You are on page 1of 79

Draft Site Development Plan 2019

for the North and Baltic Sea

Hamburg, 26. October 2018


Photos: 50 Hertz, BSH
Content I

Content

1 Introduction 1
1.1 The Central Model 1
1.2 Statutory basis of the Site Development Plan 1
1.3 Purpose and goals of the Site Development Plan 2
1.4 Subject of the Site Development Plan 3
2 Process for the expansion of offshore wind energy 4
2.1 Site Development Plan 5
2.1.1 Responsibility 5
2.1.2 Initial schedule 5
2.1.3 Update 5
2.1.4 Coordination requirements 6
2.1.5 Consensus requirement 6
2.2 Investigation of sites 6
2.3 Call for tenders 7
2.4 Planning approval 8
2.5 Interfaces with other instruments of network planning 9
2.5.1 Scenario framework 9
2.5.2 Network development plan 9
2.5.3 Federal requirement plan 10
2.5.4 Ten-Year Network Development Plan 10
2.5.5 Federal network plan 11
2.6 Existing spatial planning and planning 11
2.6.1 Exclusive Economic Zone 12
2.6.2 Lower Saxony 12
2.6.3 Schleswig-Holstein 12
2.6.4 Mecklenburg-Western Pomerania 12
3 Starting Position 13
3.1 Current state of the expansion 13
3.2 Legislative trajectory of offshore wind energy 16
3.3 Increased expansion trajectory of the scenario framework 2019-
II Content

2030 16
4 Guidelines and Basic Principles 17
4.1 Introduction 17
4.2 Connection concepts 17
4.2.1 Standard concept North Sea: DC system 17
4.2.2 Standard concept Baltic Sea: Three-phase system 18
4.3 Standardised technical principles 18
4.3.1 DC system North Sea 18
4.3.2 Three-phase system Baltic Sea 18
4.3.3 Cross-connections between converter/transformer platforms 18
4.3.4 Cross-border cables 18
4.4 Planning principles 19
4.4.1 General principles 19
4.4.2 Noise mitigation 20
4.4.3 Offshore sites and offshore wind turbines 21
4.4.4 Platforms 21
4.4.5 Subsea cable systems 22
4.5 Possible deviations 23
4.5.1 Standardised technical principles 23
4.5.2 Planning principles 23
4.6 Planning horizon 24
4.7 Determination of expected generation capacity 24
4.7.1 Aim of the power output determination 24
4.7.2 Methodology of the power output determination in Zone 1 and 2 24
4.7.3 Criteria for determining power output 24
4.7.4 Power density to be applied 26
4.7.5 Determination of expected generation capacity in zone 3 27
4.8 Criteria for determining the sites and the chronological sequence
of their call for tenders 28
4.8.1 Methodology for the application of the criteria 28
4.8.2 Description of the criteria to be applied 28
5 Rules 30
5.1 Areas for the installation and operation of offshore wind turbines 30
Content III

5.2 Sites for the installation and operation of offshore wind turbines 33
5.2.1 Rules of sites 33
5.2.2 Significant criteria for the decision concerning the stipulation of the
areas 37
5.3 Expected generation capacity 38
5.4 Rules for coastal waters 39
5.4.1 Requirement for an administrative agreement 39
5.4.2 Areas for the installation and operation of offshore wind turbines 39
5.4.3 Sites for the installation and operation of offshore wind turbines 39
5.4.4 Calendar year of commissioning of the offshore wind turbines and the
corresponding connection cables 39
5.4.5 Expected generation capacity 39
5.5 Chronological sequence of tenders for the sites 40
5.5.1 Chronological sequence of tenders for the sites 40
5.5.2 Representation of the review of the chronological sequence based on
references to offshore connecting cables, grid connection points and the
network expansion on land 40
5.6 Calendar year of the commissioning for offshore wind turbines
and connecting cables 41
5.7 Locations of converter platforms, collector platforms and
transformer platforms 41
5.8 Routes or route corridors for offshore connecting cables 41
5.9 Gates to coastal waters 41
5.9.1 Current state 41
5.9.2 Rules of gates to coastal waters 41
5.10 Routes and route corridors for cross-border cables
(interconnectors) 42
5.10.1 Current state 42
5.10.2 Rule of routes and route corridors for cross-border cables
(interconnectors) 42
5.10.3 Rules of gates for cross-border cables (interconnectors) 43
5.11 For cross-connections between converter/transformer platforms 44
6 Rules for pilot offshore wind turbines 45
6.1 Available grid connection capacities 45
6.2 Spatial specifications 45
IV Content

6.3 Technical conditions and prerequisites for grid connection 45


7 Conformity of the rules with private and public concerns 46
7.1 Legal grounds for exclusion 46
7.1.1 Compliance with requirements of spatial planning 46
7.1.2 No risk to the marine environment 47
7.1.3 No negative impact on safety or ease of traffic 47
7.1.4 No impairment of the security of national and Alliance defence 48
7.1.5 No location in legally designated protected area 48
7.1.6 No location outside areas and sites designated in BFO clusters or by
coastal states 48
7.2 Other public and private interests 48
7.3 Prevention of the occurrence of the exclusion criteria through
planning principles 49
7.4 Admissibility of the rule of areas 51
7.5 Admissibility of the rule of sites 52
7.6 Admissibility of other rules 53
8 Summary consideration 55
9 Summary environmental statement 56
10 Appendices: maps (for information) 57
11 Bibliography 61
12 Annex: Informational illustration of an increased
development path (scenario framework 2019-2030) 63
12.1 Scenarios B 2030 and C 2030 (17 GW by 2030) 64
12.2 Scenario A 2030 (20 GW by 2030) 65
12.3 Scenario B 2035 (23.2 GW by 2035) 66
12.4 Connecting lines that may be required for the scenarios 67
Content V

List of figures
Figure 1: The Site Development Plan in the overall system of the central model for the sector of
the German EEZ of the North Sea and Baltic Sea........................................................................... 4
Figure 2: Planning process of the Site Development Plan and strategic environmental assessment
....................................................................................................................................................... 5
Figure 3: Stages for the site investigations ...................................................................................... 6
Figure 4: Offshore wind farms in the German EEZ of the North Sea which will most likely be
in operation by the end of 2025 ..................................................................................................... 15
Figure 5: Offshore wind farms in the German EEZ of the Baltic Sea which will most likely be
in operation by the end of 2025 ..................................................................................................... 15
Figure 6: Schematic representation of the methodology for power output determination ............... 24
Figure 7: Power density of offshore wind farms in the German North Sea and Baltic Sea depending
on their geometry .......................................................................................................................... 25
Figure 8: Mean wind speed [m/s] at 116 m height for COSMO−REA6 between 1995 and 2014
(Source: DWD) ............................................................................................................................. 25
Figure 9: Distribution of wind speed at 90 m height of FINO 1, FINO 2 and FINO 3 2009-2014
(Borsche, Kaiser-Weiss, & Kaspar, 2016) ..................................................................................... 25
Figure 10: Long-term wind direction distribution in the North Sea (left: FINO 1, 90 m height) and in
the Baltic Sea (right: FINO 2, 92 m height) (Source: Fraunhofer IWES) ........................................ 25
Figure 11: Exemplary application of criterion 2 for assessing the degree of shading
from neighbouring wind farms ....................................................................................................... 25
Figure 12: Specific output power of wind turbines in European wind farms (Borrmann, Rehfeldt,
Wallasch, & Lüers, 2018) .............................................................................................................. 26
Figure 13: Power density of implemented and planned wind farms already awarded or with
allocated grid connection in the North Sea and Baltic Sea ............................................................ 26
Figure 14: Corrected power output of European offshore wind farms (Borrmann, Rehfeldt,
Wallasch, & Lüers, 2018) .............................................................................................................. 27
Figure 15: German North Sea depicting the distance zones of the O-NDP ................................... 28
Figure 16: German Baltic Sea depicting the distance zones of the O-NDP ................................... 29
Figure 17: Areas of the German EEZ of the North Sea ................................................................. 31
Figure 18: Areas of the German EEZ of the Baltic Sea ................................................................. 31
Figure 19: Sites of the German EEZ of the North Sea ................................................................... 34
Figure 20: Sites in the areas N-3, N-6, N-7 and N-9 in the German EEZ in the North Sea ............ 35
Figure 21: Sites of the German EEZ of the Baltic Sea ................................................................... 36
Figure 22: Areas and sites in coastal waters initially submitted for possible nomination by
Mecklenburg-Western Pomerania, subject to the conclusion of an administrative agreement ....... 39
VI Content

Figure 24: Shipping routes in the North Sea EEZ Spatial Plan ...................................................... 57
Figure 25: Shipping routes in the Baltic Sea EEZ Spatial Plan ...................................................... 57
Figure 26: Designations: subsea cables, pipelines, traffic separation areas (North Sea) ............... 58
Figure 27: Designations: subsea cables, pipelines, traffic separation areas (Baltic Sea) ............... 58
Figure 28: National defence territories (North Sea) ....................................................................... 59
Figure 29: National defence territories (Baltic Sea) ....................................................................... 59
Figure 30: Areas for the construction and operation of offshore wind turbines in the German
North Sea EEZ and nature conservation areas. ............................................................................ 60
Figure 31: Areas for the construction and operation of offshore wind turbines in the German
Baltic Sea EEZ and nature conservation areas ............................................................................. 60
Figure 32: Informational figure of possible rules according to scenarios B and C 2030
(17 GW by 2030) and challenges to be overcome......................................................................... 64
Figure 33: Informational figure of possible rules according to scenario A 2030 (20 GW by 2030)
and challenges to be overcome .................................................................................................... 65
Figure 34: Informational figure of possible rules according to scenario B 2035 (23.2 GW by 2035)
and challenges to be overcome .................................................................................................... 66
Content VII

List of tables
Table 1: Overview of offshore connecting cables by the end of 2025 and connected offshore wind
farm projects ................................................................................................................................. 14
Table 2: Categorisation of the sites for determining the expected generation capacity .................. 26
Table 3: Exemplary comparison of (corrected) power densities for two offshore wind farms ......... 27
Table 4: Grid connection systems including commissioning by the end of 2025 and available
transmission capacity .................................................................................................................... 28
Table 6: Overview of sites for offshore wind energy ...................................................................... 33
Table 7: Overview of significant criteria for the decision against rule of an area ............................ 37
Table 8: Overview of expected generation capacity in the sites for offshore wind turbines ............ 38
Table 9: Overview of the chronological sequence of tenders for the sites with the application of
criteria 1 to 8 ................................................................................................................................. 40
Table 10: Overview of the information concerning offshore connecting cables with a commissioning
date from 2026 onwards by the TSO according to the statement dated 15 June 2018 .................. 40
Table 11: Overview of calendar years of commissioning of offshore connecting cables, on
acceptance of the notes provided in chapter 5.5 ........................................................................... 41
Table 12: Overview of utilisation of gates ...................................................................................... 41
Table 13: Overview of the gates and routes for cross-border power lines as defined in
the Site Development Plan ............................................................................................................ 44
Table 14: Overview of the routes defined in the Site Development Plan for connections between
systems ........................................................................................................................................ 44
Table 15: Grid connection capacities available for pilot offshore wind turbines ............................. 45
Table 19: Overview of the commissioning years which may be necessary for the offshore
connecting lines in the various scenarios ...................................................................................... 67
VIII Content

List of abbreviations
AC Alternating current
AIS Data Data from the automatic identification system in shipping
EEZ Exclusive Economic Zone
EEZ North Sea Regulation concerning spatial planning in the German exclusive economic zone
ROV in the North Sea
EEZ Baltic Sea Regulation concerning spatial planning in the German exclusive economic zone
ROV in the Baltic Sea
BAW Federal Waterways Engineering and Research Institute
BfN Federal Agency for Nature Conservation
BFO Spatial Offshore Grid Plan
BFO-N Spatial Offshore Grid Plan North Sea
BFO-O Spatial Offshore Grid Plan Baltic Sea
BGBI Federal Law Gazette
BImSchG Act concerning the protection from harmful environmental impacts through air
pollution, noise, vibrations and similar events (Federal Immission Control Act)
BKG Federal Agency for Cartography and Geodesy
BMI Federal Ministry of the Interior, for Construction and Homeland
BMU Federal Ministry for the Environment, Nature Conservation and Nuclear Safety
BMVBS Federal Ministry for Transport, Building and Urban Development
BMVI Federal Ministry for Transport and Digital Infrastructure
BMWi Federal Ministry for Economic Affairs and Energy
BNatSchG Act concerning nature conservation and landscape management (Federal Nature
Conservation Act)
BNetzA Federal Network Agency for Electricity, Gas, Telecommunications, Post and
Railway
BSH Federal Maritime and Hydrographic Agency
DC Direct current
DRU Diode rectifier unit
DWD German Meteorological Service
EEA European Environmental Agency
EEG Act concerning the development of renewable energy (German Renewable
Energy Act)
EIS Environmental impact study
ENTSO-E European network of transmission system operators for electricity
EnWG Act concerning electricity and gas supply (German Energy Act)
ESCA European Subsea Cables Association
R&D Research and Development
FEP Site Development Plan
FFH Flora Fauna Habitat
GDWS Directorate General for Navigation and Waterways
GW Gigawatt
HELCOM Helsinki Commission
HVDC High-voltage DC transmission
ICES International Council for the Exploration of the Sea
Content IX

ICPC International Cable Protection Committee


kV Kilovolt
LEP S-H State Development Plan Schleswig-Holstein
LEP M-V State Spatial Development Programme of Mecklenburg-Western Pomerania
LROP State spatial planning program of Lower Saxony
MARNET Automated monitoring network of stations in the German Bight and western
Baltic Sea
MI Cable Paper and oil insulated ground cable
MSRL Directive 2008/56/EC of the European Parliament and the Council dated
17 June 2008 for the establishment of a Framework for Community Action
in the field of Marine Environment (Marine Strategy Framework Directive)
MW Megawatt
n.s. not stated
NABEG Network expansion acceleration act for transmission network
NDP Network development plan
NfS Notice to mariners
n.m. Nautical mile
NVP Grid connection point
O-NDP Offshore network development plan
OSPAR Oslo-Paris Convention for the Protection of the Marine Environment of the North-
East Atlantic
POD Stations Porpoise click detector stations
ROG Spatial Planning Act
SeeAnlG Offshore Installations Act
SeeAnlV Ordinance concerning offshore installations for defining German coastal waters
(Offshore Installations Ordinance)
SeeAufgG Act concerning the responsibilities of the State with respect to maritime
navigation (Federal Maritime Responsibilities Act)
SEL Sound event level
SPL p-p Peak emission sound pressure level (peak-peak)
UNCLOS United Nations Convention on the Law of the Sea
StUK4 Standard "Investigation into the impacts of offshore wind turbines (StUK4)"
SEA Strategic environmental assessment
TYNDP Ten-Year Network Development Plan
TSO Transmission system operator
UBA German Environment Agency
UVPG Environmental Impact Assessment Act
VSC Voltage sourced converter
VS-RL Conservation of Wild Birds Directive
VTG Traffic separation scheme
VwVfG Administrative Procedure Act
WEA Wind turbine
WFS Web Feature Service
WHG Act for regulating water resources (Water Resources Act)

WindSeeG Act concerning the development and promotion of offshore wind energy (Offshore
X Content

Wind Energy Act)


WMS Web Map Service
Introduction 1

1 Introduction The current Spatial Offshore Grid Plan (BFO) of


the Federal Maritime and Hydrographic Agency
for the EEZ of the North Sea and Baltic Sea,
1.1 The Central Model
and part of the current offshore network
The year 2017 marks a system change in the development plan (O-NDP) confirmed by
offshore wind energy sector. Based upon the BNetzA, are contained in the Site Development
Act concerning the development and promotion Plan. The requirement for offshore connecting
of offshore wind energy (Offshore Wind Energy cables is determined based upon rules of the
Act - WindSeeG 1), the Federal Maritime and Site Development Plan in the onshore network
Hydrographic Agency (BSH) shall in future development plan.
undertake the task of central development, and
on behalf of the Federal Network Agency 1.2 Statutory basis of the Site
(BNetzA), the investigation of sites for the
Development Plan
installation and operation of offshore wind
turbines. According to sections 4ff. WindSeeG,
the Federal Maritime and Hydrographic Agency
The central model describes a staged planning shall establish a Site Development Plan (FEP)
and tendering process. In the first stage, spatial in conjunction with the Federal Network Agency
and chronological prerequisites are specified for (BNetzA) and in consultation with the Federal
sites for offshore wind energy in the Site Agency for Nature Conservation (BfN),
Development Plan. The next step covers the the Directorate General for Navigation and
site investigation of the sites that were Waterways (GDWS) and the coastal states.
determined in the Site Development Plan. After
completing the site investigation, the sites will The regulations of the Act for the expansion of
be allocated in a competitive tender process, renewable energy (Renewable Energy Act –
wherein the tenderers are provided with the EEG 2017 2) and the Act concerning the
information gained by the site investigation. environmental impact assessment (UVPG 3) are
also applicable.
The tenderer who is awarded a contract may,
after completion of the authorisation procedure,
install wind turbines on the site, is entitled to the
market premium and is permitted to use the
connecting capacity.
The central model applies for the
commissioning of offshore wind turbines from
2026 onwards.
2
The Site Development Plan in the central model Act dated 21 July 2014, Federal Law Gazette I p. 1066,
is therefore the governing planning instrument last amended by article 1 of the Act concerning the
subsidy of sub-metered electricity and the amendment of
for the synchronous expansion of wind energy
further regulations of the renewable energy act dated
and its connection to the offshore network. 17 July 2017, Federal Law Gazette I p. 2532.
3
Act in the officially published version dated 24 February
1
Act dated 13 October 2016, Federal Law Gazette I 2010, Federal Law Gazette I p. 94, last amended by article
p. 2258, 2310, last amended by article 2 paragraph 19 of 2 of the Act for implementing regulation (EU)
the Act to modernise the law concerning environmental No. 1143/2014 concerning invasive, non-indigenous
impact assessment dated 20 July 2017, Federal Law species dated 8 September 2017, Federal Law Gazette I
Gazette I p. 2808. p. 3370.
2 Introduction

development of technologies for generating


1.3 Purpose and goals of the Site
power from renewable energy.
Development Plan
Section 1 subsection 2 of the Renewable
According to section 4 subsection 1 WindSeeG,
Energy Act stipulates an increase in the
it is the purpose of the Site Development Plan
proportion of gross electricity consumption
(FEP) to draw up planning rules for the
generated from renewable energy to
exclusive economic zone (EEZ) of the Federal
Republic of Germany. According to an • 40 to 45% by 2025,
administrative arrangement between the • 55 to 60% by 2035, and
Federal Government, represented by the
Federal Maritime and Hydrographic Agency, • at least 80% by 2050.
and the relevant state, planning rules can also The aim is to provide a steady, cost-efficient
be drawn up for coastal waters. and grid-compatible expansion. According to
Section 4 subsection 2 WindSeeG stipulates section 1 subsection 3 of the Renewable
that, for the expansion of offshore wind turbines Energy Act, this objective also has the purpose
and the offshore connecting cables required for of increasing the proportion of renewable
this, the Site Development Plan draws up rules energy in the entire gross final consumption of
with the aim of energy by 2020 to at least 18%.

• achieving the expansion target in


section 4 No. 2b of the Renewable
Energy Act,
• expanding the power generation from
offshore wind turbines in a spatially
ordered and compact fashion, and
• ensuring an ordered and efficient
utilisation and loading of the offshore
connecting cables, and planning,
installation, commissioning and use of
offshore connecting cables in parallel
with the expansion of power generation
from offshore wind turbines.
The primary purpose of the Site Development
Plan is the implementation of the objective and
goals of the Renewable Energy Act. According
to section 1 of the Renewable Energy Act, it is
the objective of the act, in particular in the
interest of climate and environment protection,
to ensure a sustainable development of energy
supply, to reduce the economic costs of energy
supply through the inclusion of long-term
external effects, to limit the use of fossil fuel
sources and to promote the further
Introduction 3

according to the following regulations for


1.4 Subject of the Site Development
coastal waters, concerning:
Plan
According to the statutory order of section 5
subsection 1 WindSeeG, the Site Development
Plan contains rules, for the period from 2026 to
at least 2030 for the German EEZ and
1. Areas; areas can only be specified in coastal waters if the country concerned has concluded
an administrative arrangement according to section 4 subsection 1 sentence 3 WindSeeG
with the Federal Maritime and Hydrographic Agency and has indicated the areas as
a possible subject for the Site Development Plan,
2. sites in areas specified according to point 1,
3. the chronological order in which the specified sites are put out to tender according to part 3
section 2 of WindSeeG, including the specification of respective calendar years,
4. the calendar years in which the allocated offshore wind turbines and the corresponding
offshore connecting cables are to be commissioned in each of the specified sites,
5. the expected generation capacity of the offshore wind turbines to be installed in each of
the specified areas and sites,
6. locations of converter platforms, collector platforms and, as far as possible, transformer
platforms,
7. routes or route corridors for offshore connecting cables,
8. places at which the offshore connecting cables cross the border between the EEZ
and coastal waters,
9. routes or route corridors for border-crossing power cables,
10. routes or route corridors for possible interconnections of the plants, routes or route corridors
listed in points 1, 2, 6, 7 and 9, and
11. standardised technical and planning principles.

In the period starting from 2021, the Site and designate the technical conditions of the
Development Plan can identify available grid offshore connecting cable and the resulting
connection capacities in existing, or in the technical prerequisites for the grid connection of
following years yet to be completed, offshore pilot offshore wind turbines.
connecting cables in areas inside the German
EEZ and in coastal waters, which may be
assigned to offshore pilot wind power plants in
accordance with section 70 subsection 2
WindSeeG. The Site Development Plan may
provide spatial specifications for the installation
of pilot offshore wind turbines in certain areas,
4 Process for the expansion of offshore wind energy

2 Process for the expansion The BNetzA will then invite tenders for the sites
to competitively determine the market premium,
of offshore wind energy and publish the investigation results and
A new process for the expansion of offshore information obtained in the site investigation
wind energy is being introduced with the (cf. sections 14 ff. WindSeeG). Only the
WindSeeG for offshore wind turbines that will successful tenderer may later apply for planning
be commissioned from 2026 onwards. There approval for the installation and operation of
are a number of steps to be completed between offshore wind turbines on the respective site.
the general site development and the The awarded tender includes an entitlement to
authorisation procedure for the wind turbines connect the wind turbines to the offshore
and connecting cables. connecting cable specified in the Site
Development Plan and to use the allotted grid
According to section 4 ff. WindSeeG, the Site connection capacity in the connection cable.
Development Plan will initially provide planning
rules for the expansion of offshore wind After the tender has been awarded, the
turbines and offshore connecting cables in successful bidder may apply for planning
the EEZ. approval under sections 44 ff. WindSeeG.
At this level of the planning stage, the Federal
The aim of specifying the chronological Maritime and Hydrographic Agency will
completion sequence of the sites is that, from investigate whether a certain project is
2026 onwards, offshore wind turbines will be permissible. If all prerequisites are met and the
brought into operation in these sites and at the investigation result is positive, the process is
same time the required installation of offshore completed with the award of the planning
connecting cables will be completed, so that the approval notice.
existing offshore connecting cables are used
efficiently and their capacity is utilised.
The next step involves the site investigation of
the sites according to sections 9 ff. WindSeeG.
This concerns the investigation of the marine
environment, the preliminary survey of the
construction site, as well as the wind and
oceanographic conditions for the site under
preliminary investigation.
Figure 1: The Site Development Plan in the overall system of the
This will accelerate the subsequent planning central model for the sector of the German EEZ of the North Sea
and Baltic Sea
approval process for offshore wind turbines in
these sites. Please see chapter 5.4 concerning coastal
Building upon the results of the site waters.
investigation, the suitability of the sites for the
tender process will then be investigated.
If suitability is confirmed, the information
including the investigation results and the rule
of the power output to be installed shall be
established by ordinance and passed on to
BNetzA.
Process for the expansion of offshore wind energy 5

2.1 Site Development Plan • Publication of the Site Development Plan


and the environmental report
section 6 WindSeeG regulates the process of
establishing the Site Development Plan, starting • Submission of a summarised declaration
from publishing the introduction of the process to the participating North Sea and Baltic
Sea states
to publishing the completed plan.

2.1.1 Responsibility
According to section 6 WindSeeG, the Federal
Maritime and Hydrographic Agency is
responsible for preparing the Site Development
Plan.

2.1.2 Initial schedule


The following summary depicts the individual
process stages.

Summary of the process stages


• Publication of the introduction and
estimated conclusion of the process Figure 2: Planning process of the Site Development Plan and
strategic environmental assessment
• Preparation of a preliminary draft and a
draft of the scope
2.1.3 Update
• Official and public participation The Federal Maritime and Hydrographic
• Issue of a common statement of the Agency initially prepares the Site Development
TSOs (Transmission System Operators) Plan by 30 June 2019.
• Assessment of the statement of the TSOs According to section 8 subsection 1 of
• Date of hearing WindSeeG, the Site Development Plan may be
amended or updated by proposal from the
• Determination of the scope
Federal Maritime and Hydrographic Agency,
• Preparation of the Site Development Plan wherein the decision concerning timing and
draft and the environmental report scope of a process for amendment or update is
• Official and public participation made by mutual agreement between the
• Public hearing Federal Maritime and Hydrographic Agency and
BNetzA.
• Assessment of the environmental report
under consideration of the statements According to section 5 WindSeeG, the Site
Development Plan is amended or updated if, to
• Consideration of the assessment in the
Site Development Plan draft achieve the goals according to section 4
WindSeeG, it is necessary to establish other or
• Consultation with the Federal Agency for
further areas and sites, or a change in
Nature Conservation, the Directorate-
General for Waterways and Shipping and chronological order of the preliminary
the coastal states assessment of the sites because, for example,
investigated sites were deemed to be
• Establish agreement with BNetzA
unsuitable.
6 Process for the expansion of offshore wind energy

Nevertheless, it shall be updated at least every a planning approval process for the installation
four years (cf. section 8 subsection 2 and operation of offshore wind turbines at the
sentence 1 WindSeeG). Federal Maritime and Hydrographic Agency
according to sections 44 ff. WindSeeG.
2.1.4 Coordination requirements
According to section 9 subsection 1 WindSeeG,
According to section 6 subsection 7 WindSeeG, the site investigation has the aim of providing
the preparation of the Site Development Plan the tenderers for the available sites
takes place in coordination with the Federal
Agency for Nature Conservation, the • with sufficient information to enable
Directorate-General for Waterways and them to ascertain a competitive market
Shipping and the coastal states. premium according to section 22d of the
Renewable Energy Act and
2.1.5 Consensus requirement
• to determine the suitability of the sites
According to section 6 subsection 7 WindSeeG, and
the preparation of the Site Development Plan
takes place in agreement with BNetzA. • to assess individual investigation objects
in advance so as to accelerate the
2.2 Investigation of sites subsequent planning approval process
According to section 11 subsection 1 for these sites.
sentence 1 of WindSeeG, the BNetzA is The process for the implementation of
responsible for the investigation of sites. the site investigation, including the
BNetzA assigns responsibility for the site suitability examination of the sites
investigations in the EEZ to the Federal nominated in the Site Development Plan
Maritime and Hydrographic Agency in is guided by section 12 WindSeeG.
accordance with the administrative A strategic environmental assessment must
arrangement dated March 2017 in accordance also be carried out.
with section 11 subsection 1 sentence 2 No. 1
WindSeeG. Thus, according to section 11 According to section 9 subsection 3 WindSeeG,
subsection 2 sentence 1 WindSeeG, the the investigation of sites must be carried out so
Federal Maritime and Hydrographic Agency that, prior to the publication of the tender, the
carries out the tasks of the authority responsible site investigation is completed for at least those
for the site investigation according to the law for sites for which, according to the Site
the sites in the German EEZ. Development Plan, tenders will be invited in the
current and the following calendar year.
Where sites in coastal waters are concerned,
the BNetzA according to section 11 The following stages are legally provided in
subsection 1 sentence 2 No. 2 WindSeeG particular:
assigns responsibility for the site investigation
to the authority responsible according to
national law in accordance with an
administrative arrangement.
The investigation of sites takes place with the
aim of BNetzA inviting tenders for the sites
suitable according to sections 16 ff. WindSeeG.
The successful bidder must then carry out
Process for the expansion of offshore wind energy 7

Figure 3: Stages for the investigation of sites tender volume. The share of a site in the total
tender volume is determined by the Site
Summary of the process stages
Development Plan and the power to be installed
• Publication of the introduction of the on the sites as determined by the site
process investigation.
• Date of hearing Six months prior to the tender deadline, BNetzA
• Determination of the scope shall publish the tender on its internet web site
according to section 19 WindSeeG, including
• Provision of information concerning the
maritime environment, the preliminary any information to be provided by the Federal
investigation of the installation site and Maritime and Hydrographic Agency, and
wind and oceanographic conditions documentation according to section 10
subsection 1 WindSeeG containing any further
• Suitability examination and determination
of the power output to be installed information as required by statutory ordinance.

• Determination of suitability through a The Federal Network Agency (BNetzA) awards


statutory ordinance the tender for each tendered site to the bid with
the lowest bid value under the caveat of
• Interpretation of the documents
revocation as well as the caveat of a transition
• Submission of the information to BNetzA in the event of an effective exercise of
subrogation. The value to be applied is the
tender value of the successful tender.
With the award of the tender according to
2.3 Call for tenders section 23 WindSeeG, the successful bidder
For sites that were deemed suitable, BNetzA has the exclusive right to carry out a planning
shall determine by way of a tender process the approval process on the respective site,
value of the market premium and the respective wherein the successful bidder benefits from the
entitled beneficiary. BNetzA is responsible for information and suitability determination of the
this according to sections 16 ff. WindSeeG. site investigation.

According to section 17 sentence 1 WindSeeG, Furthermore, the successful bidder is entitled to


BNetzA shall issue annual tenders from 2021 the market premium according to section 19 of
onwards by the tender deadline of the Renewable Energy Act to the extent of the
1 September, covering a volume between applied bid size on the respective site, as long
700 and 900 MW. The tendered quantities must and insofar as the further prerequisites for the
not exceed those that were determined in the entitlement according to section 19 of the
Site Development Plan, which according to Renewable Energy Act are met. Moreover, to
section 5 subsection 5 sentence 1 WindSeeG is the extent of the applied bid size, the successful
an average of 840 MW. The tendered volume is bidder is entitled to be connected to the wind
distributed over the preliminary investigated turbines on the respective site by the offshore
sites which, according to the Site Development connecting cable specified in the Site
Plan, are to come up for tender in the current Development Plan from the binding completion
calendar year, provided that the Site date, and receives the allotted grid connection
Development Plan allows for tenders in multiple capacity of the offshore connecting cable
sites in one year, and that the expected specified in the Site Development Plan from the
generation capacity in total makes up the entire binding completion date according to section
8 Process for the expansion of offshore wind energy

17d subsection 2 sentence 9 of the Energy platforms or transformer platforms, that the
Industry Act (EnWG). 4 obligation according to section 66 subsection 2
WindSeeG has been declared effective, and
2.4 Planning approval that other regulations according to WindSeeG
After the tender has been awarded by BNetzA, and other public law regulations have been met.
applications for a planning approval may be A planning approval notice or planning
submitted for the site covered by the plan permission for an offshore wind turbine is
according to section 46 subsection 1 granted with a limit of 25 years. A single
WindSeeG. According to section 45 retrospective extension of the time limit by a
subsection 2 WindSeeG, the Federal Maritime maximum of five years is possible, provided
and Hydrographic Agency is the authority that the Site Development Plan provides for an
responsible for the hearing process, planning immediate subsequent use according to section
approval process and planning permission 8 subsection 3 WindSeeG (cf. section 48
process. subsection 7 WindSeeG).
In addition to the statutory specifications of The planning approval or planning permission
section 73 subsection 1 sentence 2 of the requires the consent of the Directorate-General
Administrative Procedure Act, the plan must for Waterways and Shipping.
contain the information contained in section 47
As soon as the planning approval notice or
subsection 1 WindSeeG.
planning permission is no longer in force, the
In the planning approval notice, according to facilities must be removed according to section
section 48 subsection 3 WindSeeG, the Federal 58 subsection 1 WindSeeG as required therein.
Maritime and Hydrographic Agency has the
According to WindSeeG, the successful bidders
power, in the interest of a rapid installation and
must
commissioning of the project and under
consideration of the time and action plan • within twelve months of being awarded the
provided by the contractor, to specify measures tender, submit the documentation required
and to set deadlines by which said measures for the implementation of the hearing
must be fulfilled. process concerning the plan to the Federal
The plan may only be realised under certain Maritime and Hydrographic Agency,
conditions that are listed in section 48 • at the latest 24 months prior to the binding
subsection 4 WindSeeG. This includes that the completion date, supply proof to BNetzA
marine environment is not endangered, that the concerning an existing financing
safety and ease of traffic is not compromised, arrangement for the installation of wind
that the safety of the national and Alliance turbines to the extent of the applied bid
defence is not compromised, that the plan is size,
reconcilable with overriding mining activities,
• at the latest three months prior to the
that it is compatible with existing and planned
binding completion date, supply proof to
routes of cables, offshore connection cables,
BNetzA that the installation of the wind
pipelines and other lines, that it is compatible
turbines has commenced,
with existing and planned locations of converter
• within six months after the binding
4
completion date, supply proof to BNetzA
Act dated 7 July 2005, Federal Law Gazette. I p. 1970,
3621, last amended by article 2 subsection 6 of the act
that at least one wind turbine is technically
dated 20 July 2017, Federal Law Gazette I p. 2808. operational,
Process for the expansion of offshore wind energy 9

• and within 18 months after the binding Act for determining the expansion requirement
completion date, supply proof to BNetzA of the transmission network, and is approved by
that all of the wind turbines are technically BNetzA after consultation and examination
operational (cf. section 59 subsection 2 according to section 12a subsection 3 of the
WindSeeG). Energy Industry Act.
In the instance of non-compliance with 2.5.2 Network development plan
deadlines, a financial penalty shall be
Based upon the scenario framework, the
automatically applied.
transmission system operators shall submit to
the regulatory authority every even calendar
2.5 Interfaces with other
year a common national network development
instruments of network planning plan according to section 12b Energy Industry
As a result of the changeover to renewable Act for confirmation; this plan must contain,
energy and hence the expansion of offshore amongst others, all effective measures for
wind energy, a nationwide network expansion is a needs-based optimisation, improvement and
required. To determine the extent of the expansion of the network which are necessary
network expansion required, a statutory for a secure and reliable network operation at
process consisting of multiple instruments and the latest by the end of the review period in the
the participation of the public will assess and sense of the scenario framework according to
specify the nationwide requirement for section 12a subsection 1 sentence 2 Energy
expansion. Industry Act.
The following describes the interfaces with the The network development plan takes into
other instruments involved in the network consideration the community-wide network
planning process in relation to the Site development plan (Ten-Year Network
Development Plan. Development Plan, TYNDP for short, see
chapter 2.5.4).
2.5.1 Scenario framework
Starting with the submission of the first draft of
According to section 12a Energy Industry Act,
the NDP in 2018, it contains all effective
the transmission system operators shall every
measures for a needs-based optimisation and
2 years (in every even calendar year) prepare a
improvement for the expansion of the offshore
common scenario framework that describes the
connecting cables in the exclusive economic
most likely development of the German
zone (EEZ) and in coastal waters, including the
electricity distribution system. The scenario
grid connection points on land, which are
framework comprises at least three
required by the end of the review period
development paths (so-called scenarios), which
according to section 12a subsection 1 sentence
cover the extent of the most likely
2 Energy Industry Act, for a staged, needs-
developments for at least the next 10 years and
based and economic expansion as well as a
at most 15 years of the energy-political aims of
safe and reliable operation of the offshore
the Federal Government in the medium to long
connecting cables and the further transmission
term. One of the scenarios must show the most
of power generated offshore. Based upon the
likely development over the at least next
findings of the latest published Site
15 years and at most 20 years. The scenario
Development Plan, details concerning the
framework forms the basis for the
planned completion date of these measures
establishment of the network development plan
shall be provided in the NDP.
(NDP) according to section 12b Energy Industry
10 Process for the expansion of offshore wind energy

According to section 12c subsection 4 Energy one existing wind farm project according to
Industry Act, BNetzA shall confirm the NDP by section 37 subsection 1 No. 2 WindSeeG has
31 December of each odd calendar year at the received capacity by way of tender award within
latest under consideration of the results of the the scope of the second tender deadline
official and public participation. according to section 26 subsection 1
WindSeeG. Secondly, reference is made to the
From 1 January 2019 onwards, the TSO
fact that the criteria of the O-NDP for the
(Transmission System Operators) must,
chronological sequence of the implementation
according to section 17d subsection 1 Energy
of the offshore connecting cables according to
Industry Act, install and operate the offshore
section 17b subsection 2 sentence 3 Energy
connecting cables according to the
Industry Act differs from the criteria of the Site
specifications of the NDP and the Site
Development Plan for the rule of the sites and
Development Plan. The TSOs are required to
the chronological order of their call for tender
commence the grid connection of offshore wind
according to section 5 subsection 4 sentence 2
turbines according to the specifications of the
WindSeeG, and also refer to different rules, so
NDP and the Site Development Plan and to
that it is possible in principle that the completion
proceed rapidly with the installation of the grid
dates of offshore connecting cables may differ.
connections of offshore wind turbines.
Thus the confirmation of the offshore network
A number of statements on the preliminary draft development plan 2017-2030 in the Site
of the Site Development Plan are required to Development Plan cannot be taken into
take into account the offshore network consideration for offshore connecting cables
development plan that was approved by after 2025.
BNetzA on 22 December 2017. Firstly,
reference is made to section 17c subsection 1 2.5.3 Federal requirement plan
sentence 2 Energy Industry Act, according to
which the O-NDP (Offshore Network 2.5.4 Ten-Year Network Development Plan
Development Plan) for offshore connecting According to article 8 subsection 3 b) of the
cables, the planned completion date of which is Directive EC 714/2009 of the European
after 2025, is confirmed with the proviso of the Parliament and the council dated 13 July 2009
corresponding rule of the respective offshore concerning network access conditions for
connecting cable in the Site Development Plan. cross-border power trading and the revocation
Correspondingly, the confirmation of the of the Directive (EC) No. 1228/2003 5, the
offshore development plan 2017-2030 and the European transmission system operators for
assignment of the confirmed connection electricity (ENTSO-E) every two years adopt a
systems are subject to proviso of the non-binding, community-wide, ten-year network
corresponding confirmation in the network development plan ("community-wide network
development plan 2019-2030 on the basis of development plan") including a European
the Site Development Plan rule according to forecast for the adequacy of electric power
section 12c subsection 4 sentence 1 Energy generation.
Industry Act in conjunction with section 12b
In this context, the European transmission
subsection 1 sentence 4 No. 7 Energy Industry
system operators published on 20 December
Act. This proviso is no longer in effect for the
2016 a so-called Ten-Year Network
confirmation and assignment of the connecting
systems OST-2-1, OST-2-2 and OST-2-3, since
in each respective connecting system at least 5
OJ 211/15, 14 August 2009.
Process for the expansion of offshore wind energy 11

Development Plan (TYNDP 2016) in the


consulted and final version. 2.6 Existing spatial planning and
planning
It contains national and international expansion
measures that are significant for cross-border, For the coordination of all space demands and
European electrical power transmission. concerns that occur in a certain space,
The draft of the TYNDP 2018 is currently Germany has a tiered planning system for
in the consultation phase and will most likely be spatial planning through federal spatial planning
published at the end of 2018. The results as well as state and regional planning; with this
obtained from the NDP at a national level are system, according to section 1 subsection 1
included in the relevant TYNDP. sentence 2 of the Federal Spatial Planning Act,
different demands on a space are coordinated
2.5.5 Federal network plan so as to settle conflicts that may occur at a
respective planning level and to plan for
individual uses and functions of the space.
The planning of the subsequent planning levels
are further substantiated through the tiered
system. According to section 1 subsection 3 of
the Federal Spatial Planning Act,
the development, order and security of the
partial spaces is to be integrated into the
circumstances and requirements of the entire
space, and the development, order and security
of the entire space must consider the
circumstances and requirements of its partial
spaces.
The Federal Ministry of the Interior, for
Construction and Homeland is responsible for
spatial planning at the federal level in the EEZ.
In contrast, for state-level planning, the
respective federal state is responsible for the
entire space of the federal state including the
respective coastal waters. State-specific
responsibilities exist for regional planning.
Besides the spatial planning for the respective
responsibility sectors, there is sectoral planning
based upon sectoral laws for certain specific
planning sectors. Sectoral plans serve
the purpose of determining details for
the respective sector taking into account the
requirements of spatial planning.
12 Process for the expansion of offshore wind energy

Law Gazette I p. 3107) came into force on


2.6.1 Exclusive Economic Zone
26 September 2009. On the 19 December
Since 2004, the EEZ has provided the statutory 2009, the ordinance of the BMVBS concerning
basis for the establishment of maritime Spatial
the spatial planning in the German EEZ in the
Plans (see chapter 2.6.1.2). Baltic Sea dated 10 December 2009 (Federal
As part of the resolutions concerning the energy Law Gazette I p. 3861) came into force.
transition in June 2011 and the corresponding With regard to maritime spatial planning, the
statutory changes, the Federal Maritime and
international specifications of the United
Hydrographic Agency was tasked with Nations Convention on the Law of the Sea must
preparing a plan for offshore power networks in be observed. Besides the scientific and
the German EEZ, the Spatial Offshore Grid economic utilisation of the sea, mainly the
Plan, and to update it regularly (see interests of shipping and nature conservation
chapter 2.6.1.1).
are relevant. In relation to offshore wind energy,
both Spatial Plans contain amongst others aims
2.6.1.1 Spatial Offshore Grid Plans
and principles of spatial planning for offshore
The task of federal planning is now wind energy (3.5) and subsea cables (3.3).
implemented in the Site Development Plan with
additional tasks, mainly with regard to In the process of preparing the Spatial Plans, a
specifying the chronological implementation strategic environmental assessment was also
sequence of the sites for offshore wind turbines carried out to determine, describe and evaluate
and offshore connecting cables. Please see the probable significant environmental impacts
chapters 2.1 and 2.5. on factors.

The first Spatial Offshore Grid Plan for the EEZ The update of the existing Spatial Plans will
of the North Sea 2012 was published on most likely commence in 2018/2019.
22 February 2013. The first Spatial Offshore
2.6.2 Lower Saxony
Grid Plan for the EEZ of the Baltic Sea 2013
followed on 7 March 2014. Both plans were
2.6.3 Schleswig-Holstein
updated for 2016/2017.
2.6.4 Mecklenburg-Western Pomerania
2.6.1.2 Spatial Plans
To achieve a sustainable spatial planning in the
EEZ, the Federal Maritime and Hydrographic
Agency, by order of the Federal Ministry of the
Interior, prepares Spatial Plans that come into
force in form of ordinances of the Federal
Ministry of the Interior. The Federal Maritime
and Hydrographic Agency, by order of the then
Ministry for Transport, Building and Urban
Development (BMVBS), had already in 2009
prepared the Spatial Plans for the German EEZ
of the North Sea and the Baltic Sea.
The ordinance of the BMVBS concerning
the spatial planning in the German EEZ in the
North Sea dated 21 September 2009 (Federal
Starting Position 13

3 Starting Position Industry Act a.F.), capacity allocations


(according to section 17d subsection 3 or
section 118 subsection 19 Energy Industry Act)
3.1 Current state of the expansion
or tenders awarded (according to section 34
Offshore wind farms with their associated WindSeeG) through the Federal Network
connecting cables have been installed and Agency.
operated since 2009 in German coastal waters
as well as in the German EEZ of the North Sea By the end of 2017, connecting cables for
and the Baltic Sea. offshore wind farm projects with a transmission
capacity of approximately 5.7 GW had been
By the end of 2017, offshore wind turbines installed and taken into operation. Ten of the
with an output capacity of approximately connecting cables are located in the North Sea
5.4 GW had been installed and commissioned. and two in the Baltic Sea.
The expansion of offshore wind energy was and The state of expansion of offshore connecting
remains dependent on the underlying cables depicted in Tabelle 1 includes all grid
conditions. According to current planning, there connection systems for offshore wind farm
will be a capacity of approximately 7.7 GW in projects that were ordered for the fulfilment of
offshore wind farm projects connected to the an individual claim to grid connection of a wind
network by the end of 2020, and 10.8 GW by farm operator.
the end of 2025. These projects are either
provided with unconditional grid connection Thus, by the end of 2025 there will be
permits according to previous legislation 15 connecting cables in the North Sea and
(according to section 118 subsection 12 Energy 8 connecting cables in the Baltic Sea.
14 Starting Position

Table 1: Overview of offshore connecting cables by the end of 2025 and connected offshore wind farm projects
Connecting cables Transmission Offshore wind farm projects connected
by the end of 2025 capacity by the end of 2025
North Sea
NOR-0-1 (Riffgat) 113 MW Riffgat
NOR-0-2 (Nordergründe) 111 MW Nordergründe
NOR-1-1 (DolWin5/epsilon) 900 MW Borkum Riffgrund West II, OWP West, Borkum Riffgrund West I
NOR-2-1 (alpha ventus) 62 MW alpha ventus
NOR-2-2 (DolWin1/alpha) 800 MW Borkum Riffgrund 1, Trianel Wind Farm Borkum
NOR-2-3 (DolWin3/gamma) 900 MW Borkum Riffgrund 2, Merkur Offshore
NOR-3-1 (DolWin2/beta) 916 MW Gode Wind 01, Gode Wind 02, North Sea One
NOR-3-3 (DolWin6/kappa) 900 MW Gode Wind III, Gode Wind 04
NOR-4-1 (HelWin1/alpha) 576 MW Meerwind South/East, North Sea East
NOR-4-2 (HelWin2/beta) 690 MW Amrum Bank West, KASKASI II
NOR-5-1 (SylWin1/alpha) 864 MW Butendiek, Dan Tysk, Sandbank
NOR-6-1 (BorWin1/alpha) 400 MW BARD Offshore 1
NOR-6-2 (BorWin2/beta) 800 MW Albatros, German Bight, Veja Mate
NOR-7-1 (BorWin5/epsilon) 900 MW EnBW He Dreiht
NOR-8-1 (BorWin3/gamma) 900 MW EnBW High Seas, Global Tech I
Baltic Sea
OST-3-1 (Baltic1) 51 MW EnBW Baltic1, EnBW Baltic 2, GICON-SOF
OST-3-2 (Baltic2) 339 MW
OST-1-1 250 MW Arkona Basin South East, Wikinger, Wikinger South
OST-1-2 250 MW
OST-1-3 250 MW
OST-2-1 250 MW ARCADIS East I
OST-2-2 250 MW Baltic Eagle
OST-2-3 250 MW
Starting Position 15

Figure 4: Offshore wind farms in the German EEZ of the North Sea which will most likely be in operation by the end of 2025

Figure 5: Offshore wind farms in the German EEZ of the Baltic Sea which will most likely be in operation by the end of 2025
16 Starting Position

energy is regulated in that the increase in


3.2 Legislative trajectory of offshore installed offshore wind turbine capacity is to be
wind energy 6,500 MW by 2020 and 15,000 MW by 2030.
According to the climate protection strategy of To what degree the implementation of the Paris
the Federal Government for the expansion of climate protection agreement, the adoption of
offshore wind energy utilisation prepared in the national climate action plan 2050 by the
2002, offshore wind energy had already special Federal Cabinet on 14 November 2016, and the
significance then. The proportion of wind implementation of the coalition agreement
energy provided in total power consumption is dated 14 March 2018 of the governing parties
set to grow to at least 25% within the next three are reflected in specific statutory measures, and
decades. The aim was then to install a capacity what effect they have on the legislative
of a total of 25 GW in the North Sea and the expansion trajectory, remains to be seen.
Baltic Sea by 2030.
According to the energy concept of the Federal
3.3 Increased expansion trajectory
Government dated 28 September 2010, the of the scenario framework
proportion of renewable energy of the total 2019-2030
power consumption is to increase to 35%
by 2020 and to 80% by 2050.
As part of the energy transition agreed in 2011,
renewable energy increased in significance.
The Federal Government decided on 6 June
2011 on an energy package that supplemented
the measures of the energy concept and had
the aim of accelerating its implementation.
As part of the latest reform of the Renewable
Energy Act in 2016, according to section 1
subsection 2 of the Renewable Energy Act
2017, the aim is to increase the proportion of
power generated through renewable energy of
the gross electricity consumption to
• 40 to 45% by 2025,
• 55 to 60% by 2035, and
• at least 80% by 2050.
This objective also has the purpose of
increasing the proportion of renewable energy
of the entire gross final consumption of energy
by 2020 to at least 18%. The aim is to provide a
steady, cost-efficient and grid-compatible
expansion.
In section 4 No. 2 Renewable Energy Act,
the expansion trajectory for offshore wind
Guidelines and Basic Principles 17

4 Guidelines and Basic connection concept, details of which are


described in Chapter 4.2.
Principles
The planning principles build upon the aims and
principles of the Spatial Plan. As part of the
4.1 Introduction
preparation of the Spatial Plan, an overall
The strategic planning of the expansion of balancing of utilisations has already taken
offshore wind energy as well as the associated place. The relevant aims and principles are
network topology for the transmission of largely included in the Site Development Plan
electricity is of utmost significance for the as planning principles and, with respect to
supply with renewable energy. With the applicability concerning objects of regulation
increase in different utilisations in the German touched on in the Site Development Plan, are
EEZ, the available space for future utilisation checked, substantiated and assessed amongst
and infrastructure becomes less and less. each other concerning their significance based
For the purpose of systematic and efficient upon the interests and rights presented.
planning, the Federal Maritime and The determination of standardised engineering
Hydrographic Agency received a statutory principles and planning principles is already
request to allocate areas and sites for offshore based upon a consideration of possibly affected
wind energy as well as corresponding routes public interests and legal positions
and locations for the required network topology. (cf. justification of individual provisions and
The result of these coordinated processes will principles), so that the determination of
be that the actions in the German EEZ will be standardised engineering principles and
stipulated bindingly in terms of space and time. planning principles already contains a "pre-
The determination of planning principles and assessment" of possible alternatives.
standardised engineering principles for the EEZ
of the North Sea and the Baltic Sea is a 4.2 Connection concepts
mandatory prerequisite for the definite
determination of the space requirement of the 4.2.1 Standard concept North Sea: DC
entire network topology within the scope of the system
Site Development Plan. The aim of specifying
4.2.1.1 Connection between converter
standardised engineering principles and
platform and offshore wind farms:
planning principles is to provide a basis for a
standard concept 66 kV
systematic and coordinated overall planning
process. Otherwise it would not be possible to
determine the required space with the
Summary
necessary accuracy in the planning process.
Apart from determining the space requirement • Determination of the 66 kV connection
as precisely as possible, the standardised concept as standard for the EEZ of
technical principles also help with cost the North Sea
efficiency and the needs-based expansion of • The cable end plug of the 66 kV subsea
connecting cables, which is in the economic cable systems serves as the interface
interest of the country. between transmission network operator
and the project developer of the offshore
The starting point for determining standardised wind farm
engineering principles (4.3) is the technical grid
• Deviation from the standard concept is
18 Guidelines and Basic Principles

possible in case of spatial requirements in Summary


an area
• Implementation of the HVDC transmission
• If a deviation is required, determination of systems in voltage sourced (VSC)
the connection concept of the BFO-N technology
16/17 with an operating voltage of 155 kV
• Standard transmission voltage
+/- 320 kV
4.2.2 Standard concept Baltic Sea: Three- • Standard transmission power 1000 MW
phase system
• Deviation from the standard transmission
power is possible in case of spatial
requirements in an area
Summary
• Connection of offshore wind turbines to
• Determination of the three-phase the converter platform in 66 kV three-
connection concept as standard for the phase technology
EEZ of the Baltic Sea

4.3.2 Three-phase system Baltic Sea


4.3 Standardised technical
principles 4.3.2.1 Three-phase system:
Transmission voltage 220 kV
4.3.1 DC system North Sea
4.3.2.2 Three-phase system: Utilisation of
.
transformer platform by the TSO
4.3.1.1 DC system: Voltage sourced
technology
Summary
• Standard transmission voltage 220 kV
4.3.1.2 DC system: Transmission voltage
• Planning and installation of the
+/- 320 kV transformer platform by the project
developer; utilisation by the TSO must be
4.3.1.3 DC system: Standard power made possible.
1000 MW

4.3.1.4 Requirement for type and number


of control panels to be provided 4.3.3 Cross-connections between
converter/transformer platforms
4.3.1.5 Create conditions for cross-
connections between
converter/transformer platforms
4.3.4 Cross-border cables
4.3.1.6 66 kV connection concept
4.3.4.1 Bundled DC cable

4.3.4.2 Consideration overall system


Guidelines and Basic Principles 19

4.4.1.1 Chronological overall coordination


4.4 Planning principles
of installation works
According to section 5 subsection 1 No. 11
In order to prevent or mitigate cumulative
WindSeeG, the Site Development Plan contains
effects, overall coordination concerning
determinations concerning planning principles.
timing of the installation works shall be
The planning principles apply for the sector of carried out under consideration of the
the German EEZ and build upon the aims and underlying project-specific conditions.
principles of the Spatial Plan.
F.1 No negative impact on safety or ease of
General planning principles will now be shipping traffic
specified. The safety and efficiency of shipping must
not be compromised as a result of the
4.4.1 General principles operation of offshore wind turbines,
Planning principles for offshore wind turbines, platforms and subsea cables.
platforms and offshore connecting cables are
4.4.1.2 No negative impact on safety or
listed below.
ease of air traffic
Summary The safety and ease of air traffic must not be
compromised as a result of the operation of
• Chronological overall coordination of
offshore wind turbines, platforms and
installation works
subsea cables.
• Safety and ease of shipping traffic must
not be diminished 4.4.1.3 Obligation to dismantle and
security deposit
• Safety and ease of air traffic must not be
After ceasing utilisation, the offshore wind
diminished
turbines, platforms and subsea cables
• Obligation to dismantle and security should be dismantled. Should the
deposit dismantling pose greater environmental
• Consideration of all existing and approved consequences than leaving the equipment,
usages dismantling should not take place, or not to
the full extent, unless it is required due to
• Consideration of cultural assets reasons of safety and ease of traffic. Should
• Noise mitigation the equipment remain, suitable monitoring
measures are to be taken concerning
• Minimisation of scour protection possible future hazards. If dismantling takes
• Consideration of regulatory standards, place, reuse of the components should be
specifications and concepts the aim before recycling, and recycling
before thermal recycling or any other -
• Emission mitigation proven - appropriate waste management on
• Consideration of ordnance locations land. A security deposit must be paid for
meeting the dismantling obligation.
• Installation of sonar transponders
4.4.1.4 Consideration of all existing and
approved usages
A distance of 500 m shall be maintained
from existing and approved pipelines as
20 Guidelines and Basic Principles

well as existing, approved and, within the and Nuclear Safety (BMU) must be observed
scope of this plan, specified subsea cables, in this respect.
offshore wind farms and other high
structures, unless the construction site 4.4.2.1 Minimisation of scour protection
conditions require greater distances. When Scour protection measures must be reduced
selecting locations for offshore wind to a minimum.
turbines and platforms, the routing of
subsea cable systems, existing and 4.4.2.2 Consideration of regulatory
approved usages and usage rights, and the standards, specifications and
interests of maritime traffic, national and concepts
Alliance defence and the fishing industry Statutory standards, specifications and
must be taken into consideration. concepts must be taken into consideration
The planning, installation and operation of for the planning, installation and operation
offshore wind turbines, platforms and of wind turbines, platforms and subsea
subsea cable systems shall be carried out in cable systems.
close coordination with the transmission
4.4.2.3 Emission mitigation
network operator and the offshore wind
farm project developers. Emissions must be minimised.

4.4.1.5 Consideration of cultural assets 4.4.2.4 Consideration of ordnance


locations
When selecting locations or routes, known
sites of cultural assets must be taken into When selecting locations or routes, known
consideration. If, during planning or ordnance locations must be taken into
installation of the wind turbines, platforms consideration. If, during planning or
or subsea cable systems, so far installation of the wind turbines, platforms
undiscovered cultural assets are found on or subsea cable systems, so far
the seabed, corresponding measures for the undiscovered ordnance is found on the
preservation of the cultural asset must be seabed, corresponding protective measures
taken. must be taken.

4.4.2 Noise mitigation 4.4.2.5 Installation of sonar transponders

For the purpose of noise mitigation, the use Sonar transponders must be installed at
of alternative, low-noise forms of suitable corner positions of wind farms and
foundations are to be considered. If wind platforms.
turbines or platforms are installed with pile
foundations, effective technical noise
mitigation measures are to be taken during
the foundation ramming process. The noise
mitigation concept is to be integrated into
the design scope of the foundation
construction at an early stage. The noise
abatement concept of the Federal Ministry
for the Environment, Nature Conservation
Guidelines and Basic Principles 21

4.4.3.2 Economic area use


The individual wind turbines are to be
4.4.3 Offshore sites and offshore wind
arranged in the most space-saving manner
turbines
possible.
The following lists the planning principles for
sites, primarily for the installation and operation 4.4.3.3 Distances between sites and from
of offshore wind turbines. wind turbines
Wind turbines must have a mutual distance
Summary
of at least five times their rotor diameter.
• Consideration of nature conservation
areas and legally protected biotopes 4.4.4 Platforms
The following states the planning principles for
• Economic area use
platforms. Platforms include converter
• Distances between sites and from wind platforms, collector platforms, transformer
turbines platforms as well as accommodation platforms.

Summary
4.4.3.1 Consideration of nature
conservation areas and legally • Consideration of nature conservation
protected biotopes areas and regard to legally protected
biotopes
The installation of offshore wind turbines in
nature conservation areas is prohibited. • Required area and additional
When installing and operating offshore wind manoeuvring space
turbines, adverse effects on the marine
• The platform design should take into
environment, in particular the natural
consideration the requirement for
functions and the marine ecosystem, must
temporary living quarters; not to be
be prevented.
utilised for longer than three years
Known sites of legally protected biotopes
according to section 30 Federal Nature
Conservation Act or corresponding
structures must be prevented when 4.4.4.1 Consideration of nature
installing wind turbines. conservation areas and regard to
legally protected biotopes
The provisions of section 45 a of the Federal
The installation of platforms in nature
Water Management Act (WHG) 6 must be
conservation areas is not permitted. When
observed, the best environmental practice
installing and operating platforms, adverse
according to the Helsinki or OSPAR
effects on the marine environment,
convention and the respective state of the
in particular the natural functions and the
art are to be taken into consideration and
marine ecosystem, must be prevented.
substantiated in individual processes.
Known sites of legally protected biotopes
according to section 30 Federal Nature
Conservation Act or corresponding
6
The act of 31 July 2009, Federal Law Gazette l p. 2585, structures should be prevented where
last amended by article 1 of the act dated 18 July 2017
(Federal Law Gazette l p. 2771).
possible when installing platforms.
22 Guidelines and Basic Principles

The provisions of section 45 a of the Federal


Summary
Water Management Act (WHG) 7 must be
observed, the best environmental practice • Parallel bundling as far as possible
according to the Helsinki or OSPAR • Spacing in case of parallel installation:
convention and the respective state of the 100 m; 200 m after every second cable
art are to be taken into consideration and system
substantiated in individual processes.
• Routing through gates
4.4.4.2 Required area
• Perpendicular crossing of shipping priority
A site of 100 m by 200 m must be provided and shipping reservation areas
for a converter platform. A site of 100 m by
100 m must be provided for a transformer • Prevent crossings; if absolutely
platform. Additional manoeuvring space necessary, then, as much as possible, at
must be provided for platforms placed side right angles; distance between turning
by side. points 250 m
• Careful installation
4.4.4.3 Temporary living quarters
• Covering
The need for temporary living quarters
(TLQ) must already be considered in the • Mitigation of sediment heating
design phase of offshore construction sites; (compliance with 2 K criteria)
this includes in particular structural safety,
• Consideration of nature conservation
supply and waste disposal, as well as waste
areas and legally protected biotopes
water treatment and matters of occupational
safety including escape routes and means.
Temporary living quarters should generally 4.4.5.1 Bundling
exist no longer than to the end of the When installing subsea cable systems, the
commissioning phase of the respective aim is to run cables as much as possible in
building structure. They should not be used parallel bundles. Moreover, the routes
any longer than three years. should be parallel to existing structures as
far as possible.
4.4.5 Subsea cable systems
The following states the planning principles for 4.4.5.2 Spacing in case of parallel
subsea cable systems, which in the sense of installation
this plan include electrical cable systems such When installing subsea cable systems in
as offshore connecting cables, cross-border parallel, a distance between systems of
cables and cross-connections between 100 m must be maintained. A distance of
converter/transformer platforms. The following 200 m must be kept after every second cable
planning principles 4.4.4.6 and 4.4.4.8 apply to system. In this respect the actual
interconnecting subsea cables within the farm. construction site conditions are to be taken
into consideration, particularly in the Baltic
Sea.

7
The act of 31 July 2009, Federal Law Gazette l p. 2585, 4.4.5.3 Routing through gates
last amended by article 1 of the act dated 18 July 2017 Subsea cable systems that land in Germany
(Federal Law Gazette l p. 2771).
must generally be routed through the gates
Guidelines and Basic Principles 23

N-I to N-IV or O-I and O-III determined at the 4.4.5.7 Covering


border to the EEZ and the 12 n.m. zone. When determining the permanent covering
Moreover, cross-border cables are to be of subsea cable systems, the interest of the
routed through the gates N-V to N-XVII or O-I protection of the marine environment,
and O-XIV determined at the border to the shipping traffic, defence, the fishing
EEZ and the 12 n.m. zone. industry as well as system safety must be
taken into consideration.
Cross-border cables that do not land in
Germany should not be routed through the 4.4.5.8 Sediment heating
gates N-I to N-V due to the limited
When installing subsea cable systems,
availability of routes in coastal waters.
potential adverse effects on the marine
environment through cable-induced
4.4.5.4 Crossing of shipping priority and
sediment heating is to be reduced as much
shipping reservation areas
as possible. The precautionary limit with
Shipping priority and shipping reservation respect to nature conservation is the so-
areas specified in the EEZ Spatial Plan called "2 K criteria", which specifies a
should be crossed by subsea cable systems maximum tolerable temperature increase of
by the shortest possible route insofar as
the sediment by 2 degrees (Kelvin) at 20 cm
parallel routing to existing structural sediment depth.
installations is not possible.
4.4.5.9 Consideration of nature
4.4.5.5 Crossings conservation areas and legally
Mutual crossings of subsea cable systems protected biotopes
as well as crossings with existing pipelines
When installing subsea cable systems,
and existing subsea cables, or those possible adverse effects on the marine
proposed in this plan, should be prevented environment are to be minimised. Thus,
as far as possible. If crossings cannot be subsea cable systems should be installed
prevented, they must be carried out outside nature conservation areas as far as
according to the current state of the art and
possible.
at right angles as far as possible.
Known sites of legally protected biotopes
4.4.5.6 Careful installation according to section 30 Federal Nature
The installation method used for installing Conservation Act or corresponding
subsea cable systems should be as gentle structures should be prevented where
as possible to protect the marine possible when installing subsea cable
environment. systems.

4.5 Possible deviations

4.5.1 Standardised technical principles

4.5.2 Planning principles


24 Guidelines and Basic Principles

expected generation capacity. To this end, the


Any deviation from flexible planning principles
sites under consideration are first categorised
must be requested in the respective approval
based upon the criteria described below. The
process. Every deviation from any planning
aim is to identify sites for which, due to the
principle must be justified in a transparent
criteria-based assessment, a relatively higher or
and plausible manner in the specific approval
lower power density may be applied.
procedure. Compliance with the statutory
requirements must be explained in the If a site meets one of the criteria stated below, it
specific approval procedure. In particular the is allocated to one of the two categories for
following must be stated and presented for determining the power density to be applied. To
examination: determine the expected generation capacity,
the respective site is multiplied by the
• Justification of every deviation for each
applicable power density. If necessary, the
planning principle and proof of
expected generation capacity is corrected if the
compliance with statutory requirements
possible power in the respective site is limited
• Representation of instances in which by the capacity of the grid connection. A
public and private interests may be schematic representation of the methodology
affected for power output determination is shown in
• Consent of or agreement with affected Figure 6.
third parties
• Regard to space-saving and considerate
use of the site in the sense of section 2
subsection 2 No. 6 Spatial Development
Act (ROG)

4.6 Planning horizon

4.7 Determination of expected Figure 6: Schematic representation of the methodology for power
output determination
generation capacity
4.7.3 Criteria for determining power output
4.7.1 Aim of the power output
determination

4.7.2 Methodology of the power output


determination in Zone 1 and 2
Under simplified assumptions, the possible
power output on a defined site is determined by
plant engineering principles of wind turbines (in
particular nominal power output, rotor diameter)
as well as their distance from each other.
However, in order to ensure the efficient
planning of the offshore wind energy expansion
and its grid connection, further criteria must be
taken into consideration when determining the
Guidelines and Basic Principles 25

in Betrieb/Bau Zuschlag Übergangsausschreibung

35
30
Power density [MW/km²]

25
20
15
10 Figure 10: Long-term wind direction distribution in the North Sea
5 (left: FINO 1, 90 m height) and in the Baltic Sea (right: FINO 2,
92 m height) (Source: Fraunhofer IWES)
0
0,0 0,5 1,0 1,5 2,0
Site/Circumference

Figure 7: Power density of offshore wind farms in the German


North Sea and Baltic Sea depending on their geometry

Figure 8: Mean wind speed [m/s] at 116 m height for


COSMO−REA6 between 1995 and 2014 (Source: DWD)
Figure 11: Exemplary application of criterion 2 for assessing
the degree of shading from neighbouring wind farms

Specific capacity
𝑃𝑃𝑁𝑁
𝑝𝑝𝑊𝑊𝑊𝑊𝑊𝑊 =
𝐴𝐴𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟
Specific wind turbine capacity
𝑝𝑝𝑊𝑊𝑊𝑊𝑊𝑊 [Watts/m² of rotor area]
𝑃𝑃𝑁𝑁 Nominal wind turbine capacity [MW]
Figure 9: Distribution of wind speed at 90 m height of FINO 1,
FINO 2 and FINO 3 2009-2014 (Borsche, Kaiser-Weiss, & 𝐴𝐴𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟 Wind turbine rotor area [m²]
Kaspar, 2016)
26 Guidelines and Basic Principles

Figure 12: Specific output power of wind turbines in European


wind farms (Borrmann, Rehfeldt, Wallasch, & Lüers, 2018)

4.7.4 Power density to be applied


35,00
Nordsee Ostsee
30,00
Power denistiy [MW/km²]

25,00

20,00

15,00 Category B

10,00

5,00
Category A
0,00
2005 2010 2015 2020 2025 2030
Date of operation
Figure 13: Power density of implemented and planned wind farms already awarded or with allocated grid connection in the North Sea
and Baltic Sea

Table 2: Categorisation of the sites for determining the expected


generation capacity
Area category A B
Power density to be 14 17
applied [MW/km²]
Guidelines and Basic Principles 27

4.7.5 Determination of expected generation


capacity in zone 3

Corrected power density (Borrmann,


Rehfeldt, Wallasch, & Lüers, 2018)
𝑚𝑚 𝑃𝑃𝑁𝑁
𝑝𝑝𝐴𝐴𝑊𝑊𝑊𝑊 ∗ = �𝑛𝑛 − � + 1�� ∙
2 𝐴𝐴𝑊𝑊𝑊𝑊
Corrected wind farm power density
𝑝𝑝𝐴𝐴𝑊𝑊𝑊𝑊 ∗
[MW/km²]
𝑛𝑛 Number of wind turbines in wind farm
Figure 14: Corrected power output of European offshore wind
Number of peripheral wind turbines
𝑚𝑚 in wind farm
farms (Borrmann, Rehfeldt, Wallasch, & Lüers, 2018)

𝑃𝑃𝑁𝑁 Nominal wind turbine capacity [MW] Table 3: Exemplary comparison of (corrected) power densities for
two offshore wind farms
𝐴𝐴𝑊𝑊𝑊𝑊 Wind farm area [km²]
Wind farm Alpha Ventus Arkona
Basin South
East

Site [km²] approx. 4 approx. 37

Power density
approx. 15.4 approx. 9.7
[MW/km²]
Corr. Power density
approx. 7.7 approx. 7.7
[MW/km²]
28 Guidelines and Basic Principles

4.8.1 Methodology for the application of


the criteria
4.8 Criteria for determining the sites
and the chronological sequence 4.8.2 Description of the criteria to be
of their call for tenders applied
The WindSeeG provides in section 5
4.8.2.1 Criterion 1: Efficient utilisation and
subsection 4 the criteria that are to be applied
loading of the offshore connecting
for determining the sites in the Site
cables including commissioning
Development Plan as well as the chronological
by the end of 2025
sequence of their call for tenders. The primary
Table 4: Grid connection systems including commissioning by the
aim of the determination is to ensure that the end of 2025 and available transmission capacity
expansion of offshore wind turbines and the Name Year of Available
corresponding connection systems in these commissioning transmission
sites is synchronised, and that the existing capacity
connecting cables are utilised and loaded North Sea
sufficiently. This ensures that all offshore wind NOR-3-3 2023 658.25 MW
turbines are connected in good time and that (DolWin6/kappa)
there are no vacancies in the connecting Baltic Sea
cables. This is to ensure that the expansion of --

the utilisation of wind energy takes place as


cost-effectively as possible. This aim, as well as
4.8.2.2 Criterion 2: Orderly and efficient
the general aim of the act to ensure a cost-
planning, installation,
effective expansion of the utilisation of offshore
commissioning, utilisation and
wind energy, is to be observed in the
loading of the offshore connecting
application of the criteria stated in section 5
cables including commissioning
subsection 4 sentence 2 WindSeeG. The listing
from 2026 onwards
in sentence 2 is not definitive.
Moreover, according to section 5 subsection 5 4.8.2.3 Criterion 3: Spatial proximity to the
WindSeeG, the areas and sites and the coast
chronological sequence of their tenders are
determined such that offshore wind turbines
with an expected generation capacity of 700 to
900 MW and of no more than an average of
840 MW are put out for tender at each tender
deadline according to section 17 WindSeeG
and brought into operation per calendar year
from 2026 onwards.

Figure 15: German North Sea depicting the distance zones of the
O-NDP
Guidelines and Basic Principles 29

Figure 16: German Baltic Sea depicting the distance zones of the
O-NDP

4.8.2.4 Criterion 4: Usage conflicts on


a site

4.8.2.5 Criterion 5: Probable actual


development potential of a site

4.8.2.6 Criterion 6: Expected generation


capacity

4.8.2.7 Criterion 7: Balanced distribution


between North Sea and Baltic Sea

4.8.2.8 Supplementary criterion coastal


waters: Actual availability of
the site
30 Rules

Table 5: Overview of areas for offshore wind energy


5 Rules
Area Size The O-NDP zone
5.1 Areas for the installation and [km²] arrangement
North Sea
operation of offshore wind
N-1 approx. 79 1
turbines N-2 approx. 223 1
According to section 5 subsection 1 No. 1 N-3 approx. 312 1
WindSeeG, the Site Development Plan contains N-4 approx. 152 1
determinations concerning areas for the N-5 approx. 185 2
N-6 approx. 249 2
installation and operation of offshore wind
N-7 approx. 163 2
turbines.
N-8 approx. 170 2
This plan currently nominates 13 areas 8 in total N-9 approx. 196 3
in the EEZ of the North Sea and 3 areas in the N-10 approx. 162 3
EEZ of the Baltic Sea for offshore wind N-11 approx. 346 3
turbines. Please see chapter 4.6. N-12 approx. 237 3
N-13 approx. 228 3
For greater clarity, these areas are designated
Baltic Sea
with the letter N or O for the North Sea or the
O-1 approx. 134 1
Baltic Sea respectively and including the
O-2 approx. 101 1
numbers 1 to 13.
O-3 approx. 30 1
The rule and delimitation of the areas is based
in particular on the determinations of spatial
planning and the consideration of further public
and private interests. Summaries of approved
usages and protected areas as well as areas
specified through spatial planning may be found
in BFO-N 16/17 (Chapter 12) and BFO-O 16/17
(Chapter 11). Please see chapter 7. The rule of
areas was largely transferred from the
O-NDP or the BFO respectively. Areas N-1 to
N-4 and all areas in the Baltic Sea are located
in zone 1 of the O-NDP. Areas N-5 to N-8 are
located in zone 2, areas N-9 to N-13 in zone 3
of the O-NDP.

8
The Federal Maritime and Hydrographic Agency has
notices concerning usage conflicts which fundamentally
call into question the rule of area N-5. In particular,
considerations relating to conservation of wild birds as
a public interest could hinder a rule. Please see chapter 7.
Rules 31

Figure 17: Areas of the German EEZ of the North Sea

Figure 18: Areas of the German EEZ of the Baltic Sea


32 Rules

Area N-1 is located between the traffic The Federal Maritime and Hydrographic
separation schemes "German Bight Western Agency has notices concerning usage conflicts,
Approach" and "Terschelling German Bight". which fundamentally call into question a rule of
South of the area is the nature conservation area N-5. In particular, considerations relating
area "Borkum Riffgrund", and to the east the to conservation of wild birds as a public interest
shipping priority area 3 for shipping determined could hinder a rule. Please see chapter 7.
through spatial planning. On the western side of
Area N-6 is located north of the traffic
the area runs the EEZ border to The
separation scheme "German Bight Western
Netherlands. The area is located in the priority
Approach". To the east the area is bordered by
area for wind energy "North of Borkum"
shipping reservation area 12 and in the
determined through spatial planning.
northerly direction by shipping route 6. To the
Area N-2 is located north-east of the nature west of the area runs the EEZ border to The
conservation area "Borkum Riffgrund" and is Netherlands.
bordered in the north-easterly section by the
Area N-7 is located north of the traffic
pipeline "Norpipe". Towards south and north, it
separation scheme "German Bight Western
is bordered by the shipping reservation area
Approach". To the west the area is bordered by
that lies parallel to the traffic separation
shipping reservation area 12 and in the
schemes. The same applies to the eastern side.
northerly direction by the pipelines reservation
The area is located in the priority area for wind
area ("Norpipe").
energy "North of Borkum" determined through
spatial planning. Area N-8 corresponds to the priority area wind
energy "East of Austerngrund" determined in
Area N-3 is also located between the two traffic
the Spatial Plan. To the west the area is
separation schemes to the west of the priority
bordered by the pipelines reservation area
area for pipelines "Europipe 2", determined
(Europipe 1), to the east and north by the
through spatial planning.
shipping routes 4, 5 and 6.
The western half of the area lies in the priority
area for wind energy "North of Borkum", Area N-9 is bordered by the shipping routes 6
determined through spatial planning. The and 10 as well as the pipelines reservation area
pipeline "Europipe 1", which is secured by ("Norpipe").
corresponding pipeline priority and reservation Area N-10 lies between the shipping routes 4, 6
areas, runs through this area in a north-easterly and 10 and the pipelines reservation area
direction. ("Europipe 1").
Area N-4 is located north of Helgoland. At the Area N-11 is bordered by the shipping routes 4,
eastern side it borders the bird sanctuary 5 and 6, the cross-border cable "NorNed" and
"Eastern German Bight" or respectively section the nature conservation area "Sylt Outer Reef –
II of the nature conservation area "Sylt Outer Eastern German Bight".
Reef – Eastern German Bight". This area
corresponds to the wind energy priority area Area N-12 is bordered by the shipping routes 4
"South of Amrum Bank" determined in the and 10 and the cross-border cable "NorNed".
Spatial Plan. Area N-13 is bordered by the shipping route 10
The area N-5 is located to the west of Sylt in or and nature conservation area "Sylt Outer Reef
at the edge of the nature conservation area – Eastern German Bight".
"Sylt Outer Reef – Eastern German Bight".
Rules 33

Area O-1 ("West of Adlergrund") is located


north-east of the island of Rügen at the border
to the Polish EEZ. The area is located to the 5.2 Sites for the installation and
north of the nature conservation area operation of offshore wind
"Pommerian Bight - Rönnebank" as well as turbines
north of the priority area 21 for shipping. To the
west of the area is the priority area 20 for 5.2.1 Rules of sites
shipping, and on the eastern side extends the Table 6: Overview of sites for offshore wind energy
EEZ border to Poland. The area includes the Area Site Site size Connection
wind energy priority area "West of Adlergrund", [km²] concept
determined through spatial planning. North Sea
N-1 - - -
Area O-2 ("Arkona Sea") lies north-east of the
N-2 - - -
island of Rügen. The area is bordered to the
N-3 N-3.5 approx. 17 66 kV
north, east and south by the priority area 19, 20
N-3.6 approx. 43 66 kV
and 21 for shipping. In the west the area N-3.7 approx. 19 155 kV
1)

borders onto a research reservation area. N-3.8 approx. 23 155 kV


1)

Area O-3 ("Kriegers Flak") is located north-west N-4 - - -


2)
N-5 N-5.4 approx. 56 n.s.
of the island of Rügen. The area is bordered in 3)
N-6 N-6.6 approx. 42 155 kV
the north by the Swedish EEZ border, in the 3)
N-6.7 approx. 16 155 kV
west by the Danish EEZ border and in the south
N-7 N-7.2 approx. 52 66 kV
and east by the priority area 19 for shipping. N-8 - - -
This area encloses the priority area for wind N-9 N-9.1
4)
approx. 86
4)
66 kV
energy "Kriegers Flak", determined through Baltic Sea
spatial planning. O-1 O-1.3 approx. 26 AC connection
5)
O-2 O-2.2 approx. 20 -
O-3 - - -

1)
The sites N-3.7 and N-3.8 will be connected to the
connection system NOR-3-3 and thus with the 155 kV
connection concept, which will become operational
in 2023.
2)
The rule of site N-5.4 is fundamentally in doubt.
Please see chapters 5.1, 5.2.2 and 7.
3)
The sites N-6.6 and N-6.7 will be connected with the
155 kV connection system due to their comparatively large
distance from each other as well as the spatial limitations
for cable routes.
4)
The site N-9.1 is not fully required to achieve
the statutory expansion target. In Chapter 5.5, therefore,
only a sub-site of the specified site N-9.1 is taken into
consideration.
5)
The rule of the site O-2.2 is in doubt. Please see
chapters 5.2.2 and 7.
34 Rules

North Sea

Figure 19: Sites of the German EEZ of the North Sea

Notes:
Re. N-5.4: The determination of the site N-5.4 is fundamentally in doubt. Please see chapters 5.1, 5.2.2 and 7.
Rules 35

Figure 20: Sites in the areas N-3, N-6, N-7 and N-9 in the German EEZ in the North Sea
36 Rules

Baltic Sea

Figure 21: Sites of the German EEZ of the Baltic Sea


Rules 37

5.2.2 Significant criteria for the decision


concerning the stipulation of the
areas
Table 7: Overview of significant criteria for the decision against
rule of an area
Area Site Significant criteria for
the decision against rule of
an area
North Sea
N-5 N-5.4 Criterion 4
N-8 - Criterion 2
Baltic Sea
1)
O-1 - Criterion 4 and 6
1)
O-2 O-2.2 Criterion 4, 5 and 6

1)
See Chapter 6 in which available grid connection
capacities for pilot offshore wind turbines in the areas O-1
and O-2 are identified. Concerning notes on possible
usage conflicts, please see the environmental statement
as well as Chapter 7.6. Exactly if and where the
installation and operation of pilot offshore wind turbines
will be permitted shall be solely decided by the
authorisation procedure for pilot offshore wind turbines,
which will take place at a later stage.
38 Rules

5.3 Expected generation capacity


Table 8: Overview of expected generation capacity in the sites for offshore wind turbines
Area Designation of Site size [km²] Power density Expected
sites to be applied generation
[MW/km²] capacity [MW]

North Sea
N-3.5 approx. 17 14 234
1)
N-3.6 approx. 43 15 666
N-3
2)
N-3.7 approx. 19 12 225
3)
N-3.8 approx. 23 14/17 345
N-6.6 approx. 42 17 706
N-6
N-6.7 approx. 16 17 273
N-7 N-7.2 approx. 52 17 900
4) 4) 4)
N-9 N-9.1 approx. 86 12 1.000
Baltic Sea
2)
O-1 O-1.3 approx. 26 11 300
1)
Individual rule taking into account the exploitation of a minimum capacity of 900 MW with DC connecting systems
in the North Sea
2)
Individual rule taking into account the available grid connection capacity
3)
Due to a data cable, the site N-3.8 is separated into two sub-sites, wherein the applied power density is estimated
2 2
at 17 MW/km for the north-eastern sub-site and the applied power density is estimated at 14 MW/km for
the south-western sub-site.
4)
Please see chapter 5.5 concerning the sub-site N-9.1.
Rules 39

5.4 Rules for coastal waters

Figure 22: Areas and sites in coastal waters initially submitted for possible nomination by Mecklenburg-Western Pomerania, subject to
the conclusion of an administrative agreement

5.4.1 Requirement for an administrative 5.4.4 Calendar year of commissioning of


agreement the offshore wind turbines and the
corresponding connection cables
5.4.2 Areas for the installation and
operation of offshore wind turbines 5.4.5 Expected generation capacity

5.4.3 Sites for the installation and


operation of offshore wind turbines
40 Rules

5.5.1 Chronological sequence of tenders


5.5 Chronological sequence of for the sites
tenders for the sites

Table 9: Overview of the chronological sequence of tenders for the sites with the application of criteria 1 to 8
Calendar year Calendar year Area Grid Expected Total expected
of call for of designation connection generation generation capacity
tender commissioning (TF=sub-site) system capacity [MW] to be installed [MW]

1)
N-3.7 NOR-3-3 225
2021 2026 N-3.8 NOR-3-3
1)
345 870
1)
O-1.3 OST-1-4 300
2022 2027 1) 900
N-7.2 NOR-7-2 900
1)
N-3.5 NOR-3-2 234
2023 2028 900
1)
N-3.6 NOR-3-2 666
2) 1)
O-7.1 OST-7-1 160
2024 2029 866
1)
N-6.6 NOR-6-3 706
1)
N-6.7 NOR-6-3 273
2025 2030 664
1)
N-9.1 TF 1 NOR-9-1 391
Total target system 4.200
Probable implementation by end of 2025 10.800
Probable implementation by end of 2030 15.000
1)
Reference is made to the preparation, assessment and confirmation of the network development plan 2019-2030.
2)
The prerequisite is, amongst others, the conclusion of an administrative agreement between Mecklenburg-Western
Pomerania and the Federal Maritime and Hydrographic Agency. Please see section 11 subsection 1 WindSeeG.

references to offshore connecting


5.5.2 Representation of the review of the cables, grid connection points and
chronological sequence based on the network expansion on land

Table 10: Overview of the information concerning offshore connecting cables with a commissioning date from 2026 onwards by the TSO
according to the statement dated 15 June 2018
Name Probable grid connection point Earliest possible Probable transmission network
completion operator
OST-1-4 Area Lubmin/Siedenbrünzow probably 2026 50 Hertz Transmission GmbH
NOR-7-2 Büttel 2027 TenneT TSO GmbH
NOR-3-2 Hanekenfähr 2028 Amprion GmbH
1)
NOR-6-3 Hanekenfähr 2029 Amprion GmbH
NOR-9-1 n.s. n.s. n.s.
1)
According to the statement by the TSO dated 15 June 2018, the completion of a second offshore connecting cable with
the grid connection point Hanekenfähr is not possible before 2029 due to the overall (also land-based) planning and
installation time and the relatively long cable section on land.
Rules 41

Table 12: Overview of utilisation of gates


5.6 Calendar year of the Border Subsea cable systems
commissioning for offshore corridor
wind turbines and connecting N-I (1) NOR-1-1/DolWin5
(2) NOR-8-1/BorWin3
cables (3) NOR-2-3/DolWin3
Table 11: Overview of calendar years of commissioning of (4) COBRAcable
offshore connecting cables, on acceptance of the notes provided
N-II (1) NOR-7-1/BorWin5
in chapter 5.5
(2) NOR-3-1/DolWin2
Name Calendar year of Transmission
(3) NOR-2-2/DolWin1
commissioning capacity [MW]
(4) NOR-2-1 (alpha ventus)
OST-1-4 2026 300
1) 1)
(5) NOR-6-1/BorWin1
OST-7-1 2027 n.s. (6) NOR-6-2/BorWin2
NOR-7-2 2027 900 (7) NOR-3-3/DolWin6
NOR-3-2 2028 900 (8) NOR-3-2
NOR-6-3 2029 979 (9) NOR-6-3
NOR-9-1 2030 1.000 (10) NOR-9-1
1)
N-III (1) Interconnector to Norway
The prerequisite is, amongst others, the conclusion of (2) Interconnector to Great Britain
an administrative agreement between Mecklenburg-
N-IV (1) NOR-7-2
Western Pomerania and the Federal Maritime and
N-V (1) NOR-4-2/HelWin2
Hydrographic Agency. Please see section 11 subsection 1
WindSeeG. (2) NOR-4-1/HelWin1
(3) NOR-5-1/SylWin1
(4) NordLink
5.7 Locations of converter
(5) NOR-7-2
platforms, collector platforms O-I (1) OST-1-1
and transformer platforms (2) OST-1-2
(3) OST-1-3
5.8 Routes or route corridors for (4) OST-2-1
(5) OST-2-2
offshore connecting cables (6) OST-2-3
(7) OST-1-4
5.9 Gates to coastal waters (8) Interconnector to Sweden
(9) Interconnector to Denmark
5.9.1 Current state O-II (1) OST-2-1
(2) Cross connection between
5.9.2 Rules of gates to coastal waters "Arcadis East 1" and "Baltic Eagle"
O-III (1) OST-3-1
(2) OST-3-2
(3) Interconnector to Sweden
(4) Interconnector to Sweden
(5) Interconnector to Denmark
O-IV (1) Kontek
(2) Interconnector to Denmark
O-V (1) Interconnector to Denmark
O-XIV (1) Interconnector to Denmark
42 Rules

spatially integrated in a coordinated overall


5.10 Routes and route corridors for system, i.e. in particular with regard to
cross-border cables connecting lines for offshore wind farms.
(interconnectors) On the basis of TYNPD 2016 (cf. section 2.5.4)
Cross-border cables (interconnectors) in the and the ENTSO-E System Needs Report on
sense of this plan are subsea cable systems TYNDP 2018 (ENTSO-E AISBL, 2018), routes
that pass through at least two states bordering or route corridors for the following potential
the North Sea or the Baltic Sea. cross-border power lines are to be secured in
spatial terms.
5.10.1 Current state
As part of this plan, six additional cross-border
Multiple cross-border cables (interconnectors)
cables (interconnectors) will be stipulated in the
pass through the German EEZ of the North
North Sea EEZ. Of these, two connections
Sea. Firstly, there is a cross-border cable
landing in Germany are planned. Both start at
system (interconnectors) in operation called
gate N-III in Lower Saxony. The interconnector
"NorNed" that connects Norway and The
to Norway runs here in parallel to "Europipe 2",
Netherlands. Furthermore, the project
shipping route 4 and shipping route 5 up to the
"COBRAcable" is currently under construction,
"Sylt Outer Reef – Eastern German Bight"
which will connect The Netherlands and
nature conservation area, then at the boundary
Denmark. Moreover, the project "NordLink",
of the nature conservation area up to the
which has been approved and is under
"NorNed" interconnector, and is then bundled
construction, extends through the German EEZ
with this to gate N-IX.
to connect Norway and Germany. The project
"Viking Link" to connect Denmark with Great The second interconnector landing in Germany
Britain is currently undergoing the approval leads to Great Britain. There are two alternative
process. routes for this one. Both routes start at gate N-
III and then run parallel to "Europipe 2" in a
Cross-border cables (interconnectors) are also
northerly direction to the northern edge of
in operation in the German EEZ of the Baltic
shipping route 2. From there, the route leads
Sea: "Kontek" (linking Denmark and Germany)
west to the crossing of "Europipe 1", at which
and "Baltic Cable" (between Sweden and
point the two routes separate. One route leads
Germany).
south of the N-7 and N-6 areas and on to the
The cross-border cable by the name of
west, to gate N-XVIII. The other alternative is
"Kriegers Flak Combined Grid Solution" is also
planned to run parallel to the "Norpipe" pipeline
under construction. This project will link
or along the western EEZ border to gate N-XIII.
Denmark and Germany by combining Danish
and German offshore wind farm projects. In addition, four further cross-border cables
(interconnectors) are planned which merely
5.10.2 Rule of routes and route corridors for cross the German EEZ and may link The
cross-border cables Netherlands with Denmark or Norway. Two
(interconnectors) routes run on both sides of shipping route 10
This plan is intended to secure space for routes and connect gates N-VIII and N-XVII, as well as
or route corridors for potential cross-border gates N-X and N-XVI. One system is planned to
cables (interconnectors) so as to be able to run parallel to "Viking Link". Another system
ensure in future that the existing and planned connects gates N-XII and N-XV. This runs
cross-border cables (interconnectors) can be mostly parallel to the "Norpipe" and then
Rules 43

continues along the EEZ boundary to gate N- Pomerania as well as the EEZs of Denmark,
XV. Sweden and Poland.
In the Baltic Sea EEZ, eight routes will be The gates in this plan should therefore be
established for cross-border cables connecting defined in close consultation with the coastal
German coastal waters with the EEZs of states and neighbouring countries. In areas
Denmark and Sweden. Systems are also where it is possible to do so based on present
planned for the area of the Fehmarn Belt knowledge, gates for the bundling of subsea
crossing (O-V to O-VI) and parallel to "Kontek" cable systems will be established in the
(O-IV to O-VII). A further system to Denmark transitional areas to the coastal waters, and all
leads from gate O-III to gate O-VIII. Two subsea cable systems landing in Germany are
systems heading towards Sweden also to be routed via these. The intention here is to
commence in gate O-III, subsequently running concentrate the cable systems at these points
parallel to the "EnBW Baltic 2" wind farm to as far as possible, and to bundle them for
gate O-IX. Another interconnector to Sweden further diversion towards the grid connection
starts at gate O-I and runs parallel to area O-2 points. Please see chapter 5.9 with regard to
to gate O-X. An interconnector towards the designation of gates for coastal waters.
Bornholm from gate O-I is also planned, Reference is made to the planning
running parallel to the existing connecting lines principle 4.4.4.3.
to gate O-XII. A further interconnector is
The gates N-VI to N-XIX and O-VI to O-XV,
planned to run parallel to "NordStream 1" or
planned at the outer boundary of the EEZ,
between "NordStream 1" and "NordStream 2",
serve to bundle possible cross-border cables
connecting gates O-XIII and O-XIV.
which have not yet been defined in terms of
A route running from Poland to Denmark does their specific routing into or through the German
not appear to be possible at present due to EEZ. The gates are based on existing plans for
existing restrictions within the German EEZ. interconnectors and wind farms, as well as on
existing pipelines and data cables. When
Reference is made to the cartographic portrayal
defining the gates, the existing plans for
in the annex.
offshore wind farms in neighbouring countries
5.10.3 Rules of gates for cross-border were also taken into account so as to permit
cables (interconnectors) development of a sea-wide grid. Gate N-XIX
has been extended sufficiently to make it
It must be possible to direct the routes planned
possible to route subsea cables to the gate
in the Site Development Plan appropriately,
north of the wind farms in The Netherlands.
through the coastal waters or EEZs of adjacent
On the German side, however, a route
states to the grid connection points. The gates
compliant with spatial planning appears to be
serve as points at which the connecting lines
possible only up to the converter site in area N-
cross the border between the EEZ and the
1, so that this gate is primarily suitable for
coastal waters, or to neighbouring countries.
connecting the directly adjacent wind farms
For the North Sea EEZ, this concerns the
belonging to Germany and The Netherlands.
coastal waters of Lower Saxony and Schleswig-
Holstein and the EEZs of The Netherlands, Further coordination of gates N-VI to N-XIX and
Great Britain and Denmark. For the Baltic Sea O-VI to O-XV for cross-border cables with
region, this affects the coastal waters of neighbouring states is to take place within the
Schleswig-Holstein and Mecklenburg-Western framework of the Site Development Plan
44 Rules

establishment procedure, the relevant Spatial Reference is made to the cartographic portrayal
Plans or the relevant approval procedures. in the annex.

Table 13: Overview of the gates and routes for cross-border power lines as defined in the Site Development Plan
Gate A Gate B Country A Country B
North Sea
N-III N-IX Germany Norway
N-III N-XIII / N-XVIII Germany Great Britain
N-VIII N-XVII Denmark / Norway Netherlands
N-X N-XVI Denmark / Norway Netherlands
N-XI N-XIV Denmark Great Britain
N-XII N-XV Norway Netherlands
Baltic Sea
O-V O-VI Germany Denmark
O-IV O-VII Germany Denmark
O-III O-VIII Germany Denmark
O-III O-IX Germany Sweden
O-III O-IX Germany Sweden
O-I O-X Germany Sweden
O-I O-XII Germany Denmark
O-XIV O-XIII Germany n.a.

5.11 For cross-connections between


converter/transformer platforms
Table 14: Overview of the routes defined in the Site Development
Plan for connections between systems
Platform A Platform B
North Sea
NOR-2-3/DolWin
NOR-1-1/DolWin epsilon
gamma
NOR-3-2 NOR-3-1/DolWin beta
NOR-6-1/BorWin alpha NOR-6-3
NOR-8-1/BorWin
NOR-6-2/BorWin beta
gamma
NOR-7-1/BorWin epsilon NOR-7-2
NOR-8-1/BorWin
NOR-7-1/BorWin epsilon
gamma
Baltic Sea
Wikinger O-1.3
O-1.3 Baltic Eagle
Baltic Eagle Arcadis East 1
Rules for pilot offshore wind turbines 45

6 Rules for pilot offshore


wind turbines 6.2 Spatial specifications

6.1 Available grid connection 6.3 Technical conditions and


capacities prerequisites for grid connection
Table 15: Grid connection capacities available for pilot offshore
wind turbines
Connecting line Available grid Summary
connection capacities
for pilot offshore wind • Consent of or agreement with affected
turbines third parties, for example
North Sea - Offshore wind farm projects for the
NOR-2-2 88 MW use of the transformer platform and
/DolWin1/alpha for spatial and technical integration in
NOR-2-3 50 MW its projects
/DolWin3/gamma
NOR-3-3 approx. 88.25 MW - Adjacent offshore wind farm projects
/DolWin6/kappa
1)
- Responsible TSO, e.g. for testing
NOR-4-2 32 MW
operation of the connecting line in
/HelWin2/beta
compliance with the approval
NOR-6-2 14.4 MW
/BorWin2/beta (e.g. compliance with temperature
Baltic Sea criteria) and for distributing power
OST-1-3 5 MW
if multiple AC cables are available
OST-2-1 3 MW • Interface agreement with offshore wind
OST-2-3 23.75 MW farm project sponsors or TSOs for
connection to the platform
1)
The grid connection capacity available in area N-4 for
pilot offshore wind turbines will be reduced to 32 MW,
since the 62 MW capacity available on the NOR-4-2
connection system (HelWin2/beta) will be partly released
for the NOR-7-2 connection system to be set up at the
Büttel grid connection point.
46 Conformity of the rules with private and public concerns

7 Conformity of the rules balancing decision was already made in


accordance with the applicable provisions in
with private and public which the concerns were weighed against and
concerns among one another.

The rules of the Site Development Plan are The admissibility of the rules was examined by
a manifestation of a planning process offering the state of Mecklenburg-Western Pomerania
scope for manoeuvre. Public and private for the coastal waters of Mecklenburg-Western
interests are to be determined, adjusted, Pomerania. Please see the environmental
evaluated and balanced within the framework of report of the Mecklenburg-Western Pomerania
the planning consideration. spatial development programme (LEP-MV) with
regard to the threat to the marine environment.
According to section 5 subsection 3 of
the WindSeeG, spatial rules are inadmissible if 7.1 Legal grounds for exclusion
there are overriding opposing public or private
interests. A catalogue lists the particular 7.1.1 Compliance with requirements of
concerns involved. If any of these reasons for spatial planning
exclusion exists, a rule is inadmissible in any Any provisions that fail to comply with
case. The list of concerns is not exhaustive. 9 requirements of spatial planning according to
Individual concerns must be weighed against section 17 subsection 3 of the Federal Spatial
each other where there is competition between Planning Act are inadmissible. This will then
them. involve the land use aspects of the rules
For the rule of sites and areas according to according to regional criteria. According to
section 5 subsection 1 nos. 1 and 2 of the section 3 subsection 1 No. 1 of the Federal
WindSeeG which are located in a cluster Spatial Planning Act, the requirements of
defined by the Spatial Offshore Grid Plan (BFO) spatial planning represent the generic term for
under section 17a of the Energy Industry Act, or spatial planning objectives, principles and other
in a priority, reserved or designated area of requirements of spatial planning. According to
a Spatial Plan according to section 17 section 4 subsection 1 No. 1 of the Federal
subsection 3 sentence 1 of the Federal Spatial Spatial Planning Act, the spatial planning
planning Act, the admissibility of the rule need objectives must be observed in regionally
only be examined if additional or other significant planning operations and measures,
significant aspects are discernible or if updates and other requirements of spatial planning must
and in-depth examinations are required (cf. be taken into account in balancing or
section 5 subsection 3 sentence 3 of the discretionary decisions.
WindSeeG). The background to this is that The Spatial Plans for the German Exclusive
when examining the rules of the clusters in the Economic Zone in the North and Baltic Sea
Spatial Offshore Grid Plan and priority, EEZs 10 for the first time specify spatial planning
reserved or designated sites in the Spatial
Plans for the North Sea and Baltic Sea EEZs, a 10
Appendix volume to Federal Law Gazette I No. 61 of
25 September 2009, annex to the Ordinance on Spatial
9
Cf. BT DrS 18/8860 of 21 July 2016, draft bill of the Planning in the German Exclusive Economic Zone in the
CDU/CSU and SPD parliamentary groups, draft bill on the North Sea; appendix volume to the Federal Law Gazette I
introduction of calls for tenders relating to renewable No. 78 of 18 December 2009, annex to the Ordinance on
energies and further amendments to the law on renewable Spatial Planning in the German Exclusive Economic Zone
energies, p. 273. in the Baltic Sea.
Conformity of the rules with private and public concerns 47

objectives and principles for this region with Conservation Act. This means that in particular,
regard to economic and scientific use, ensuring the requirements of statutory biotope
the safety and ease of shipping traffic and conservation (section 30 of the Federal Nature
protection of the marine environment. Conservation Act), European conservation of
Guidelines for spatial development are natural habitats (section 34 of the Federal
formulated and objectives and principles are Nature Conservation Act) and special wildlife
defined, in particular areas for uses and conservation (sections 44 ff. of the Federal
functions. The Spatial Plan defines coordinated Nature Conservation Act) must be observed.
rules for the individual uses and functions of The corresponding examinations were carried
shipping, extraction of raw materials, pipelines out as part of the Strategic Environmental
and subsea cables, scientific marine research, Assessment and presented in the
wind power generation, fisheries and environmental reports. For assessment of the
mariculture, and protection of the marine risk to the marine environment, reference is
environment. made to chapters 7.3 to 7.6, the environmental
reports and, for rules based on previous
The rules of the draft were reviewed to ensure
sectoral plans, the environmental reports for the
that they are compliant with the spatial planning
Spatial Offshore Grid Plan, in particular the
objectives and principles.
environmental report on the Spatial Offshore
7.1.2 No risk to the marine environment Grid Plan for EEZ 2016/17.
According to section 5 subsection 3 sentence 2 7.1.3 No negative impact on safety or ease
no. 2 of the WindSeeG, rules that endanger the of traffic
marine environment are inadmissible.
Rules that effect the safety and ease of traffic
In this context, the existing provisions of are also inadmissible according to section 5
specific legislation, i.e. above all those relating subsection 3 sentence 2 no. 3 WindSeeG.
to wildlife conservation and conservation of
The rules of the areas in the North Sea and
natural habitats, as well as the assessments
Baltic Sea were largely taken from the clusters
with regard to likely significant environmental
already defined in the BFOs for the North Sea
effects within the scope of the Strategic
and Baltic Sea. As issues related to shipping
Environmental Assessment, establish the fact
have already been examined within the
of the threat to the marine environment.
framework of the preparation and updating of
Reference is made to the maps in chapter 10 the BFO, re-examination of the areas and sites
for the representation of the area. in accordance with section 5 subsection 3
Under Art. 1 of the Federal Nature sentence 3 WindSeeG is probably not
Conservation Act (BNatSchG), 11 all instruments necessary initially, with the exception of a few
of nature conservation (with the exception of individual rules.
chapter 2: Landscape planning) were extended Effects relating to air traffic will be discussed
to the area of the German EEZ and the after the consultation.
continental shelf in accordance with section 56
subsection 1 of the Federal Nature

11
Act dated 29 July 2009, Federal Law Gazette. I No. 51
p. 2542, last amended by article 1 of the Act dated
15 September 2017, Federal Law Gazette I p. 3434.
48 Conformity of the rules with private and public concerns

With this regulation, connection of the new


7.1.4 No impairment of the security of
system to previous sectoral planning with the
national and Alliance defence
BFO is ensured. In particular, expansion of the
According to section 5 section 3 subsection 4
use of offshore wind energy should initially take
WindSeeG, the security of national and Alliance place in the clusters already examined in more
defence must not be impaired by any rules. detail and in the coastal area designated by a
The rules of the areas in the North Sea and country. The opening clause ensures that
Baltic Sea were largely taken from the clusters planning can go beyond the stated BFO
already defined in the BFOs for the North Sea clusters and areas and sites in coastal waters if
and Baltic Sea. Concerns relating to national this is necessary in order to achieve the
and Alliance defence have already been expansion objective.
examined within the framework of the
establishment and updating of the BFO, so re- 7.2 Other public and private
examination of the areas and sites according to interests
section 5 subsection 3 sentence 3 WindSeeG is In addition to the reasons for exclusion
probably not necessary initially, apart from a expressly listed in section 5 subsection 3
few individual rules. sentence 2 WindSeeG, a number of other
concerns are relevant within the framework of
7.1.5 No location in legally designated
the review of the Site Development Plan rules
protected area
according to section 5 subsection 3 sentence 1
Section 5 subsection 3 sentence 2 no. 5 WindSeeG. These include, among others, other
WindSeeG stipulates that rules of areas or sites uses such as planned and existing data cables,
in protected sites designated in accordance pipelines and mining activities, the concerns of
with section 57 of the Federal Nature the fishing industry, health and safety at work,
Conservation Act are inadmissible. The rules of cultural heritage, disaster control, the economic
the areas in the North Sea and Baltic Sea were costs of constructing and operating wind farms,
largely taken from the clusters already defined and the economic costs of constructing and
in the BFOs for the North Sea and Baltic Sea. operating offshore connecting lines.
Therefore, areas and sites are not specified in
nature conservation sites. The latter is also taken into account in the rule
of the sites and the chronological order of their
7.1.6 No location outside areas and sites tendering via criterion 1 of efficient use and
designated in BFO clusters or by utilisation of the connecting lines and criterion 2
coastal states of efficient planning, construction and use of the
The rule of areas or sites outside clusters 1 to 8 connecting lines still to be completed in
in the North Sea and clusters 1 to 3 in the Baltic accordance with section 5 subsection 4
Sea of the BFO, or the areas or sites sentence 2 nos. 1 and 2 WindSeeG. This also
designated by a coastal state in coastal waters, applies to the geographical proximity to the
are inadmissible according to section 5 coast according to section 5 subsection 4
subsection 3 sentence 2 no. 5b WindSeeG. sentence 3 no. 3 WindSeeG, which influences
This does not apply if sufficient areas and sites the costs of the offshore connecting line. The
cannot be defined in these clusters, areas and operational costs are included in the rules of the
sites in order to achieve the expansion target draft via the criteria of geographical proximity to
according to section 4 no. 2b of the Renewable the coast, the expected actual development
Energy Sources Act (15 GW in 2030). potential, chronological order and the expected
Conformity of the rules with private and public concerns 49

generation capacity, which are also mentioned The requirements of spatial planning are taken
in section 5 subsection 4 sentence 2 up by the following planning principles in the
WindSeeG. Please see chapter 4.8.1. draft Site Development Plan:
The interests of existing projects that have not - the principle of overall coordination of
been awarded contracts in the tendering construction and laying work over time
procedures are not private or public interests
- the objective of respecting nature
which preclude rule. 12 This is indicated by the
conservation areas and taking legally
wording of section 5 subsection 3 sentence 2
protected biotopes into account
WindSeeG, which lists the concerns with a
potential degree of involvement and does not - the objective or principle stating that the
mention the right of subrogation. Even if the safety and efficiency of shipping must not
right of subrogation – contrary to the be compromised
explanatory memorandum – were a private - the objective of dismantling wind turbines,
interest, there is no right to specify a site or a subsea cables and pipelines
certain site layout.
- the objective of taking into account all
Insofar as the prerequisites for the right of existing and authorised uses
subrogation according to sections 39 ff.
WindSeeG are met, it is in all events relevant - the principle of taking into account
that the right of subrogation according to locations where cultural assets have been
section 39 of the WindSeeG can be assigned found
with a predominant proportion for the - the principle of economic area use
subsequent exercising of the right of
- the principle of bundling of subsea cable
subrogation.
systems
7.3 Prevention of the occurrence of - the objective of ensuring that shipping
the exclusion criteria through traffic crosses priority and reservation
areas by the shortest possible route
planning principles
As a basis, planning principles were introduced - the principle of least intrusive laying
in order to prevent hazards to the marine procedures
environment, impairments to safety and ease of The following planning principles concern
traffic, and impairments to safety and ease of threats to the marine environment:
national and Alliance defence, and to mitigate
- Overall chronological coordination of
these to such an extent that there are no
installation works
impairments or hazards. Besides the general
principles, the planning principles also - Consideration of nature conservation areas
specifically concern areas and sites, platforms and regard to legally protected biotopes
and subsea cable systems (see chapter 4.4). - Dismantling of wind turbines, subsea
cables and pipelines

12
- Consideration of locations of cultural assets
Cf. BT DrS 18/8860 of 21 June 2016, draft bill of the
CDU/CSU and SPD parliamentary groups, draft bill on the - Noise mitigation
introduction of tenders from renewable energies and
further amendments to the law on renewable energies, p. - Minimisation of scour protection
273.
50 Conformity of the rules with private and public concerns

- Consideration of regulatory standards, The following planning principles serve to


specifications and concepts prevent impairment of the safety and ease of
national and Alliance defence
- Emission mitigation
- Consideration of all existing and approved
- Economic area use
usages
- Bundling of subsea cable systems
- Dismantling of wind turbines, subsea
- Bundling of subsea cable systems in the cables and pipelines
sense of parallel routing
- Covering
- Careful installation
- Installation of sonar transponders
- Covering
With regard to other public and private
- Mitigation of sediment heating (compliance concerns, health and safety at work concerns
with 2 K criteria) are included in the draft via the planning
The following planning principles serve to principle of compliance with official standards;
prevent impairments to the safety and efficiency as are data cables and pipelines via the
of shipping: planning principle that involves taking existing
and approved uses into consideration.
- Overall chronological coordination of
installation works
- No negative impact on safety and efficiency
of shipping
- Dismantling of wind turbines, subsea
cables and pipelines
- Bundling of subsea cable systems in the
sense of parallel routing
- Ensuring that shipping traffic crosses
priority and reservation areas by the
shortest possible route
- Consideration of regulatory standards,
specifications and concepts
- Perpendicular crossing of shipping priority
and shipping reservation areas
- Preventing crossings; any crossings should
be as perpendicular as possible
- Accessibility of platforms with ships
- Careful installation
- Covering
As regards air traffic, a planning principle has
been introduced stating that the safety and
ease of air traffic must not be compromised.
Conformity of the rules with private and public concerns 51

Eastern German Bight" nature conservation


7.4 Admissibility of the rule of areas
area.
The rules of areas in the North Sea and Baltic
The Federal Maritime and Hydrographic
Sea were largely taken from the clusters
Agency has notices concerning usage conflicts,
already defined in the BFOs for the North Sea
which basically call into question a rule of
and Baltic Sea. As related issues have already
Cluster 5 of BFO-N 16/17 as area N-5.
been examined within the framework of the
In particular, considerations relating to
preparation and updating of the BFO,
conservation of wild birds as a public interest
re-examination according to section 5
could hinder a rule. Accordingly, the area will
subsection 3 sentence 3 WindSeeG is generally
not be designated for the time being, but is still
not required. Updating or consolidation of the
under review.
examination is probably not necessary beyond
the aspects described below, due to the last Furthermore, the rules of the areas are not
update which took place as recently as the end inadmissible according to section 5
of 2017. subsection 3 sentence 2 no. 5b WindSeeG,
according to which areas and sites must lie
The designated areas are in any case outside
within clusters 1 to 8 of the North Sea and
the priority and reservation areas for shipping
clusters 1 to 3 of the Baltic Sea as defined by
traffic and outside nature conservation areas.
the BFO. The rules of areas and sites in
With regard to military training areas, there are the North Sea and Baltic Sea were largely
overlaps with rules of areas in the draft. Thus taken from the clusters already defined in the
areas N-3, N-4, O-1, O-2 and large parts of O-3 BFOs for the North Sea and Baltic Sea. Area N-
are located within military training areas. As the 9 is located outside clusters 1 to 8 of the BFO
areas have already been defined as clusters for the North Sea, but it may be necessary to
with the BFO North Sea and Baltic Sea, and specify a site in area N-9 with site N-9.1
partly as priority areas for wind energy in the in order to safely achieve the expansion target
Spatial Plan for the North Sea, and no according to section 5 subsection 3 sentence 2
additional, other significant or new aspects are no. 5b last clause of the WindSeeG. The sites
discernible, admissibility according to section 5 in areas N-10, N-11 and N-12 listed in the
subsection 3 sentence 3 of the WindSeeG does annex for an enhanced development pathway
not need to be re-examined for the time being. are also outside clusters 1 to 8. However, these
For area N-4, there are indications of conflicts were initially presented for information purposes
of use, but these have not yet become more only, and would also be necessary in order to
acute to the extent that a threat to the marine achieve an enhanced expansion target in the
environment must be assumed at the planning event of a time-frame extending in part beyond
level (see chapters 4.6 and 5.2.2 of the 2030 in accordance with section 5 subsection 1
environmental report for the North Sea). of the WindSeeG.
The draft Site Development Plan does not Concerns have been expressed with regard to
define a zone in this site either. the rule of areas N-11 and N-13. The Federal
In area N-5, a zone for the existing "Butendiek" Ministry for the Environment, Nature
wind farm as the easternmost wind farm was Conservation and Nuclear Safety and the
not designated. A stipulation here would be Federal Agency for Nature Conservation
inadmissible according to section 5 subsection recently pointed out, in their statement in
3 sentence 2 no. 5a WindSeeG, as the site respect of the consultation on the preliminary
would be located in the "Sylt Outer Reef – draft of the Site Development Plan, that
52 Conformity of the rules with private and public concerns

clusters 13 and 11 are also very important for


7.5 Admissibility of the rule of sites
harbour porpoises (main concentration area for
harbour porpoises) and for seabirds and resting The specified sites are beyond the priority and
birds as resting and feeding habitats, as well as reservation areas for shipping traffic and
overwintering habitats. If absolutely necessary, outside nature conservation sites. Please see
however, clusters 9, 10 and only then cluster 12 chapter 7.4 with regard to the location of
should be developed first by offshore wind individual sites in military training areas.
farms (see the statement dated 25 June 2018 As regards site N-3.7, there are no overriding
by the Federal Ministry for the Environment, private concerns preventing rule by awarding a
Nature Conservation and Nuclear Safety and contract with location coordinates in a call for
the statement dated 14 June 2018 by the tenders for existing projects. If a contract is
Federal Agency for Nature Conservation). awarded only to the extent of the minimum or
As development of the areas in zone 3 may be secondary bid size, as a result only a smaller
necessary in order to implement the installed line will be used as a basis for the
development pathway, the comment was taken approval procedure for wind turbines, i.e. the
into account in the draft of the Site number of turbines and their locations will
Development Plan within the framework of the deviate from the original approval or
rules by initially defining a site for area N-9 only. application.13 Coordinates in the contract are
Accordingly, sites in areas N-9, N-10 and N-12 used only for clear local allocation of the wind
are initially presented for information purposes farm and to prevent the contract from being
in the annex for an enhanced development transferred to another project in another site,
path. Sites in area N-11 would probably only be and do not indicate a claim to the entire site.
designated for scenario B 2035 of the scenario Moreover, the principle of economic area use in
framework 2019-2030. No threat to the marine accordance with section 2 subsection 2 no. 6 of
environment is therefore assumed initially (see the Spatial Development Act (ROG) and the
the environmental report, chapters 4.5.1, 4.6.1, early use of vacant areas in accordance with
5.1.2, 5.2.2 and 6). section 5 subsection 4 sentence 2 no. 2
WindSeeG run counter to a corresponding use
Area O-3 in the eastern area was reduced to
of the site merely for the reduced capacity of
the site of the existing "Baltic 2" wind farm in
the partial contract. Rule of the site will continue
order to counter the threat to national and
after the consultation.
Alliance defence posed by military training
areas located in the east of area O-3. With regard to site N-5.4, it is currently being
examined whether considerations relating to the
[further elaboration will take place after the
conservation of wild birds would prevent a rule.
consultation]
In accordance with section 5 subsection 3
sentence 3 WindSeeG, sites currently located
in BFO clusters may also be checked for
inadmissibility in the event of necessary

13
BT-DrS. 18/9096 of 6 July 2016, Recommendation and
report of the Committee on Economic and Energy Affairs
(9th Committee) on the draft bill of the CDU/CSU and SPD
parliamentary groups – Journal 18/8860 – and on the draft
bill of the Federal Government – Journals 18/8832,
18/8972 – pp. 301, 302.
Conformity of the rules with private and public concerns 53

updates or in-depth examinations. In its bidding procedure. The background to this is


statement on the preliminary draft of the Site the location of cluster 5 in a region of particular
Development Plan dated 14 June 2018, the importance for divers and harbour porpoises.
Federal Agency for Nature Conservation The same was requested by the Federal
pointed out that it was necessary, for reasons Agency for Nature Conservation in the context
relating to the conservation of wild birds, not to of the O-NDP 2017-2030 consultation (cf.
develop the site. Accompanying observations Federal Agency for Nature Conservation
had shown that the wind farm areas were statement dated 22 February 2017, which is
practically prevented entirely and that densities also an annex to Federal Agency for Nature
of divers (loons) in areas around wind farms Conservation statement on BFO-N 16/17 dated
were statistically significantly lower up to 26 July 2017). The problem with regard to the
distances of approx. 10 km. This had been main distribution area for divers was already
confirmed by various surveys. Following a described in BFO-N 2016/17, and also in
comparative analysis, the prevention radius has BFO-N 2013/14 (see also chapters 4.6.1,
shifted from a 2 km interference radius to 4.12.4, 5.2.2.1 and 6.3.3.2 in the environmental
5.5 km. It can therefore be assumed that habitat report).
loss due to development of the site is greater
With regard to site O-1.3, concerns were
than previously assumed. The "Nördlicher
expressed by the Directorate-General for
Grund" wind farm would probably not be eligible
Waterways and Shipping in its statement
for approval according to regulations relating to
regarding possible hazards to shipping traffic.
wildlife conservation. The statement of the
These can be clarified by means of a risk
Federal Agency for Nature Conservation dated
analysis as well as a nautical traffic and
24 November 2014 in the context of the
maritime police investigation, as evidenced by
updating of BFO-N 13/14 (on the sensitivity
the statement on further investigations.
report for the O-NDP in this respect) also points
This may be presented and evaluated within the
out that, from standpoint of nature conservation,
context of the suitability examination.
the "SylWin2" and "SylWin beta" connection
should be postponed to after 2024 due to the The rule of site O-2.2 is still under
location of the cluster in the main concentration consideration. Concerns relating to
area for harbour porpoises and the main endangerment of shipping traffic and the marine
concentration area for divers. Furthermore, the environment due to bird migration form
Federal Agency for Nature Conservation a background to this. Moreover, there are
pointed out in this statement that from the point indications of difficulties with regard to the
of view of the Agency, and in order to comply expected actual development potential (see
with the legal framework conditions, the main chapter 5.2.2 and chapters 4.12.5 and 5.2.2.1
concentration area for divers poses an obstacle in the environmental report for the Baltic Sea).
to the approval of offshore wind farms planned [further elaboration will take place after
for this region but not yet approved. As part of the consultation]
the update of BFO-N 16/17, the Federal Agency
for Nature Conservation demanded (cf. Federal 7.6 Admissibility of other rules
Agency for Nature Conservation statement
The locations of platforms, routes and route
dated 26 July 2017) that the NOR-5-2
corridors for offshore connecting lines, as well
connecting line should be removed if no
as for cross-border power lines, for possible
contract were awarded for a wind farm in
connections between or among the turbines,
cluster 5 during the transitional phase of the
locations where the connecting lines cross the
54 Conformity of the rules with private and public concerns

boundary between the EEZ and coastal waters, the covering and mitigation of sediment
and standardised technical and planning warming, reduce the effects, it is not assumed
principles are also examined with regard to that the marine environment is endangered.
whether they are admissible under section 5
Two cross-border cables cross the "Dogger
subsection 3 sentence 2 WindSeeG.
Bank" nature conservation area from gate N-XII
According to the Federal Agency for Nature to gate N-XV, and from gate N-XIII to N-III.
Conservation, the grid connections passing In the Baltic Sea, cross-border cables run from
through gate N-II run across a sandbank that is gate O-XIV to gate O-XIII through the
a legally protected biotope according to section "Pomeranian Bight – Rönnebank" nature
30 of the Federal Nature Conservation Act. This conservation area, and from gate O-V to gate
does not significantly effect the biotope. O-VI through the "Fehmarn Belt" nature
Available grid connection capacities for pilot conservation area. The Strategic Environmental
offshore wind turbines exist in area N-2. Assessment has shown that this is unlikely to
According to the Federal Agency for Nature have a significant impact on the environment
Conservation, the southern part of area N-2 is (see chapter 6.5.1 of the environmental reports
also located on the sandbank. The rule of for the North Sea and Baltic Sea).
available grid connection capacities is not a
[further elaboration will take place after the
subject of the inadmissibility test according to
consultation]
the list in section 5 subsection 3 sentence 1
WindSeeG. Apart from that, however, the rule
would not significantly effect the biotope (see
chapter 6.5.1 of the environmental report).
Exactly if and where the installation and
operation of pilot offshore wind turbines will be
permitted shall be solely decided by the
authorisation procedure for pilot offshore wind
turbines, which will take place at a later stage 14.
The connection system NOR-7-2 runs through
the "Sylt Outer Reef – Eastern German Bight"
nature conservation area. Some crossing
structures are connected to this. This route is
based on the need for crossing the remaining
cables in the EEZ that pass through gate N-V.
As the spatial use of the nature conservation
area is very low, there are no known legally
protected biotopes and the planning principles
of the least intrusive laying procedure,

14
BT-DrS. 18/9096 of 6 July 2016, Recommendation and
report of the Committee on Economic and Energy Affairs
(9th Committee) on the draft bill of the CDU/CSU and SPD
parliamentary groups – Journal 18/8860 – and on the draft
bill of the Federal Government – Journals 18/8832,
18/8972 – pp. 373
Summary consideration 55

8 Summary consideration
[elaboration will take place after the
consultation]
56 Summary environmental statement

9 Summary environmental
statement
[elaboration will take place after the
consultation]
Appendices: maps (for information) 57

10 Appendices: maps (for information)

Figure 23: Shipping routes in the North Sea EEZ Spatial Plan

Figure 24: Shipping routes in the Baltic Sea EEZ Spatial Plan
58 Appendices: maps (for information)

Figure 25: Designations: subsea cables, pipelines, traffic separation areas (North Sea)

Figure 26: Designations: subsea cables, pipelines, traffic separation areas (Baltic Sea)
Appendices: maps (for information) 59

Figure 27: National defence territories (North Sea)

Figure 28: National defence territories (Baltic Sea)


60 Appendices: maps (for information)

Figure 29: Areas for the construction and operation of offshore wind turbines in the German North Sea EEZ and nature conservation
areas.

Figure 30: Areas for the construction and operation of offshore wind turbines in the German Baltic Sea EEZ and nature conservation
areas
Bibliography 61

11 Bibliography
Borrmann, R., Rehfeldt, D. K., Wallasch, A.-K., & Lüers, S. (2018). Approaches and standards for
the determination of the capacity density of offshore wind farms. Downloaded from
http://vasab.org/wp-
content/uploads/2018/06/BalticLINes_CapacityDensityStudy_June2018-2.pdf
Borsche, M., Kaiser-Weiss, A. K., & Kaspar, F. (2016). Wind speed variability between 10m and
116m height from global and regional re-analyses compared to wind mast measurements
over Northern Germany and The Netherlands. Adv. Sci. Res.(13), pp. 151-161.
Federal Ministry for the Environment, Nature Conservation and Nuclear Safety (2009). Position
paper from the business sector of the Federal Environmental Ministry on cumulative
evaluation of diver habitat loss due to offshore wind farms in the German EEZ of the North
Sea and Baltic Sea as a basis for an agreement of the BfN with the BSH. Downloaded from
https://www.bfn.de/fileadmin/BfN/awz/Dokumente/seetaucher_positionspapier_bf.pdf
Federal Ministry for the Environment, Nature Conservation and Nuclear Safety (2013). Concept for
protection of harbour porpoises from noise exposure during construction of offshore wind
farms in the German North Sea (noise protection concept). Downloaded from
https://www.bfn.de/fileadmin/BfN/awz/Dokumente/schallschutzkonzept_BMU.pdf
Danish Energy Agency (2017). Master data register for wind turbines at end of December 2017.
Downloaded from https://ens.dk/en/our-services/statistics-data-key-figures-and-energy-
maps/overview-energy-sector
DNV KEMA (2012). Study on minimum distances between subsea cables. On behalf of the
Offshore Wind Energy Institute.
Ehlers, P. (2016). Comment on the Marine Responsibilities Act (section 1). Baden-Baden: Nomos.
ENTSO-E AISBL (2018). European Power System 2040, Completing the map, The Ten-Year
Network Development Plan 2018 System Needs Analysis. Brussels.
Hirth, L., & Müller, S. (2016). System-friendly wind power – How advanced wind turbine design can
increase the economic value of electricity generated through wind power. Energy
Economics 56.
ICPC (November 2015). ICPC Recommendation #2, Recommended Routing and Reporting
Criteria for Cables in Proximity to Others.
Klinski, S. (2001). Legal problems of allowing wind turbines in the exclusive economic zone. Berlin:
German Federal Environment Agency.
Knorr, K., Horst, D., Bofinger, S., & Hochloff, P. (2017). Economic significance of offshore wind
energy for the energy crisis. Varel: Fraunhofer Institute for Wind Energy and Energy
System Technology.
Leiding, T., Tinz, B., Gates, L., Rosenhagen, G., Herklotz, K., Senet, C., et al. (2016).
Standardisation and comparative analysis of meteorological FINO measurement data
(FINO123). Final report of BMWi Research Project FINO-Wind.
62 Bibliography

Luger, D. &. (2013). Anchor Test German Bight. Test set-up and results. Deltares on behalf of
TenneT Offshore GmbH.
Maushake, C. L.-H. (2013). : Study of penetration behaviour of ship's anchors by means of anchor
traction tests. Report on the survey of anchor penetration depth. Federal Waterways
Engineering and Research Institute on behalf of the Directorate-General for Waterways and
Shipping – North-west Office.
Platis, A., Siedersleben, S. K., Bange, J., Lampert, A., Bärfuss, K., Hankers, R., et al. (1 February
2018). First in-situ evidence of wakes in the far field behind offshore wind farms. Nature
Scientific Reports.
Annex: Informational illustration of an increased development path (scenario framework 2019- 63
2030)

12 Annex: Informational connection points, it appears to be necessary,


for implementation of the scenarios, for more
illustration of an increased than one offshore connecting line per year to be
development path implemented per TSO. Further examination
would be necessary here.
(scenario framework 2019-
A further challenge could be presented by the
2030) availability of grid connection points,
The scenario framework 2019-2030 approved network expansion on land and routing
by the Federal Network Agency on 15 June through coastal waters.
2018 contains, on the basis of the coalition These challenges would have to be
agreement of 12 March 2018, a development of overcome in order to implement the
the expansion of offshore wind energy that scenarios.
deviates from the objectives of the Renewable
Reference is made to the preparation,
Energy Sources Act and thus from the legal
assessment and confirmation of the network
requirements of the Site Development Plan. In
development plan 2019-2030.
statements on the preliminary draft of the Site
Development Plan, with reference to the
scenario framework 2019-2030, it was required
that the Site Development Plan should
demonstrate a corresponding scenario even
before legal modification. In order to meet this
requirement, the individual scenarios of the
scenario framework 2019-2030, with possible
definitions for each scenario, are presented
here for information purposes only.
In principle, if the expansion target is increased
by 2030, bringing a higher output per year to
tender than with the implementation of 15 GW
by 2030 (base case) presents a challenge. For
this reason, besides increasing the target from
15 GW by 2030 in accordance with section 4
subsection 2 no. 1 WindSeeG in connection
with section 4 no. 2 b of the Renewable Energy
Sources Act, a legal modification of the
annual expansion corridor from 700 MW to 900
MW and an average of 840 MW according to
section 5 subsection 5 WindSeeG would also
be required.
There is also the challenge of completing grid
connection systems on time. According to
current information, a transmission system
operator can implement one offshore
connecting line per year. On the basis of the
information currently available on grid
64 Annex: Informational illustration of an increased development path (scenario framework 2019-2030)

12.1 Scenarios B 2030 and C 2030


(17 GW by 2030)

Figure 31: Informational figure of possible rules according to scenarios B and C 2030 (17 GW by 2030) and challenges to be overcome
Annex: Informational illustration of an increased development path (scenario framework 2019- 65
2030)

12.2 Scenario A 2030


(20 GW by 2030)

Figure 32: Informational figure of possible rules according to scenario A 2030 (20 GW by 2030) and challenges to be overcome
66 Annex: Informational illustration of an increased development path (scenario framework 2019-2030)

12.3 Scenario B 2035


(23.2 GW by 2035)

Figure 33: Informational figure of possible rules according to scenario B 2035 (23.2 GW by 2035) and challenges to be overcome
Annex: Informational illustration of an increased development path (scenario framework 2019- 67
2030)

12.4 Connecting lines that may be required for the scenarios

Table 16: Overview of the commissioning years which may be necessary for the offshore connecting lines in the various scenarios
Designation Possibly necessary calendar year of commissioning
for offshore connecting lines
Basis Scenarios B and C Scenario A 2030 Scenario B 2035
(15 GW) 2030 (17 GW) (20 GW) (23.2 GW)
OST-1-4 2026 2026 2026 2026
NOR-7-2 2027 2027 2027 2027
NOR-3-2 2028 2028 2027 2028
1) 1) 1) 1) 1)
OST-7-1 2029 2027 2027 2027
NOR-6-3 2029 2029 2028 2029
NOR-9-1 2030 2029 2028 2029
NOR-9-2 - 2030 2029 2030
NOR-10-2 - 2030 2029 2030
NOR-10-1 - - 2030 2031
NOR-12-1 - - 2030 2032
NOR-12-2 - - 2030 2033
NOR-11-1 - - - 2034
NOR-11-2 - - - 2035

1)
The prerequisite is, amongst others, the conclusion of an administrative agreement between Mecklenburg-Western
Pomerania and the Federal Maritime and Hydrographic Agency. Please see section 11 subsection 1 WindSeeG.

You might also like