JO Transmittal PMC Comment Transmittal
TR. No. JO's Doc. Cat. TR. No. Review Code 2
Document No. 26071-100-V1A-H601-02006 Title ACCU GENERAL ARRANGEMENT DRAWING FOR UTILITY AREA Revision 000

No. Reference/Page No. Purchaser's Comment VENDOR Response or Concusion Purchaser's Comment VENDOR Response or Concusion

1 Page 3 of 14 Weld Brazing to be added by Vendor Noted

2 Page 3 of 14 Lifting lug detail is missing Noted

3 Page 3 of 14 Piping conection detail is still missing Noted

4 Page 3 of 14 Add Note: a. Internal wiring is to be finished by VENDOR/DAIKIN. Noted

5 Page 3 of 14 Mention doc number Noted

6 Page 3 of 14 Refer to datasheet this shold be H4000CC, DAIKIN to clarify Noted, follow datasheet

7 Page 3 of 14 DAIKIN to clarify this value refer to selection criteria Noted

8 Page 3 of 14 in Mechanical data & datasheet the SA 11.006 L/s The value of AHU blower

ACCU doesn't have to be mirrored installation. Please apply same pipe dirrection to both unit
9 Page 3 of 14 Follow layout drawing OCR, The location of piping connection ACCU to AHU right side from LCP => Noted
A & B (view from LCP: Left side

Rearrange the equipment and prevent clashes or problem maintenance, refer to process
10 Page 3 of 14 The position component have a distance => Ensure the space during maintenance or overhaul is enough Ensure the space during maintenance or overhaul is enough Noted
area arrangement is completely different

Refer to 26071-203-H6C-341-37012 the cooling capacity should be 260kW, DAIKIN to explain Noted. Already revised. => put the correct data, data that mentioned at GA drawing is for maximal cooling put the correct data, data that mentioned at GA drawing is for maximal cooling capacity, please
11 Page 3 of 14 Noted
the selection criteria capacity, please revise accordingly revise accordingly

As per Datasheet and Mechanical Data dimention suction pipe Ø2 1/8" and liquid pipe connection Ø7/8" =>
12 Page 3 of 14 Refer to P&ID this should be 1 1/8", Daikin check datasheet and relevant drawings
Noted

What does by field mean? Foundation will be prepared by main contractor as per required
13 Page 8 of 14 Drawing already provided, Please check again. => Noted
dimention and minimum height provided in this drawing.

Provide notes, how big and size of the maintenance equipment required. The availability if
Noted.
14 Page 5 of 14 space in this building shall refer to the operation manual by VENDOR. 3000mm clearance is
Minimum clearence for access maintenance area is width unit. => Noted
the conservative approach. Clarify the unit of equipment required on the maintenance area.

Add provide the lifting gear (crane assembly into the lifting lug) illustration, including the size
15 Page 7 of 14 Noted, location of the padeyes to be revised after COG calculation => Noted
of equipment required, location of the padeyes and arrangement

As per GAD data base on 1 unit => please ensure the qty, which document which are valid to follow, please make please ensure the qty, which document which are valid to follow, please make align the
16 Page 9 of 14 Compressor qty id contradictive with datasheet which show qty per ACCU 4 unit Noted, will be revise (2 EA Compressor for each ACCU)
align the number of compressor. 2 compressor for each ACCU or 4 compressor for each ACCU number of compressor. 2 compressor for each ACCU or 4 compressor for each ACCU

Not Agreed.
17 Page 9 of 14 Hot gas bypass is missing The system already had controllor for control system. Cause the system have two compressor and running with
capacity control 33-66-100% and the compressor have stepless capacity regulator

18 Page 9 of 14 Add RAL colour here Ready add BOM GAD

Please try to make ACCU 001A/B and 002A/B shall be delivered become 1 unit and please
19 Page 11 of 14 Noted, will be revised on GAD => Noted
make sure no issued for transportation during shipment

some comment from page 3 & 9 are still


not incorporated in this CRS yet, please
incorporate all of comment on this CRS

Comment Resolution Sheet after rev.log


Doc. No. : 26071-100-V1A-H601-02006

Job No. : 26071 Rev.000

AIR COOLED CONDENSING UNIT (ACCU)


GENERAL ARRANGEMENT DRAWING FOR
HVAC EQUIPMENT UTILITY AREA

PROJECT : Engineering, Procurement and Construction (EPC) Inside


Battery Limits (ISBL) and Outside Battery Limits (OSBL) for
the Refinery Development Master Plan (RDMP) Project
RU V Balikpapan
LOCATION : Refinery Unit V Balikpapan, East Kalimantan,Indonesia
OWNER : PT PERTAMINA (Persero)
PO NO. : 26071-100-POA-H601-00001

Comment Resolution Sheet after rev.log

M. Naufal

000 30 AUG 21 ISSUED FOR CONSTRUCTION FAHMI MARTUA JEREMY

00B 13 JUL 21 RE - ISSUED FOR REVIEW FAHMI MARTUA JEREMY

00A 08 FEB 21 ISSUED FOR REVIEW FAHMI MARTUA JEREMY

REV. DATE DESCRIPTION PREPARED CHECKED APPROVED

1 of 14
Doc. No. : 26071-100-V1A-H601-02006

Job No. : 26071 Rev.000

REVISION LOG

REV. NO. DATE PAGE DESCRIPTION

00A 08 FEB 21 - ISSUED FOR REVIEW


00B 13 JUL 21 - RE - ISSUED FOR REVIEW
000 30 AUG 21 - ISSUED FOR CONSTRUCTION

TYPICAL, please optimize the dimension because there is limitation space for AHU
indoor and size maximum limit

2 of 14
detail piping from ACCU, and AHU to be mentioned ACCU SPECIFICATION
& Joining skid installation detail

TOP VIEW

Name Plate

SELECTOR SWITCH SELECTOR SWITCH


MANUAL - OFF - AUTO ON- OFF

DRAWING
RACK

FRONT VIEW
SIDE VIEW

TB1 TB1.1 TB1.2 TB1.3 TB1.4 TB1.5 TB1.6 TB2 TB3 TB4 TB5 TB6 SPARE

PE IE

PERTAMINA

FRONT VIEW SIDE VIEW


DETAILED DETAILED
3 of 14
ACCU SPECIFICATION

detail piping from ACCU, and AHU to be mentioned

& Joining skid installation detail

TOP VIEW

Name Plate

SELECTOR SWITCH SELECTOR SWITCH


ON- OFF MANUAL - OFF - AUTO

DRAWING
RACK

FRONT VIEW
SIDE VIEW

SPARE TB6 TB5 TB4 TB3 TB2 TB1.6 TB1.5 TB1.4 TB1.3 TB1.2 TB1.1 TB1

IE PE

PERTAMINA

SIDE VIEW FRONT VIEW


DETAILED DETAILED
4 of 14
PERTAMINA

5 of 14
Lifting gear illustration

PERTAMINA

6 of 14
NOTE :

TOP VIEW

Name Plate

SELECTOR SWITCH SELECTOR SWITCH


MANUAL - OFF - AUTO ON- OFF

DRAWING
RACK

PERTAMINA

FRONT VIEW SIDE VIEW

7 of 14
TOP VIEW

+300 mm (min) from


TOC, it's OK?

SIDE VIEW FRONT VIEW PERTAMINA

8 of 14
as per data sheet shall be
4 ea
ACCU SPECIFICATION

DETAIL A
DETAIL C

DETAIL B DETAIL D
TOP VIEW

Name Plate

SELECTOR SWITCH SELECTOR SWITCH


MANUAL - OFF - AUTO ON- OFF

DRAWING
RACK

FRONT VIEW
SIDE VIEW

TB1

TB1.1 TB1.2 TB1.3 TB1.4 TB1.5 TB1.6 TB1.7 TB1.8 TB1.9 TB1.10 TB1.11 TB1.12 TB2 TB3 TB4 TB5 TB6 SPARE

PE IE

PERTAMINA

FRONT VIEW SIDE VIEW


DETAILED DETAILED
9 of 14
ACCU SPECIFICATION

DETAIL A

DETAIL C

DETAIL B
TOP VIEW DETAIL D

etalP emaN

HCTIWS ROTCELES HCTIWS ROTCELES


FFO -NO OTUA - FFO - LAUNAM

GNIWARD
KCAR

FRONT VIEW
SIDE VIEW

TB1

SPARE TB6 TB5 TB4 TB3 TB2 TB1.12 TB1.11 TB1.10 TB1.9 TB1.8 TB1.7 TB1.6 TB1.5 TB1.4 TB1.3 TB1.2 TB1.1

IE PE

PERTAMINA

SIDE VIEW FRONT VIEW


DETAILED DETAILED
10 of 14
Lifting gear illustration

PERTAMINA

TOP VIEW

11 of 14
Lifting gear illustration

PERTAMINA

TOP VIEW

12 of 14
NOTE :

TOP VIEW

Name Plate

SELECTOR SWITCH SELECTOR SWITCH


MANUAL - OFF - AUTO ON- OFF

DRAWING
RACK

FRONT VIEW SIDE VIEW PERTAMINA

13 of 14
TOP VIEW

FRONT VIEW LEFT SIDE VIEW PERTAMINA

14 of 14

You might also like